4526 N SYLMAR AVE 91423
Certificate Information: 4526 N SYLMAR AVE 91423
- Application / Permit
- 18010-20000-00795
- Plan Check / Job No.
- B18VN03163
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW (11'-7 3/4" x 16'-7 1/4") DET RECREATION ROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2018 | MENA WASSEF |
| Corrections Issued | 4/10/2018 | MENA WASSEF |
| Quality Review Completed | 4/13/2018 | GUANG MIN TUNG |
| Building Plans Picked Up | 4/19/2018 | APPLICANT |
| Green Plans Picked Up | 4/19/2018 | APPLICANT |
| Applicant returned to address corrections | 9/26/2019 | TROY DEGUZMAN |
| Applicant returned to address corrections | 2/10/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 3/9/2020 | TROY DEGUZMAN |
| Plan Check Approved | 8/6/2020 | TROY DEGUZMAN |
| Issued | 9/3/2020 | APPLICANT |
| CofO in Progress | 2/9/2023 | MISAEL ESPARZA |
| Permit Finaled | 2/17/2023 | MICHAEL SMITH |
| CofO Issued | 2/17/2023 | MICHAEL SMITH |
| Permit Finaled | 2/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2019 | GABRIEL ROBLES |
| Green Code | Cleared | 1/17/2020 | PARISA ZAHABI |
| Roof/Waste drainage to street | Cleared | 1/29/2020 | GUILLERMO PETRA |
| ZI | Cleared | 1/31/2020 | NELSON RODRIGUEZ |
| Hydrant and Access approval | Cleared | 7/31/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 7/31/2020 | ROBIN YAMADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/24/2021 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 9/20/2021 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 1/4/2022 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 2/25/2022 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 2/25/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 3/21/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 3/21/2022 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/25/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 3/30/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 4/4/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 4/6/2022 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/6/2022 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 5/13/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 5/18/2022 | Approved | MISAEL ESPARZA |
| Insulation | 6/1/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 6/1/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 6/15/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/8/2022 | No Access for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/22/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 12/14/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 1/6/2023 | Approved | MISAEL ESPARZA |
| HVAC-Final | 1/25/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/8/2023 | Approved | MISAEL ESPARZA |
| Final | 2/8/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/8/2023 | Approved | MISAEL ESPARZA |
| Green Building Final | 2/8/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 2/8/2023 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 2/8/2023 | Approved | MISAEL ESPARZA |
| MERV13>=Rough | 2/8/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 2/8/2023 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 2/8/2023 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 2/8/2023 | Approved | MISAEL ESPARZA |