4526 N SYLMAR AVE 91423

Certificate Information: 4526 N SYLMAR AVE 91423

Application / Permit
18010-20000-00794
Plan Check / Job No.
B18VN03163
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (57'-6 3/8" x 35'-9 5/8") TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED TWO CAR GARAGE . WITH FIRE SPRINKLER NFPA-13D THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2018 APPLICANT
Assigned to Plan Check Engineer 3/22/2018 MENA WASSEF
Corrections Issued 4/10/2018 MENA WASSEF
Quality Review Completed 4/13/2018 GUANG MIN TUNG
Building Plans Picked Up 4/19/2018 APPLICANT
Green Plans Picked Up 4/19/2018 APPLICANT
Applicant returned to address corrections 9/26/2019 TROY DEGUZMAN
Applicant returned to address corrections 2/10/2020 TROY DEGUZMAN
Applicant returned to address corrections 3/9/2020 TROY DEGUZMAN
Plan Check Approved 8/6/2020 TROY DEGUZMAN
Issued 9/3/2020 APPLICANT
CofO in Progress 2/9/2023 MISAEL ESPARZA
Permit Finaled 2/17/2023 MICHAEL SMITH
CofO Issued 2/17/2023 MICHAEL SMITH
Permit Finaled 2/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 5/8/2018 SAM NAVID
Address approval Cleared 8/5/2019 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/5/2019 GABRIEL ROBLES
Hydrant and Access approval Cleared 8/5/2019 GEORGE SUCHAND
Permit Cleared 8/5/2019 GABRIEL ROBLES
Sewer availability Cleared 8/5/2019 GABRIEL ROBLES
Green Code Cleared 1/17/2020 PARISA ZAHABI
Roof/Waste drainage to street Cleared 1/29/2020 GUILLERMO PETRA
ZI Cleared 1/31/2020 NELSON RODRIGUEZ
GPI Written Notices Cleared 2/10/2020 MENA WASSEF

Contact Information

Architect Steven, Lane; Lic. No.: C36063 19742 BYRNE PLACE      SANTA CLARITA, CA 91350
Contractor Owner-Builder       ,
Engineer Gharibans,, Armineh H; Lic. No.: S3801 18544 BRYMER STREET      NORTHRIDGE, CA 91326

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/24/2021 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 9/15/2021 Corrections Issued MISAEL ESPARZA
Deputy Reinf. Concrete 9/23/2021 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Approval MISAEL ESPARZA
Wood Frame 1/4/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 2/25/2022 Corrections Issued MISAEL ESPARZA
Sewer 2/25/2022 Approved MISAEL ESPARZA
Deputy Wood Construction 3/21/2022 Approved MISAEL ESPARZA
Wood Frame 3/21/2022 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 3/25/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 3/30/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 4/4/2022 Approved MISAEL ESPARZA
Shower Pan 4/4/2022 Approved MISAEL ESPARZA
HVAC-Rough 4/6/2022 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 5/6/2022 Partial Approval MISAEL ESPARZA
HVAC-Rough 5/13/2022 Approved MISAEL ESPARZA
Wood Frame 5/18/2022 Partial Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 6/1/2022 Approved MISAEL ESPARZA
Deputy Wood Construction 6/1/2022 Approved MISAEL ESPARZA
Insulation 6/1/2022 Approved MISAEL ESPARZA
Wood Frame 6/1/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 6/8/2022 Approved MISAEL ESPARZA
Drywall Nailing 6/17/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 6/17/2022 Approved MISAEL ESPARZA
Green Building Rough 6/17/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 6/17/2022 Approved MISAEL ESPARZA
Special/Order Compliance 9/14/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 11/8/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 11/22/2022 Approved MISAEL ESPARZA
PLUMBING-Final 12/14/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 1/6/2023 Approved MISAEL ESPARZA
HVAC-Final 1/25/2023 Corrections Issued MISAEL ESPARZA
HVAC-Final 1/31/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 2/6/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/8/2023 Approved MISAEL ESPARZA
Drywall Nailing 2/8/2023 Approved MISAEL ESPARZA
Final 2/8/2023 OK to Issue CofO MISAEL ESPARZA
Footing/Foundation/Slab 2/8/2023 Approved MISAEL ESPARZA
Green Building Final 2/8/2023 Approved MISAEL ESPARZA
MERV13>=Final 2/8/2023 Approved MISAEL ESPARZA
MERV13>=Rough 2/8/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Approved MISAEL ESPARZA
Service/Power Release 2/8/2023 Approved MISAEL ESPARZA
Smoke Detectors 2/8/2023 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 2/8/2023 Approved MISAEL ESPARZA