3863 W MONT CLAIR ST Unit 1-4 90018
Certificate Information: 3863 W MONT CLAIR ST Unit 1-4 90018
- Application / Permit
- 18010-20000-01155
- Plan Check / Job No.
- B18VN04363
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 2 STORY APARTMENT WITH 4 UNITS OVER ON-GRADE PARKING GARAGE, TOTAL OF 3-STORY BLDG.
- Permit Issued
- Issued on 11/7/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2018 | APPLICANT |
| Green Plans Picked Up | 4/9/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2018 | ABDUL CHEGENI |
| Disabled Access Plans Picked Up | 4/25/2018 | APPLICANT |
| Corrections Issued | 5/2/2018 | ABDUL CHEGENI |
| Quality Review Completed | 5/10/2018 | STEVEN KIM |
| Building Plans Picked Up | 5/11/2018 | APPLICANT |
| Applicant returned to address corrections | 7/5/2018 | ABDUL CHEGENI |
| Applicant returned to address corrections | 10/11/2018 | ABDUL CHEGENI |
| Plan Check Approved | 11/1/2018 | ABDUL CHEGENI |
| Issued | 11/7/2018 | LADBS |
| CofO in Progress | 1/29/2021 | LARRY ARNICK |
| Permit Finaled | 3/10/2021 | DAVID TSAU |
| CofO Issued | 3/10/2021 | DAVID TSAU |
| Permit Finaled | 3/10/2021 | DAVID TSAU |
Permit Application Clearance Information
| ZI | Cleared | 5/24/2018 | ANNA VIDAL |
| Frnt yard landscape/Water mgmt | Cleared | 5/25/2018 | RINA LARA |
| Address approval | Cleared | 6/4/2018 | CARLA VALLADARES |
| Hydrant and Access approval | Cleared | 6/4/2018 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 6/4/2018 | MITESH PATEL |
| Permit | Cleared | 6/4/2018 | CARLA VALLADARES |
| Roof/Waste drainage to street | Cleared | 6/4/2018 | CARLA VALLADARES |
| Green Code | Cleared | 6/5/2018 | PARISA ZAHABI |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2018 | LEE GUILBEAUX |
| Highway dedication | Cleared | 6/27/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/27/2018 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 6/29/2018 | OLLIE CARTER |
| Fire Marshall Fire Life Safety | Cleared | 9/21/2018 | OSCAR SALGADO JR |
| Miscellaneous | Cleared | 10/11/2018 | ABDUL CHEGENI |
Contact Information
| Contractor | Gregg M Kent; Lic. No.: 805393-B | 210 W BENNETT AVENUE GLENDORA, CA 91741 |
| Engineer | Eden, Joseph Taki; Lic. No.: C39955 | 14416 FRIAR ST STE A VAN NUYS, CA 91401 |
| Engineer | Jones, Ryan Keith; Lic. No.: GE2852 | 1253 W MASLINE ST COVINA, CA 91722 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/19/2018 | Partial Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 1/7/2019 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Barrier | 1/7/2019 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Subgrade | 1/7/2019 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 1/9/2019 | Partial Approval | LARRY ARNICK |
| METHANE-Barrier | 1/9/2019 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Subgrade | 1/9/2019 | Not Ready for Inspection | LARRY ARNICK |
| Deputy Reinf. Concrete | 1/30/2019 | Conditional Approval | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 1/30/2019 | Partial Approval | LARRY ARNICK |
| Footing/Foundation/Slab | 1/30/2019 | Partial Approval | LARRY ARNICK |
| METHANE-Barrier | 1/30/2019 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Subgrade | 1/30/2019 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 2/12/2019 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Barrier | 2/12/2019 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Subgrade | 2/12/2019 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 2/19/2019 | Partial Approval | LARRY ARNICK |
| METHANE-Barrier | 2/19/2019 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Subgrade | 2/19/2019 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 2/21/2019 | Not Ready for Inspection | LARRY ARNICK |
| Green Building Rough | 2/21/2019 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Barrier | 2/21/2019 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Rough | 2/21/2019 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Subgrade | 2/21/2019 | Not Ready for Inspection | LARRY ARNICK |
| Reinforced Masonry Frame | 2/21/2019 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 2/21/2019 | Not Ready for Inspection | LARRY ARNICK |
| Reinforced Concrete Frame | 2/22/2019 | Partial Approval | JAMES POWERS |
| Reinforced Concrete Frame | 2/25/2019 | Not Ready for Inspection | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2019 | Partial Approval | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2019 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2019 | Approved | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2019 | Approved | LARRY ARNICK |
| Insulation | 10/24/2019 | Partial Approval | JOEY BUCHANAN |
| Green Building Rough | 10/29/2019 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Rough | 10/29/2019 | Approved | LARRY ARNICK |
| Verify Sprinkler Sign Off | 10/29/2019 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 10/29/2019 | Not Ready for Inspection | LARRY ARNICK |
| Special/Order Compliance | 11/8/2019 | Partial Inspection | LARRY ARNICK |
| Insulation | 1/7/2020 | Not Ready for Inspection | LARRY ARNICK |
| Drywall Nailing | 3/31/2020 | Not Ready for Inspection | LARRY ARNICK |
| Green Building Rough | 3/31/2020 | Approved | LARRY ARNICK |
| Insulation | 3/31/2020 | Approved | LARRY ARNICK |
| Interior/Exterior Lathing | 3/31/2020 | Partial Approval | LARRY ARNICK |
| Verify Sprinkler Sign Off | 3/31/2020 | Approved | LARRY ARNICK |
| Wood Frame | 3/31/2020 | Approved | LARRY ARNICK |
| Drywall Nailing | 4/8/2020 | No Access for Inspection | LARRY ARNICK |
| Insulation | 4/9/2020 | Partial Approval | LARRY ARNICK |
| Drywall Nailing | 4/13/2020 | Approved | LARRY ARNICK |
| Interior/Exterior Lathing | 4/28/2020 | Partial Approval | LARRY ARNICK |
| Verify Rec and Parks Fee Memo | 10/7/2020 | Partial Inspection | LARRY ARNICK |
| Final | 11/10/2020 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 11/10/2020 | Approved | LARRY ARNICK |
| Green Building Final | 11/10/2020 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Barrier | 11/10/2020 | Approved | LARRY ARNICK |
| METHANE-Subgrade | 11/10/2020 | Approved | LARRY ARNICK |
| Reinforced Masonry Frame | 11/10/2020 | Approved | LARRY ARNICK |
| SGSOV-Seismic Gas S/O Valve | 11/10/2020 | SGSOV Approved | LARRY ARNICK |
| Smoke Detectors | 11/10/2020 | Not Ready for Inspection | LARRY ARNICK |
| Structural Steel Frame | 11/10/2020 | Approved | LARRY ARNICK |
| Final | 11/25/2020 | Partial Inspection | EDWIN GREGORYONA |
| Green Building Final | 11/25/2020 | Approved | EDWIN GREGORYONA |
| Smoke Detectors | 11/25/2020 | Approved | EDWIN GREGORYONA |
| Final | 1/19/2021 | Conditional Approval | LARRY ARNICK |