Pre-Inspection
|
1/22/2021
|
Partial Inspection
|
SCOTT FINNILA
|
|
Underground Mechanical
|
2/25/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
Deputy Reinf. Concrete
|
3/2/2021
|
Conditional Approval
|
SCOTT FINNILA
|
|
Deputy Reinf. Concrete
|
3/9/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
3/19/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
3/25/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Excavation/Setback/Form/Re-Bar
|
3/30/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
5/11/2021
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
5/24/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
6/24/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
7/21/2021
|
Partial Inspection
|
SCOTT FINNILA
|
|
Pre-Inspection
|
7/21/2021
|
Partial Inspection
|
SCOTT FINNILA
|
|
Excavation/Setback/Form/Re-Bar
|
7/26/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
Pre-Inspection
|
7/26/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
Deputy Reinf. Concrete
|
7/29/2021
|
Conditional Approval
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
8/4/2021
|
Partial Inspection
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
8/10/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Excavation/Setback/Form/Re-Bar
|
8/12/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Reinf. Concrete
|
8/16/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
Deputy Steel/Welding
|
8/23/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
Drywall Nailing
|
9/1/2021
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Green Building Rough
|
9/1/2021
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Pre-Inspection
|
9/1/2021
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Drywall Nailing
|
9/7/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
9/7/2021
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Pre-Inspection
|
9/7/2021
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
9/10/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
9/10/2021
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/21/2021
|
Conditional Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/22/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
Drywall Nailing
|
9/27/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
Drywall Nailing
|
10/1/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
Drywall Nailing
|
10/14/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
Green Building Rough
|
10/14/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
10/21/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/2/2021
|
Conditional Approval
|
SCOTT FINNILA
|
|
Drywall Nailing
|
3/2/2022
|
Partial Approval
|
CRAIG DAVIS
|
|
Green Building Rough
|
3/2/2022
|
Not Ready for Inspection
|
CRAIG DAVIS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/11/2022
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/12/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/19/2022
|
Corrections Issued
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/24/2022
|
Corrections Issued
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/20/2022
|
No Access for Inspection
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/21/2022
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
PLUMBING-Rough
|
7/21/2022
|
Conditional Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/1/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
PLUMBING-Rough
|
8/1/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
Insulation
|
8/11/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/17/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/22/2022
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/23/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
Verify Sprinkler Sign Off
|
8/23/2022
|
Approved
|
SCOTT FINNILA
|
|
PLUMBING-Rough
|
9/19/2022
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Rough-Elec/Plmb/HVAC
|
9/19/2022
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
10/18/2022
|
Corrections Issued
|
SCOTT FINNILA
|
|
Green Building Rough
|
10/18/2022
|
Corrections Issued
|
SCOTT FINNILA
|
|
Rough-Elec/Plmb/HVAC
|
10/18/2022
|
Corrections Issued
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
10/25/2022
|
Conditional Approval
|
SCOTT FINNILA
|
|
Green Building Rough
|
10/25/2022
|
Approved
|
SCOTT FINNILA
|
|
Rough-Elec/Plmb/HVAC
|
10/25/2022
|
Approved
|
SCOTT FINNILA
|
|
Interior/Exterior Lathing
|
10/28/2022
|
Not Ready for Inspection
|
STUART CHAPMAN
|
|
Insulation
|
11/1/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Shower Pan
|
11/1/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Special/Order Compliance
|
11/1/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
11/15/2022
|
Approved
|
SCOTT FINNILA
|
|
Interior/Exterior Lathing
|
11/15/2022
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Shower Pan
|
11/15/2022
|
Approved
|
SCOTT FINNILA
|
|
Interior/Exterior Lathing
|
1/4/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
Sewer
|
4/7/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
|
Underground Mechanical
|
5/2/2023
|
Partial Approval
|
STUART CHAPMAN
|
|
Gas Test
|
6/20/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
|
ELECTRICAL-Rough
|
7/18/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
|
PLUMBING-Rough
|
7/18/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
|
HVAC-Final
|
8/2/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
|
Gas Test
|
8/22/2023
|
Not Ready for Inspection
|
ALIZAH MAYAGOITIA
|
|
Gas Test
|
9/22/2023
|
Approved
|
BRENDAN MORELLI
|
|
PLUMBING-Final
|
9/22/2023
|
Approved
|
BRENDAN MORELLI
|
|
ELECTRICAL-Final
|
9/28/2023
|
Not Ready for Inspection
|
ALIZAH MAYAGOITIA
|
|
HVAC-Final
|
9/28/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
|
ELECTRICAL-Final
|
10/2/2023
|
Approved
|
BRENDAN MORELLI
|
|
HVAC-Final
|
10/2/2023
|
Approved
|
BRENDAN MORELLI
|
|
Service/Power Release
|
10/2/2023
|
Not Ready for Inspection
|
BRENDAN MORELLI
|
|
Service/Power Release
|
12/20/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
|
BUILDING-Rough-Frame
|
1/2/2024
|
Approved
|
ALIZAH MAYAGOITIA
|
|
Final
|
1/2/2024
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
|
Footing/Foundation/Slab
|
1/2/2024
|
Approved
|
ALIZAH MAYAGOITIA
|
|
Green Building Final
|
1/2/2024
|
Approved
|
ALIZAH MAYAGOITIA
|
|
SGSOV-Seismic Gas S/O Valve
|
1/2/2024
|
SGSOV Approved
|
ALIZAH MAYAGOITIA
|
|
Smoke Detectors
|
1/2/2024
|
Approved
|
ALIZAH MAYAGOITIA
|
|
Final
|
2/21/2024
|
Not Ready for Inspection
|
BRENDAN MORELLI
|
|
Final
|
3/4/2024
|
OK to Issue CofO
|
BRENDAN MORELLI
|