20541 W SHELLEY LANE 91326

Certificate Information: 20541 W SHELLEY LANE 91326

Application / Permit
18010-20000-01550
Plan Check / Job No.
B18VN06061
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(TRACT 50509-01) TWO STORY SFD WITH ATTACH 3 CAR GARAGE_ STANDARD PLAN # 648 _ PLAN 4A
Permit Issued
Issued on 7/18/2018
Issuing Office
Valley
Current Status
CofO Corrected on 11/14/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2018 APPLICANT
Green Plans Picked Up 4/25/2018 APPLICANT
Assigned to Plan Check Engineer 5/3/2018 DAWN MC NULTY
Corrections Issued 5/7/2018 DAWN MC NULTY
Quality Review Completed 5/18/2018 STEVEN KIM
Building Plans Picked Up 5/21/2018 APPLICANT
Plan Check Approved 7/18/2018 DAWN MC NULTY
Issued 7/18/2018 LADBS
CofO in Progress 7/17/2019 BRUCE ROZAK
CofO Issued-Status Void 7/18/2019 DONALD SUNSERI
Permit Finaled-Status Void 7/18/2019 DONALD SUNSERI
Re-Activate Permit 10/16/2019 MICHAEL SMITH
CofO Corrected 11/14/2020 DONALD SUNSERI
Permit Finaled 11/14/2020 DONALD SUNSERI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/31/2018 KENNETH PHAM
Permit Cleared 5/31/2018 KENNETH PHAM
Roof/Waste drainage to street Cleared 5/31/2018 KENNETH PHAM
Sewer availability Cleared 5/31/2018 KENNETH PHAM
Hydrant and Access approval Cleared 6/19/2018 ROBERT DUFF
"T" removal Cleared 6/25/2018 STEVEN WECHSLER
CPC Cleared 6/25/2018 STEVEN WECHSLER
Miscellaneous Cleared 6/25/2018 STEVEN WECHSLER
Miscellaneous Cleared 6/25/2018 STEVEN WECHSLER
Miscellaneous Cleared 6/25/2018 STEVEN WECHSLER
Miscellaneous Cleared 6/25/2018 STEVEN WECHSLER
Specific Plan Cleared 6/25/2018 STEVEN WECHSLER
Tract Map conditions Cleared 6/25/2018 STEVEN WECHSLER
Tract Map conditions Cleared 6/25/2018 STEVEN WECHSLER
ZA Case Cleared 6/25/2018 STEVEN WECHSLER
ZA Case Cleared 6/25/2018 STEVEN WECHSLER
Low Impact Development Cleared 6/27/2018 AMMAR ELTAWIL
Address approval Cleared 7/18/2018 LEE GUILBEAUX
Green Code Cleared 7/18/2018 DAWN MC NULTY

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 250 GIBRALTAR RD   ATTN: GATES/LEGAL    HORSHAM, PA 19044
Engineer Miller, Karen Lynn; Lic. No.: GE2257 5364 DORIS WY      TORRANCE, CA 90505
Engineer Wong, Ramon Roman Ii; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/11/2018 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 10/4/2018 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 11/16/2018 Partial Approval BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 1/23/2019 Partial Approval BRUCE ROZAK
Sewer 1/29/2019 Approved BRUCE ROZAK
Underground Mechanical 2/11/2019 Not Ready for Inspection BRUCE ROZAK
Underground Mechanical 2/13/2019 Approved BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 2/26/2019 Not Ready for Inspection BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 2/27/2019 Not Ready for Inspection BRUCE ROZAK
Floor/Roof Diaphrgm/Shear Wall 3/1/2019 Partial Approval DONALD SUNSERI
BUILDING-Rough-Frame 3/6/2019 Approved BRUCE ROZAK
ELECTRICAL-Rough 3/6/2019 Approved BRUCE ROZAK
Green Building Rough 3/6/2019 Approved BRUCE ROZAK
HVAC-Rough 3/6/2019 Approved BRUCE ROZAK
PLUMBING-Rough 3/6/2019 Approved BRUCE ROZAK
Verify Sprinkler Sign Off 3/6/2019 Approved BRUCE ROZAK
Drywall Nailing 3/21/2019 Approved BRUCE ROZAK
Interior/Exterior Lathing 3/21/2019 Not Ready for Inspection BRUCE ROZAK
Interior/Exterior Lathing 4/29/2019 Approved BRUCE ROZAK
Gas Test 4/30/2019 Approved BRUCE ROZAK
SGSOV-Seismic Gas S/O Valve 6/6/2019 SGSOV Approved BRUCE ROZAK
Service/Power Release 6/6/2019 Approved BRUCE ROZAK
ELECTRICAL-Final 7/16/2019 Approved BRUCE ROZAK
Final 7/16/2019 OK to Issue CofO BRUCE ROZAK
Green Building Final 7/16/2019 Approved BRUCE ROZAK
HVAC-Final 7/16/2019 Approved BRUCE ROZAK
PLUMBING-Final 7/16/2019 Approved BRUCE ROZAK
Smoke Detectors 7/16/2019 Approved BRUCE ROZAK