3443 W PERLITA AVE 90039

Certificate Information: 3443 W PERLITA AVE 90039

Application / Permit
18010-20000-01361
Plan Check / Job No.
B18VN05168
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSE 16' X 28'-4" ONE STORY ACCESSORY DWELLING UNIT (PER AB 494 & SB 229) WITH ATTACHED STORAGE ACCESS FROM OUTSIDE ONLY & PROVIDE 3 OPEN PARKING STALLS
Permit Issued
Issued on 3/6/2019
Issuing Office
Metro
Current Status
CofO Issued on 1/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2018 APPLICANT
Assigned to Plan Check Engineer 4/5/2018 DAWN MC NULTY
Green Plans Picked Up 4/6/2018 APPLICANT
Corrections Issued 4/9/2018 DAWN MC NULTY
Quality Review Completed 4/10/2018 CHON CHIO KUO
Building Plans Picked Up 4/11/2018 APPLICANT
Applicant returned to address corrections 6/21/2018 DAWN MC NULTY
Applicant returned to address corrections 11/9/2018 DAWN MC NULTY
Applicant returned to address corrections 1/10/2019 DAWN MC NULTY
Plan Check Approved 1/15/2019 DAWN MC NULTY
Issued 3/6/2019 LADBS
CofO in Progress 4/9/2020 HAMIK HARTOUNIAN
Permit Finaled 1/6/2022 DEROLD HAUFF
CofO Issued 1/6/2022 DEROLD HAUFF
Permit Finaled 1/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 6/13/2018 PARISA ZAHABI
Address approval Cleared 12/6/2018 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 12/6/2018 MARKOS PEREZ-BRAN
Permit Cleared 12/6/2018 MARKOS PEREZ-BRAN
Sewer availability Cleared 12/6/2018 MARKOS PEREZ-BRAN
Low Impact Development Cleared 12/14/2018 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/14/2018 ZIXUAN CHEN
ZI Cleared 1/15/2019 RINA LARA
Hydrant and Access approval Cleared 1/22/2019 JOHN DALLAS

Contact Information

Contractor Williams Christopher; Lic. No.: 711380-B P O BOX 8652      LA CRESCENTA, CA 91224
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/6/2019 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/14/2019 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/20/2019 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 5/31/2019 Corrections Issued PIERRE VEGA
Footing/Foundation/Slab 8/9/2019 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/14/2019 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/4/2019 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/7/2019 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/7/2019 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/7/2019 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 10/7/2019 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/7/2019 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 10/7/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 10/7/2019 Partial Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/17/2019 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/17/2019 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/17/2019 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 10/17/2019 Conditional Approval HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 10/17/2019 Approved HAMIK HARTOUNIAN
Insulation 10/22/2019 Approved PIERRE VEGA
Drywall Nailing 10/30/2019 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 10/30/2019 Approved HAMIK HARTOUNIAN
Final 2/6/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 2/6/2020 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/6/2020 SGSOV No Gas HAMIK HARTOUNIAN
Service/Power Release 2/6/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 2/6/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Final 3/11/2020 No Access for Inspection HAMIK HARTOUNIAN
Green Building Final 3/11/2020 No Access for Inspection HAMIK HARTOUNIAN
Service/Power Release 3/11/2020 No Access for Inspection HAMIK HARTOUNIAN
Smoke Detectors 3/11/2020 No Access for Inspection HAMIK HARTOUNIAN
Final 3/20/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 3/20/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 3/20/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 4/8/2020 Approved HAMIK HARTOUNIAN
Final 4/8/2020 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 4/8/2020 Approved HAMIK HARTOUNIAN
HVAC-Final 4/8/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Final 4/8/2020 Approved HAMIK HARTOUNIAN