15430 W ROMAR ST 91345

Certificate Information: 15430 W ROMAR ST 91345

Application / Permit
18010-20000-00931
Plan Check / Job No.
B18VN03540
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW 1-STORY 40'6"X23' DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 PER WFPP. THIS PERMIT TO BE ISSUED CONCURRENTLY WITH NEW MAIN DWELLING UNIT AT FRONT PER 18010-20000-00930. <NFPA 13D FIRE SPRINKLER THRU-OUT>
Permit Issued
Issued on 12/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2018 APPLICANT
Assigned to Plan Check Engineer 3/29/2018 HAYATO TSUCHIYA
Corrections Issued 4/4/2018 HAYATO TSUCHIYA
Quality Review Completed 4/4/2018 ABDUL CHEGENI
Green Plans Picked Up 5/30/2018 APPLICANT
Applicant returned to address corrections 3/23/2020 HAYATO TSUCHIYA
Building Plans Picked Up 6/24/2021 APPLICANT
Applicant returned to address corrections 10/20/2023 HAYATO TSUCHIYA
Applicant returned to address corrections 10/26/2023 HAYATO TSUCHIYA
Applicant returned to address corrections 11/1/2023 HAYATO TSUCHIYA
Plan Check Approved 11/3/2023 HAYATO TSUCHIYA
Issued 12/18/2023 APPLICANT
CofO in Progress 7/29/2025 JENNIFER RABUCHIN
Permit Finaled 9/4/2025 RUBEN SALAS
CofO Issued 9/4/2025 RUBEN SALAS
Permit Finaled 9/4/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 10/22/2018 WALTER RAMIREZ
Address approval Cleared 3/17/2020 JOHN TRIANTAFYLLOS
Permit Cleared 3/17/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 7/28/2021 MATTHEW CRAIG
Low Impact Development Cleared 2/3/2022 MITESH PATEL
Sewer availability Cleared 2/10/2022 ABDULLAH SADOZAI
Roof/Waste drainage to street Cleared 10/18/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/26/2023 COLIN LOREDO
Green Code Cleared 11/3/2023 HAYATO TSUCHIYA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/15/2024 Corrections Issued JENNIFER RABUCHIN
Pre-Inspection 4/15/2024 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 4/25/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 4/29/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/7/2024 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 8/7/2024 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 8/7/2024 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/12/2024 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 8/12/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 8/12/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 8/12/2024 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 8/12/2024 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/30/2024 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 8/30/2024 Approved JACK KARGODORIAN
Green Building Rough 8/30/2024 Approved JACK KARGODORIAN
HVAC-Rough 8/30/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 8/30/2024 Corrections Issued JACK KARGODORIAN
Verify Sprinkler Sign Off 8/30/2024 Approved JACK KARGODORIAN
Insulation 9/10/2024 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 9/20/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 9/20/2024 Approved LOUIS ESCOTO
ELECTRICAL-Rough 4/7/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/29/2025 Approved JENNIFER RABUCHIN
Final 5/29/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/29/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 5/29/2025 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 5/29/2025 Approved JENNIFER RABUCHIN
Final 7/18/2025 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 7/18/2025 Not Ready for Inspection JENNIFER RABUCHIN
Final 7/23/2025 Corrections Issued NICHOLAS TROWBRIDGE
Service/Power Release 7/23/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Final 7/30/2025 Approved JENNIFER RABUCHIN
Final 7/30/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 7/30/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/30/2025 Approved JENNIFER RABUCHIN
Service/Power Release 7/30/2025 Approved JENNIFER RABUCHIN