4526 N SYLMAR AVE 91423

Certificate Information: 4526 N SYLMAR AVE 91423

Application / Permit
18010-20000-00795
Plan Check / Job No.
B18VN03163
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW (11'-7 3/4" x 16'-7 1/4") DET RECREATION ROOM. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2018 APPLICANT
Assigned to Plan Check Engineer 3/22/2018 MENA WASSEF
Corrections Issued 4/10/2018 MENA WASSEF
Quality Review Completed 4/13/2018 GUANG MIN TUNG
Building Plans Picked Up 4/19/2018 APPLICANT
Green Plans Picked Up 4/19/2018 APPLICANT
Applicant returned to address corrections 9/26/2019 TROY DEGUZMAN
Applicant returned to address corrections 2/10/2020 TROY DEGUZMAN
Applicant returned to address corrections 3/9/2020 TROY DEGUZMAN
Plan Check Approved 8/6/2020 TROY DEGUZMAN
Issued 9/3/2020 APPLICANT
CofO in Progress 2/9/2023 MISAEL ESPARZA
Permit Finaled 2/17/2023 MICHAEL SMITH
CofO Issued 2/17/2023 MICHAEL SMITH
Permit Finaled 2/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/5/2019 GABRIEL ROBLES
Green Code Cleared 1/17/2020 PARISA ZAHABI
Roof/Waste drainage to street Cleared 1/29/2020 GUILLERMO PETRA
ZI Cleared 1/31/2020 NELSON RODRIGUEZ
Hydrant and Access approval Cleared 7/31/2020 KURT CORRAL
Low Impact Development Cleared 7/31/2020 ROBIN YAMADA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/24/2021 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 9/20/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Partial Approval MISAEL ESPARZA
Wood Frame 1/4/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 2/25/2022 Corrections Issued MISAEL ESPARZA
Sewer 2/25/2022 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 3/21/2022 Approved MISAEL ESPARZA
Wood Frame 3/21/2022 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 3/25/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 3/30/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 4/4/2022 Approved MISAEL ESPARZA
HVAC-Rough 4/6/2022 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 5/6/2022 Partial Approval MISAEL ESPARZA
HVAC-Rough 5/13/2022 Approved MISAEL ESPARZA
Wood Frame 5/18/2022 Approved MISAEL ESPARZA
Insulation 6/1/2022 Approved MISAEL ESPARZA
Wood Frame 6/1/2022 Approved MISAEL ESPARZA
Drywall Nailing 6/15/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 11/8/2022 No Access for Inspection MISAEL ESPARZA
ELECTRICAL-Final 11/22/2022 Approved MISAEL ESPARZA
PLUMBING-Final 12/14/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 1/6/2023 Approved MISAEL ESPARZA
HVAC-Final 1/25/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/8/2023 Approved MISAEL ESPARZA
Final 2/8/2023 OK to Issue CofO MISAEL ESPARZA
Footing/Foundation/Slab 2/8/2023 Approved MISAEL ESPARZA
Green Building Final 2/8/2023 Approved MISAEL ESPARZA
Green Building Rough 2/8/2023 Approved MISAEL ESPARZA
MERV13>=Final 2/8/2023 Approved MISAEL ESPARZA
MERV13>=Rough 2/8/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Approved MISAEL ESPARZA
Service/Power Release 2/8/2023 Approved MISAEL ESPARZA
Smoke Detectors 2/8/2023 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 2/8/2023 Approved MISAEL ESPARZA