18317 W COLLINS ST 91356

Certificate Information: 18317 W COLLINS ST 91356

Application / Permit
18010-20000-01074
Plan Check / Job No.
B18VN03993
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 31'-6" x 19'-6" irregular shape Three-Story Single Family Dwelling with attached 2-Car Garage and rooftop deck per Small Lot Subdivision pursuant to Vesting Tentative Map No. 74583-SL . Certificate of Occupancy (temporary or final) shall not be issued until after the final map has been recorded.
Permit Issued
Issued on 12/5/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 OMID HEDAYAT
Green Plans Picked Up 4/12/2018 APPLICANT
Corrections Issued 4/19/2018 OMID HEDAYAT
Quality Review Completed 4/24/2018 CHON CHIO KUO
Building Plans Picked Up 5/1/2018 APPLICANT
Applicant returned to address corrections 9/18/2018 OMID HEDAYAT
Applicant returned to address corrections 10/17/2018 OMID HEDAYAT
Applicant returned to address corrections 4/23/2019 OMID HEDAYAT
Applicant returned to address corrections 8/1/2019 OMID HEDAYAT
Applicant returned to address corrections 9/16/2019 OMID HEDAYAT
Plan Check Approved 9/16/2019 OMID HEDAYAT
Issued 12/5/2019 LADBS
CofO in Progress 4/23/2022 HENRY KIM
CofO Issued 4/25/2022 MICHAEL SMITH
Permit Finaled 4/25/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/9/2018 CHRISTINE REUSCH
Hydrant and Access approval Cleared 10/24/2018 JOHN DALLAS
Miscellaneous Cleared 10/24/2018 JOHN DALLAS
Green Code Cleared 11/14/2018 DAVID MATSON
Low Impact Development Cleared 12/18/2018 IDA MEISAMI-FARD
Sewer availability Cleared 1/14/2019 APEKSHYA BAJRACHARYA
Address approval Cleared 2/8/2019 HOWARD COOPER
Highway dedication Cleared 2/11/2019 APEKSHYA BAJRACHARYA
Miscellaneous Cleared 2/11/2019 APEKSHYA BAJRACHARYA
Permit Cleared 2/11/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 2/11/2019 APEKSHYA BAJRACHARYA
"Q" conditions Cleared 2/20/2019 RICK TORRES
Miscellaneous Cleared 2/20/2019 RICK TORRES
ZA Case Cleared 2/20/2019 RICK TORRES
ZI Cleared 2/20/2019 RICK TORRES
"T" removal Cleared 9/12/2019 STEVEN WECHSLER
Miscellaneous Cleared 9/12/2019 STEVEN WECHSLER

Contact Information

Architect Texter, Christopher S; Lic. No.: C25901 2 BUELLTON      IRVINE, CA 92602
Contractor Netal Electric Inc; Lic. No.: 995085-B 4915 LIBBIT AVENUE      ENCINO, CA 91436
Engineer Morris, Kyle Byron; Lic. No.: C72911 54 SANDPIPER      IRVINE, CA 92604
Engineer Smith, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

HENRY KIM, (818) 774-4334 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/1/2020 Partial Approval JOSEPH SAGEN
Footing/Foundation/Slab 7/8/2020 Partial Approval JOSEPH SAGEN
Footing/Foundation/Slab 8/19/2020 Approved DONALD SUNSERI
Deputy Reinf. Concrete 8/24/2020 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 9/24/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 10/6/2020 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 11/6/2020 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 11/24/2020 Partial Approval JOSEPH SAGEN
Drywall Nailing 12/10/2020 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 2/8/2021 Not Ready for Inspection JOSEPH SAGEN
HVAC-Rough 2/24/2021 Approved JOSEPH SAGEN
PLUMBING-Rough 2/26/2021 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/1/2021 Partial Approval JOSEPH SAGEN
Interior/Exterior Lathing 3/1/2021 Partial Approval JOSEPH SAGEN
Shower Pan 3/2/2021 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 3/18/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Partial Approval JOSEPH SAGEN
Pre-Inspection 4/13/2021 Partial Approval JOSEPH SAGEN
Pre-Inspection 4/15/2021 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 4/19/2021 Partial Approval JOSEPH SAGEN
Interior/Exterior Lathing 5/4/2021 Partial Approval JOSEPH SAGEN
Insulation 6/14/2021 Partial Approval JOSEPH SAGEN
Insulation 6/15/2021 Partial Approval JOSEPH SAGEN
BUILDING-Rough-Frame 6/18/2021 Approved JOSEPH SAGEN
ELECTRICAL-Rough 6/18/2021 Approved JOSEPH SAGEN
Green Building Rough 6/18/2021 Approved JOSEPH SAGEN
Verify Sprinkler Sign Off 6/18/2021 Approved JOSEPH SAGEN
Insulation 6/21/2021 Partial Approval JOSEPH SAGEN
Drywall Nailing 7/1/2021 Approved JOSEPH SAGEN
Sewer 10/7/2021 Approved JOSEPH SAGEN
Underground Mechanical 10/19/2021 Partial Approval JOSEPH SAGEN
Underground Mechanical 10/22/2021 Not Ready for Inspection JOSEPH SAGEN
Underground Mechanical 10/26/2021 Partial Approval JOSEPH SAGEN
Gas Test 10/28/2021 Not Ready for Inspection JOSEPH SAGEN
Gas Test 11/15/2021 Approved HENRY KIM
Underground Mechanical 12/6/2021 Corrections Issued HENRY KIM
Underground Mechanical 12/20/2021 Partial Approval HENRY KIM
SGSOV-Seismic Gas S/O Valve 1/3/2022 SGSOV Approved HENRY KIM
PLUMBING-Final 1/20/2022 Approved HENRY KIM
Service/Power Release 2/8/2022 Approved HENRY KIM
ELECTRICAL-Final 3/24/2022 Approved HENRY KIM
HVAC-Final 3/24/2022 Approved HENRY KIM
Final 4/22/2022 OK to Issue CofO HENRY KIM
Green Building Final 4/22/2022 Approved HENRY KIM
Smoke Detectors 4/22/2022 Approved HENRY KIM
Structural Steel Frame 4/22/2022 Approved HENRY KIM