Underground Mechanical
|
5/3/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Excavation/Setback/Form/Re-Bar
|
5/28/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Excavation/Setback/Form/Re-Bar
|
5/29/2019
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/11/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/14/2019
|
Partial Approval
|
SCOTT FINNILA
|
|
Deputy Wood Construction
|
6/19/2019
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/21/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
6/25/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
7/9/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/19/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/24/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
7/30/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/30/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/2/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/8/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/9/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
8/14/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
8/16/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
8/16/2019
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/11/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/24/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
10/18/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/18/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Shower Pan
|
10/23/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
10/25/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
10/25/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Shower Pan
|
10/25/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
10/28/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
10/30/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
11/1/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
11/1/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
11/5/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
11/13/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
11/15/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
11/15/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/19/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/26/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
11/26/2019
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Wood Construction
|
12/4/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
12/4/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
12/5/2019
|
Corrections Issued
|
SCOTT FINNILA
|
|
Green Building Rough
|
12/5/2019
|
Corrections Issued
|
SCOTT FINNILA
|
|
METHANE-Rough
|
12/5/2019
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
Verify Sprinkler Sign Off
|
12/5/2019
|
Approved
|
SCOTT FINNILA
|
|
BUILDING-Rough-Frame
|
12/10/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
12/10/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
12/10/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Rough
|
12/10/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
12/12/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
12/12/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Rough
|
12/12/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
12/13/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
12/16/2019
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Rough
|
12/16/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Insulation
|
12/19/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
12/20/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
12/24/2019
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Insulation
|
12/24/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
12/27/2019
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
12/31/2019
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
12/31/2019
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
1/7/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
1/9/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
1/22/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Shower Pan
|
1/22/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Verify Rec and Parks Fee Memo
|
2/28/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Gas Test
|
4/21/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
4/21/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
4/28/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Service/Power Release
|
4/28/2020
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Verify Rec and Parks Fee Memo
|
4/28/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
4/30/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
5/11/2020
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Gas Test
|
5/13/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Final
|
5/13/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Final
|
5/13/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
5/15/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Gas Test
|
5/22/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Final
|
5/22/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Final
|
5/22/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Service/Power Release
|
5/22/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Service/Power Release
|
6/5/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Service/Power Release
|
6/25/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Service/Power Release
|
7/1/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
7/13/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Final
|
7/13/2020
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
7/13/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Green Building Final
|
7/13/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Barrier
|
7/13/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Final
|
7/13/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Rough
|
7/13/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Subgrade
|
7/13/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
SGSOV-Seismic Gas S/O Valve
|
7/13/2020
|
SGSOV Approved
|
ALEJANDRO DE ARTOLA
|
|
Smoke Detectors
|
7/13/2020
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Final
|
8/11/2020
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Final
|
9/3/2020
|
OK to Issue CofO
|
ALEJANDRO DE ARTOLA
|