14621 W HAMLIN ST 91411
Certificate Information: 14621 W HAMLIN ST 91411
- Application / Permit
- 18010-20000-01004
- Plan Check / Job No.
- B18VN03822
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 11/22/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2018 | JEFFREY TANGONAN |
| Corrections Issued | 3/20/2018 | JEFFREY TANGONAN |
| Green Plans Picked Up | 3/20/2018 | APPLICANT |
| Quality Review Completed | 3/21/2018 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 3/27/2018 | APPLICANT |
| Plan Check Approved | 11/22/2019 | JEFFREY TANGONAN |
| Issued | 11/22/2019 | LADBS |
| CofO in Progress | 3/16/2023 | RYAN SALAZAR |
| Permit Finaled | 4/12/2023 | MICHAEL SMITH |
| CofO Issued | 4/12/2023 | MICHAEL SMITH |
| Permit Finaled | 4/12/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2018 | JOSEPH RHYU |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2018 | JOSEPH RHYU |
| Hydrant and Access approval | Cleared | 4/12/2018 | OSCAR SALGADO JR |
| Sewer availability | Cleared | 4/12/2018 | JOSEPH RHYU |
| HPOZ | Cleared | 11/6/2018 | SUKI GERSHENHORN |
| Miscellaneous | Cleared | 11/6/2018 | SUKI GERSHENHORN |
| ZI | Cleared | 11/6/2018 | SUKI GERSHENHORN |
| Green Code | Cleared | 9/23/2019 | PARISA ZAHABI |
| Low Impact Development | Cleared | 11/5/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 11/5/2019 | ERIK BEASLEY |
Contact Information
| Contractor | Bas Associates Construction; Lic. No.: 610162-B | 6821 PLATT AVE WEST HILLS, CA 91307 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/28/2020 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/16/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/22/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 5/27/2020 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/14/2020 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2020 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 8/14/2020 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/14/2020 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/18/2020 | Partial Approval | DANIEL ORRANTE |
| Green Building Rough | 8/18/2020 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 8/18/2020 | Partial Approval | DANIEL ORRANTE |
| Rough-Elec/Plmb/HVAC | 8/18/2020 | Approved | DANIEL ORRANTE |
| Insulation | 8/21/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 8/26/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 9/3/2020 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/3/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 9/8/2020 | Corrections Issued | DANIEL ORRANTE |
| Interior/Exterior Lathing | 9/14/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 5/28/2021 | Approved | MARK JOHNSON |
| Final | 5/28/2021 | Corrections Issued | MARK JOHNSON |
| Green Building Final | 5/28/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 5/28/2021 | SGSOV Not Ready | MARK JOHNSON |
| Service/Power Release | 5/28/2021 | Not Required | MARK JOHNSON |
| Smoke Detectors | 5/28/2021 | Not Ready for Inspection | MARK JOHNSON |
| Verify Sprinkler Sign Off | 5/28/2021 | Approved | MARK JOHNSON |
| Final | 11/23/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 11/23/2021 | Approved | RICHARD DOCKUS |
| Final | 3/17/2023 | OK to Issue CofO | RYAN SALAZAR |