17570 W DEARBORN ST 91324
Certificate Information: 17570 W DEARBORN ST 91324
- Application / Permit
- 18010-20000-01088
- Plan Check / Job No.
- B18VN04088
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) 34'-0" x 26'-3" detached Three-Car Garage.
- Permit Issued
- Issued on 2/12/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2018 | OMID HEDAYAT |
| Corrections Issued | 3/19/2018 | OMID HEDAYAT |
| Quality Review Completed | 3/20/2018 | CHON CHIO KUO |
| Building Plans Picked Up | 3/23/2018 | APPLICANT |
| Green Plans Picked Up | 4/25/2018 | APPLICANT |
| Applicant returned to address corrections | 7/17/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 8/16/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 10/30/2018 | OMID HEDAYAT |
| Applicant returned to address corrections | 2/11/2019 | OMID HEDAYAT |
| Applicant returned to address corrections | 2/10/2020 | OMID HEDAYAT |
| Plan Check Approved | 2/10/2020 | OMID HEDAYAT |
| Issued | 2/12/2020 | LADBS |
| CofO in Progress | 7/24/2024 | JAVIER RAMOS JR |
| Permit Finaled | 10/21/2024 | DANIEL ORRANTE |
| CofO Issued | 10/21/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/21/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 8/16/2018 | DAISY BENICIA |
| Low Impact Development | Cleared | 1/16/2020 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 2/10/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 2/11/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Amado Marble & Construction Inc; Lic. No.: 793379-B | 15526 LANARK STREET VAN NUYS, CA 91406 |
| Engineer | Basma, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/26/2020 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 9/30/2020 | Corrections Issued | MARK JOHNSON |
| Footing/Foundation/Slab | 9/30/2020 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 9/30/2020 | Not Ready for Inspection | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 10/2/2020 | Approved | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 10/16/2020 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 1/4/2021 | Partial Approval | MARK JOHNSON |
| Green Building Rough | 1/4/2021 | Not Ready for Inspection | MARK JOHNSON |
| Wood Frame | 1/4/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 2/9/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Rough | 2/9/2021 | Not Ready for Inspection | MARK JOHNSON |
| Wood Frame | 2/9/2021 | Corrections Issued | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2021 | Partial Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 4/21/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 4/21/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 4/21/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 4/21/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 4/29/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 4/29/2021 | Approved | MARK JOHNSON |
| Wood Frame | 4/29/2021 | Approved | MARK JOHNSON |
| Insulation | 5/28/2021 | Approved | MARK JOHNSON |
| Sewer | 5/28/2021 | Approved | MARK JOHNSON |
| Sewer | 6/7/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 8/2/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 10/18/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 10/18/2021 | Approved | MARK JOHNSON |
| Sewer | 10/18/2021 | Approved | MARK JOHNSON |
| Gas Test | 11/1/2021 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 11/1/2021 | Partial Approval | MARK JOHNSON |
| ELECTRICAL-Final | 4/6/2022 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Final | 3/31/2023 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 3/31/2023 | Approved | JAVIER RAMOS JR |
| Green Building Final | 3/31/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Not Required | JAVIER RAMOS JR |
| Service/Power Release | 3/31/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 3/31/2023 | Approved | JAVIER RAMOS JR |
| Final | 12/4/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 12/4/2023 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 12/4/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 7/24/2024 | OK to Issue CofO | JAVIER RAMOS JR |