11249 W HATTERAS ST 91601

Certificate Information: 11249 W HATTERAS ST 91601

Application / Permit
18010-20000-01305
Plan Check / Job No.
B18VN04998
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD/GARAGE
Permit Issued
Issued on 1/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2018 APPLICANT
Assigned to Plan Check Engineer 3/29/2018 VLADIMIR ARUTYUNYAN
Green Plans Picked Up 4/3/2018 APPLICANT
Corrections Issued 4/6/2018 VLADIMIR ARUTYUNYAN
Quality Review Completed 4/11/2018 STEVEN KIM
Building Plans Picked Up 4/11/2018 APPLICANT
Plan Check Approved 5/17/2019 VLADIMIR ARUTYUNYAN
Issued 1/24/2020 LADBS
CofO in Progress 12/7/2020 DANIEL ORRANTE
CofO Issued 12/8/2020 MICHAEL SMITH
Permit Finaled 12/8/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/4/2018 STEVE MELGAR
Project located in CRA area Cleared 6/26/2018 JIM URQUHART
Hydrant and Access approval Cleared 3/8/2019 JOHN DALLAS
Green Code Cleared 3/22/2019 DAVID MATSON
Low Impact Development Cleared 4/1/2019 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 4/30/2019 JOSHUA DIAZ
Highway dedication Cleared 4/30/2019 APEKSHYA BAJRACHARYA
Permit Cleared 4/30/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 4/30/2019 JOSHUA DIAZ
Sewer availability Cleared 4/30/2019 JOSHUA DIAZ

Contact Information

Contractor Ender Enterprises; Lic. No.: 962814-B 9903 SANTA MONICA BLVD #747      BEVERLY HILLS, CA 90212
Engineer Phan, Phillip Trung Tri; Lic. No.: C76425 19221 E NORTHAM      WEST COVINA, CA 91792

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/12/2020 Approved RAYMOND KEHOE
Footing/Foundation/Slab 2/21/2020 Approved RAYMOND KEHOE
Underground Mechanical 2/21/2020 Approved RAYMOND KEHOE
Deputy Wood Construction 3/19/2020 Approved RAYMOND KEHOE
Deputy Wood Construction 4/9/2020 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 4/9/2020 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 4/16/2020 Partial Approval RAYMOND KEHOE
HVAC-Rough 4/24/2020 Approved RAYMOND KEHOE
PLUMBING-Rough 4/24/2020 Approved RAYMOND KEHOE
BUILDING-Rough-Frame 4/30/2020 Not Ready for Inspection RAYMOND KEHOE
ELECTRICAL-Rough 4/30/2020 Approved RAYMOND KEHOE
Green Building Rough 4/30/2020 Not Ready for Inspection RAYMOND KEHOE
Interior/Exterior Lathing 4/30/2020 Not Ready for Inspection RAYMOND KEHOE
Shower Pan 4/30/2020 Approved RAYMOND KEHOE
Verify Sprinkler Sign Off 4/30/2020 Not Ready for Inspection RAYMOND KEHOE
BUILDING-Rough-Frame 5/6/2020 Approved RAYMOND KEHOE
Green Building Rough 5/6/2020 Approved RAYMOND KEHOE
Verify Sprinkler Sign Off 5/6/2020 Approved RAYMOND KEHOE
Wood Frame 5/6/2020 Approved RAYMOND KEHOE
Drywall Nailing 5/18/2020 Approved RAYMOND KEHOE
Insulation 5/18/2020 Approved RAYMOND KEHOE
Interior/Exterior Lathing 5/18/2020 Approved RAYMOND KEHOE
Sewer 6/19/2020 Approved DANIEL DREW
Underground Mechanical 6/25/2020 Approved RAYMOND KEHOE
Final 7/21/2020 Not Ready for Inspection RAYMOND KEHOE
Green Building Final 7/21/2020 Approved RAYMOND KEHOE
SGSOV-Seismic Gas S/O Valve 7/21/2020 SGSOV Approved RAYMOND KEHOE
Service/Power Release 7/21/2020 Approved RAYMOND KEHOE
Smoke Detectors 7/21/2020 Approved RAYMOND KEHOE
Final 7/30/2020 Not Ready for Inspection RAYMOND KEHOE
Final 12/7/2020 OK to Issue CofO DANIEL ORRANTE