9607 W HIGH RIDGE DR 90210

Certificate Information: 9607 W HIGH RIDGE DR 90210

Application / Permit
18010-20000-00592
Plan Check / Job No.
B18VN02677
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2 story SFD with basement
Permit Issued
Issued on 7/14/2021
Issuing Office
Current Status
CofO Issued on 2/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2018 APPLICANT
Assigned to Plan Check Engineer 2/22/2018 VLADIMIR ARUTYUNYAN
Green Plans Picked Up 2/27/2018 APPLICANT
Corrections Issued 2/28/2018 VLADIMIR ARUTYUNYAN
Quality Review Completed 3/2/2018 STEVEN KIM
Plan Check Approved 6/15/2021 VLADIMIR ARUTYUNYAN
Plan Check Approved 7/1/2021 VLADIMIR ARUTYUNYAN
Issued 7/14/2021 APPLICANT
Building Plans Picked Up 8/4/2021 APPLICANT
CofO in Progress 10/4/2021 MATT KELLERMAN
No Progress 10/29/2021 DANIEL ORRANTE
CofO in Progress 10/29/2021 MATT KELLERMAN
CofO in Progress 1/24/2022 MICHAEL PELHAM
Permit Finaled 2/26/2022 DANIEL ORRANTE
CofO Issued 2/26/2022 DANIEL ORRANTE
Permit Finaled 2/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Green Code Cleared 5/31/2018 PARISA ZAHABI

Contact Information

Contractor See Construction Inc; Lic. No.: 923837-B 145 N LA BREA AVENUE #D      LOS ANGELES, CA 90036
Engineer Tsao, Tze-Tzong; Lic. No.: C46886 9428 ETON AVE STE M      CHATSWORTH, CA 91311

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/21/2021 Approved ANTHONY MCDOWALL
Final 7/21/2021 Not Ready for Inspection ANTHONY MCDOWALL
Footing/Foundation/Slab 7/21/2021 Approved ANTHONY MCDOWALL
Green Building Final 7/21/2021 Approved ANTHONY MCDOWALL
Green Building Rough 7/21/2021 Approved ANTHONY MCDOWALL
SGSOV-Seismic Gas S/O Valve 7/21/2021 SGSOV Approved ANTHONY MCDOWALL
Service/Power Release 7/21/2021 Approved ANTHONY MCDOWALL
Smoke Detectors 7/21/2021 Approved ANTHONY MCDOWALL
Verify Sprinkler Sign Off 7/21/2021 Approved ANTHONY MCDOWALL
Final 9/2/2021 Partial Approval MATT KELLERMAN
Final 10/4/2021 Corrections Issued MATT KELLERMAN