704 N LUCILE AVE LOT 1-PARCEL A 90026

Certificate Information: 704 N LUCILE AVE LOT 1-PARCEL A 90026

Application / Permit
18010-20000-01540
Plan Check / Job No.
B18VN06046
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 35'-6" x 31' Three Story irr. shape Single Family Dwelling with attached 2-Car Garage per Small Lot Subdivision pursuant to Preliminary Parcel Map No. AA-2018-2484-PMLA-SL. Certificate of Occupancy (temporary or final) shall not be issued until after the final map has been recorded.
Permit Issued
Issued on 6/18/2022
Issuing Office
Current Status
Issued on 6/18/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/11/2018 APPLICANT
Green Plans Picked Up 5/4/2018 APPLICANT
Assigned to Plan Check Engineer 5/17/2018 OMID HEDAYAT
Corrections Issued 5/24/2018 OMID HEDAYAT
Quality Review Completed 5/30/2018 CHON CHIO KUO
Building Plans Picked Up 6/1/2018 APPLICANT
Applicant returned to address corrections 4/29/2019 OMID HEDAYAT
Applicant returned to address corrections 11/15/2019 OMID HEDAYAT
Applicant returned to address corrections 4/9/2021 OMID HEDAYAT
Applicant returned to address corrections 11/2/2021 OMID HEDAYAT
Applicant returned to address corrections 3/11/2022 OMID HEDAYAT
Plan Check Approved 3/24/2022 OMID HEDAYAT
Issued 6/18/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/5/2018 KAYLA PEJI
Hydrant and Access approval Cleared 8/27/2018 JOHN DALLAS
ZI Cleared 8/27/2018 ANNA VIDAL
Sewer availability Cleared 8/29/2018 LEE GUILBEAUX
Green Code Cleared 10/11/2019 MICHAEL AYERS
Address approval Cleared 4/1/2021 CELINA MORENO
Permit Cleared 4/1/2021 CELINA MORENO
Highway dedication Cleared 5/6/2021 CELINA MORENO
Low Impact Development Cleared 6/18/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/23/2021 CELINA MORENO
Miscellaneous Cleared 10/19/2021 TERRY PHAN
Frnt yard landscape/Water mgmt Cleared 1/21/2022 RICHARD REASER
Miscellaneous Cleared 1/21/2022 RICHARD REASER
Miscellaneous Cleared 1/21/2022 RICHARD REASER
Miscellaneous Cleared 1/21/2022 RICHARD REASER
Miscellaneous Cleared 1/21/2022 RICHARD REASER
GPI Written Notices Cleared 3/24/2022 OMID HEDAYAT
Grading Pre-Inspection Cleared 3/24/2022 OMID HEDAYAT

Contact Information

Contractor Stangby Noah; Lic. No.: 1086678-B 2205 ESPERANZA      IRVINE, CA 92618
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107
Engineer Nazari, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327
Geologist Irvine, Jon A; Lic. No.: EG1691 1150 ENCANTO DR      ARCADIA, CA 91007

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/10/2022 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 8/10/2022 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/6/2022 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 9/7/2022 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 9/13/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/13/2022 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 9/14/2022 Partial Approval ALEJANDRO DE ARTOLA
Deputy Other (see comments) 9/19/2022 Approved ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 9/19/2022 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/19/2022 Partial Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 9/21/2022 Conditional Approval ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 10/26/2022 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/26/2022 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 10/28/2022 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 10/31/2022 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 11/1/2022 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 11/22/2022 Conditional Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 11/29/2022 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/9/2022 Partial Approval SCOTT FINNILA
Deputy Wood Construction 12/13/2022 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 12/23/2022 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/4/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Partial Approval ALEJANDRO DE ARTOLA
Wood Frame 1/18/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 1/19/2023 Approved ALEJANDRO DE ARTOLA
Masonry Wall/Backfill 1/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 2/1/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 2/17/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/13/2023 Corrections Issued ALEJANDRO DE ARTOLA
Shower Pan 3/13/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 3/17/2023 Conditional Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 3/17/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 3/17/2023 Approved ALIZAH MAYAGOITIA
Deputy Wood Construction 3/30/2023 Conditional Approval ALEJANDRO DE ARTOLA
HVAC-Rough 3/30/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/3/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/6/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 4/12/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/12/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/19/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 4/19/2023 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/27/2023 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 4/27/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/3/2023 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 5/3/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/5/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Wood Construction 5/9/2023 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/18/2023 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 5/18/2023 Approved ALIZAH MAYAGOITIA
Green Building Rough 5/18/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/18/2023 Partial Approval ALIZAH MAYAGOITIA
Insulation 5/24/2023 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 6/1/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/22/2025 Not Ready for Inspection NICHOLAS LOPEZ
Gas Test 1/22/2025 Not Ready for Inspection NICHOLAS LOPEZ
Green Building Final 1/22/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 1/22/2025 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Final 1/22/2025 Not Ready for Inspection NICHOLAS LOPEZ
Pre-Inspection 1/22/2025 Partial Approval NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 1/22/2025 SGSOV Not Ready NICHOLAS LOPEZ
Service/Power Release 1/22/2025 Not Ready for Inspection NICHOLAS LOPEZ
Smoke Detectors 1/22/2025 Not Ready for Inspection NICHOLAS LOPEZ
Verify Rec and Parks Fee Memo 1/22/2025 Approved NICHOLAS LOPEZ
Special/Order Compliance 2/25/2025 Corrections Issued NICHOLAS LOPEZ
Special/Order Compliance 6/24/2025 Corrections Issued BRENDAN MORELLI