16545 W VINTAGE ST 91343

Certificate Information: 16545 W VINTAGE ST 91343

Application / Permit
18010-20000-01058
Plan Check / Job No.
B18VN04055
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED (2) STORY IRREGULAR SHAPED 37'-5" X 29'-7" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED TWO-CAR GARAGE.
Permit Issued
Issued on 8/15/2024
Issuing Office
Valley
Current Status
CofO in Progress on 4/16/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/9/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 ALYSSA N NARCISO
Corrections Issued 4/18/2018 ALYSSA N NARCISO
Quality Review Completed 4/26/2018 STEVEN KIM
Building Plans Picked Up 4/27/2018 APPLICANT
Plan Check Approved 6/21/2018 ALYSSA N NARCISO
Plan Check Approved 3/22/2024 SELLA BENYAMIN
Issued 8/15/2024 APPLICANT
Permit Closed-Status Void 4/4/2025 CHRISTOPHER ROJAS
Re-Activate Permit 4/10/2025 CHRISTOPHER ROJAS
CofO in Progress 4/16/2026 CHRISTOPHER ROJAS

Permit Application Clearance Information

Address approval Cleared 5/31/2018 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 5/31/2018 JOHN LIN
Permit Cleared 5/31/2018 JOHN LIN
Sewer availability Cleared 5/31/2018 JOHN LIN
Green Code Cleared 6/4/2018 MICHAEL AYERS
Low Impact Development Cleared 6/8/2018 SAM NAVID
Roof/Waste drainage to street Cleared 6/8/2018 CARLA VALLADARES
Construction near power lines Cleared 6/11/2018 RIDWAN HARDY
Grading Pre-Inspection Cleared 6/21/2018 ALYSSA N NARCISO

Contact Information

Contractor Owner-Builder       ,
Contractor Power Connection Company The; Lic. No.: 744755-B 10136 NATIONAL BLVD #222      LOS ANGELES, CA 90034
Engineer Samer, Naeem; Lic. No.: C88038 3928 N HARTLEY AVE      COVINA, CA 91722

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/2/2024 Partial Approval JAVIER RAMOS JR
Underground Mechanical 10/2/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 10/11/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 10/22/2024 Approved MATTHEW NELSON
Deputy Reinf. Concrete 10/29/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 11/19/2024 Approved JAVIER RAMOS JR
Deputy Wood Construction 2/21/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 2/28/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 2/28/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Inspection JAVIER RAMOS JR
HVAC-Rough 2/28/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 2/28/2025 Approved JAVIER RAMOS JR
Insulation 3/20/2025 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 4/4/2025 Partial Inspection CHRISTOPHER ROJAS
Final 4/4/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/4/2025 Partial Inspection CHRISTOPHER ROJAS
Drywall Nailing 4/11/2025 Partial Approval NICHOLAS TROWBRIDGE
Green Building Rough 4/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Shower Pan 5/5/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 5/14/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 5/20/2025 Partial Approval CHRISTOPHER ROJAS
Sewer 7/16/2025 Approved NICHOLAS TROWBRIDGE
Gas Test 7/25/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 7/25/2025 Approved CHRISTOPHER ROJAS
Gas Test 10/17/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Final 10/17/2025 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Final 12/5/2025 Corrections Issued MICHEL ABAJAN
HVAC-Final 12/5/2025 Corrections Issued MICHEL ABAJAN
PLUMBING-Final 12/5/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/27/2026 Approved CHRISTOPHER ROJAS
Drywall Nailing 2/27/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 2/27/2026 Corrections Issued CHRISTOPHER ROJAS
Final 2/27/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 2/27/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 2/27/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 2/27/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/27/2026 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 2/27/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 2/27/2026 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 2/27/2026 Approved CHRISTOPHER ROJAS
Final 4/14/2026 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 4/14/2026 Approved CHRISTOPHER ROJAS
Service/Power Release 4/14/2026 Approved CHRISTOPHER ROJAS
Special/Order Compliance 7/16/2026 Corrections Issued CHRISTOPHER ROJAS