13853 W VICTORY BLVD 91401

Certificate Information: 13853 W VICTORY BLVD 91401

Application / Permit
18010-20000-00913
Plan Check / Job No.
B18VN03483
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 24 UNIT (DENSITY BONUS-4 UNITS TO BE LOW INCOME), 3-STORY APARTMENT OVER BASEMENT GARAGE.
Permit Issued
Issued on 10/5/2021
Issuing Office
Valley
Current Status
CofO Issued on 12/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2018 APPLICANT
Green Plans Picked Up 3/22/2018 APPLICANT
Assigned to Plan Check Engineer 3/29/2018 JEFFREY TANGONAN
Disabled Access Plans Picked Up 4/3/2018 APPLICANT
Corrections Issued 4/10/2018 JEFFREY TANGONAN
Quality Review Completed 4/13/2018 GUANG MIN TUNG
Applicant returned to address corrections 4/1/2019 JEFFREY TANGONAN
Plan Check Approved 8/4/2021 JEFFREY TANGONAN
Building Plans Picked Up 8/4/2021 APPLICANT
Issued 10/5/2021 APPLICANT
TCO Issued (Expire Date: 05-25-2026) 11/26/2025 RICKEY JACKSON
CofO in Progress 12/4/2025 JOHN KITCKO
Permit Finaled 12/23/2025 RICKEY JACKSON
CofO Issued 12/23/2025 RICKEY JACKSON
Permit Finaled 12/23/2025 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 9/7/2018 MARKOS PEREZ-BRAN
Permit Cleared 3/29/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 3/29/2019 MARKOS PEREZ-BRAN
Work Adjacent to Public Way Cleared 3/29/2019 MARKOS PEREZ-BRAN
Low Impact Development Cleared 7/25/2019 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 7/30/2019 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 7/30/2019 MARKOS PEREZ-BRAN
Highway dedication Cleared 8/22/2019 JULIUS GARCIA
Fire Marshall Fire Life Safety Cleared 10/9/2019 OSCAR SALGADO JR
Hydrant and Access approval Cleared 10/9/2019 GEORGE SUCHAND
"Q" conditions Cleared 11/21/2019 DAISY BENICIA
Frnt yard landscape/Water mgmt Cleared 11/21/2019 DAISY BENICIA
Green Code Cleared 11/21/2019 DAVID MATSON
Opn space landscape/Water mgmt Cleared 11/21/2019 DAISY BENICIA
DAS Clearance Cleared 12/18/2019 JEFFREY TANGONAN
Density Bonus 12.22.A.25 Cleared 5/25/2021 KENNETH LE
Excavation more than 5-ft deep Cleared 9/8/2021 CALOSHA APPROVED

Contact Information

Contractor Engineering And Seismic Construction Inc; Lic. No.: 1041609-B 350 N GLENDALE AVE #B305      GLENDALE, CA 91206

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/29/2022 Partial Inspection DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 7/27/2022 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 8/3/2022 Partial Approval DANIEL VARNUM
Green Building Rough 8/25/2022 Not Ready for Inspection JOHN KITCKO
Masonry Wall/Backfill 8/25/2022 Corrections Issued JOHN KITCKO
Reinforced Concrete Frame 8/25/2022 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 8/25/2022 Not Ready for Inspection JOHN KITCKO
Deputy Shotcrete 8/29/2022 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 8/29/2022 Partial Approval JOHN KITCKO
Deputy Shotcrete 8/30/2022 Approved JOHN KITCKO
Green Building Rough 8/30/2022 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 8/30/2022 Corrections Issued JOHN KITCKO
Verify Sprinkler Sign Off 8/30/2022 Not Ready for Inspection JOHN KITCKO
Deputy Shotcrete 8/31/2022 Approved JOHN KITCKO
Deputy Shotcrete 9/1/2022 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 9/2/2022 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 9/6/2022 Conditional Approval JOHN KITCKO
Deputy Shotcrete 9/7/2022 Approved JOHN KITCKO
Pre-Inspection 9/7/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 9/8/2022 Conditional Approval JOHN KITCKO
Deputy Shotcrete 9/8/2022 Conditional Approval JOHN KITCKO
Deputy Shotcrete 9/9/2022 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 9/30/2022 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 10/12/2022 Conditional Approval JOHN KITCKO
Green Building Rough 10/19/2022 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 10/19/2022 Corrections Issued JOHN KITCKO
Verify Sprinkler Sign Off 10/19/2022 Not Ready for Inspection JOHN KITCKO
Green Building Rough 10/20/2022 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 10/20/2022 Partial Inspection JEFFREY FULTON
Reinforced Masonry Frame 10/20/2022 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 10/20/2022 Not Ready for Inspection JEFFREY FULTON
Deputy Shotcrete 10/21/2022 Conditional Approval JOHN KITCKO
Deputy Drilled-In Anchors 10/27/2022 Approved JOHN KITCKO
Footing/Foundation/Slab 10/27/2022 Partial Approval JOHN KITCKO
Piling/Pier/Caisson 11/5/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 11/7/2022 Approved JOHN KITCKO
Green Building Rough 11/14/2022 Partial Approval JOHN KITCKO
Reinforced Concrete Frame 11/14/2022 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 11/14/2022 Not Ready for Inspection JOHN KITCKO
Masonry Wall/Backfill 11/17/2022 Partial Approval ROBERT DAVIS
Deputy Steel/Welding 12/20/2022 Approved JOHN KITCKO
Deputy Steel/Welding 12/21/2022 Approved JOHN KITCKO
Deputy Steel/Welding 12/22/2022 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 12/23/2022 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 2/10/2023 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 3/6/2023 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 3/6/2023 Partial Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 3/8/2023 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 3/9/2023 Approved JOHN KITCKO
Deputy Reinf. Concrete 3/10/2023 Approved JOHN KITCKO
Footing/Foundation/Slab 3/10/2023 Partial Inspection JOHN KITCKO
Deputy Reinf. Concrete 3/13/2023 Approved JOHN KITCKO
Masonry Wall/Backfill 3/13/2023 Corrections Issued JOHN KITCKO
Footing/Foundation/Slab 3/15/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 3/17/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/19/2023 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/20/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/21/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 No Access for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 11/9/2023 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 11/27/2023 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 1/31/2024 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 2/26/2024 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 3/27/2024 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 4/12/2024 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 4/15/2024 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 4/18/2024 Not Ready for Inspection GREGORY POMISH
Interior/Exterior Lathing 4/19/2024 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 4/22/2024 Partial Approval JOHN KITCKO
Insulation 4/24/2024 Partial Inspection JOHN KITCKO
Insulation 4/26/2024 Not Ready for Inspection JOHN KITCKO
Insulation 4/30/2024 Partial Approval JOHN KITCKO
Deputy Drilled-In Anchors 5/1/2024 Conditional Approval JOHN KITCKO
Wood Frame 5/1/2024 Partial Approval JOHN KITCKO
Green Building Rough 5/8/2024 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 5/8/2024 Not Ready for Inspection JOHN KITCKO
Wood Frame 5/8/2024 Not Ready for Inspection JOHN KITCKO
Green Building Rough 5/14/2024 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 5/14/2024 Not Ready for Inspection JOHN KITCKO
Wood Frame 5/14/2024 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Partial Approval JOHN KITCKO
Insulation 5/28/2024 Partial Approval JOHN KITCKO
Deputy Wood Construction 5/30/2024 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Corrections Issued JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Approval JOHN KITCKO
Green Building Rough 6/10/2024 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 6/10/2024 Not Ready for Inspection JOHN KITCKO
Wood Frame 6/10/2024 Not Ready for Inspection JOHN KITCKO
Green Building Rough 6/12/2024 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 6/12/2024 Not Ready for Inspection JOHN KITCKO
Wood Frame 6/12/2024 Partial Inspection JOHN KITCKO
Green Building Rough 6/17/2024 Partial Approval JOHN KITCKO
Verify Sprinkler Sign Off 6/17/2024 Not Ready for Inspection JOHN KITCKO
Wood Frame 6/17/2024 Conditional Approval JOHN KITCKO
Green Building Rough 6/24/2024 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 6/24/2024 Not Ready for Inspection JOHN KITCKO
Wood Frame 6/24/2024 Not Ready for Inspection JOHN KITCKO
Green Building Rough 6/26/2024 Approved JOHN KITCKO
Verify Sprinkler Sign Off 6/26/2024 Approved JOHN KITCKO
Wood Frame 6/26/2024 Partial Approval JOHN KITCKO
Insulation 7/2/2024 Not Ready for Inspection JOHN KITCKO
Insulation 7/9/2024 Partial Approval JOHN KITCKO
Insulation 7/11/2024 Partial Approval JOHN KITCKO
Wood Frame 7/15/2024 Partial Approval JOHN KITCKO
Insulation 7/17/2024 Partial Approval JOHN KITCKO
Wood Frame 7/17/2024 Partial Approval JOHN KITCKO
Drywall Nailing 7/26/2024 Partial Approval JOHN KITCKO
Drywall Nailing 7/31/2024 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 7/31/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 10/21/2024 Partial Approval JOHN KITCKO
Final 5/5/2025 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 5/5/2025 Not Ready for Inspection JOHN KITCKO
Green Building Final 5/5/2025 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 5/5/2025 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 5/5/2025 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 5/5/2025 Not Ready for Inspection JOHN KITCKO
Wood Frame 5/5/2025 Not Ready for Inspection JOHN KITCKO
Final 7/10/2025 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 7/10/2025 Approved JOHN KITCKO
Green Building Final 7/10/2025 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 7/10/2025 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 7/10/2025 Not Ready for Inspection JOHN KITCKO
Wood Frame 7/10/2025 Approved JOHN KITCKO
Final 7/16/2025 Partial Inspection JOHN KITCKO
Green Building Final 7/16/2025 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 7/16/2025 Not Ready for Inspection JOHN KITCKO
Final 9/2/2025 Partial Inspection JOHN KITCKO
Green Building Final 9/2/2025 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 9/2/2025 Not Ready for Inspection JOHN KITCKO
Final 9/10/2025 Partial Inspection JOHN KITCKO
Green Building Final 9/10/2025 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 9/10/2025 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 9/10/2025 Not Ready for Inspection JOHN KITCKO
Final 10/8/2025 Not Ready for Inspection JOHN KITCKO
Green Building Final 10/8/2025 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 10/8/2025 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 10/8/2025 Not Ready for Inspection JOHN KITCKO
Final 10/23/2025 Not Ready for Inspection JOHN KITCKO
Green Building Final 10/23/2025 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 10/23/2025 Approved JOHN KITCKO
Final 10/28/2025 Partial Inspection JOHN KITCKO
Green Building Final 10/28/2025 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 10/28/2025 SGSOV Approved JOHN KITCKO
Final 11/24/2025 Conditional Approval JOHN KITCKO
Final 12/4/2025 OK to Issue CofO JOHN KITCKO