743 N SEWARD ST 90038

Certificate Information: 743 N SEWARD ST 90038

Application / Permit
18010-20000-00243
Plan Check / Job No.
B18VN01138
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
OFFICE BUILDING OVER BASEMENT PARKING GARAGE. (Only two tenants ..See Comments)
Permit Issued
Issued on 4/10/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2018 APPLICANT
Assigned to Plan Check Engineer 2/1/2018 RUDOLF KINAR MELIKOFF
Disabled Access Plans Picked Up 2/1/2018 APPLICANT
Green Plans Picked Up 2/1/2018 APPLICANT
Corrections Issued 2/6/2018 RUDOLF KINAR MELIKOFF
Quality Review Completed 2/9/2018 TIEN JEN WANG
Building Plans Picked Up 2/13/2018 APPLICANT
Applicant returned to address corrections 4/20/2018 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 4/27/2018 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 5/8/2018 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 5/9/2018 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 5/18/2018 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 7/13/2018 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 7/20/2018 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 7/24/2018 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 7/31/2018 RUDOLF KINAR MELIKOFF
Plan Check Approved 4/10/2019 RUDOLF KINAR MELIKOFF
Issued 4/10/2019 LADBS
TCO Issued (Expire Date: 06-12-2021) 12/14/2020 ERNESTO CORRAL
CofO in Progress 5/14/2021 EDWIN GREGORYONA
Permit Finaled 5/21/2021 ERNESTO CORRAL
CofO Issued 5/21/2021 ERNESTO CORRAL
Permit Finaled 5/21/2021 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 4/10/2018 SOPHIE GABEL-SCHEINBAU
Address approval Cleared 4/10/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 4/10/2018 STEVE MELGAR
Highway dedication Cleared 4/10/2018 STEVE MELGAR
Permit Cleared 4/10/2018 STEVE MELGAR
ZI Cleared 4/10/2018 SOPHIE GABEL-SCHEINBAU
Hydrant and Access approval Cleared 4/13/2018 GEORGE SUCHAND
Sewer availability Cleared 4/13/2018 CARLA VALLADARES
Disturb/Remove Protected Trees Cleared 5/31/2018 LUIS TORRES
Low Impact Development Cleared 6/25/2018 MITESH PATEL
Work Adjacent to Public Way Cleared 6/28/2018 KENNETH PHAM
Bicycle Parking Cleared 6/29/2018 STEVE MELGAR
Roof/Waste drainage to street Cleared 6/29/2018 JOHN LIN
DAS Clearance Cleared 7/20/2018 NORLITO MEDRANO
Green Code Cleared 7/23/2018 DAVID MATSON
Fire Marshall Fire Life Safety Cleared 7/26/2018 MENOA AGHAJANI
Mechanical Car Lift Cleared 7/26/2018 OSCAR SALGADO JR
Construction near power lines Cleared 3/20/2019 RIDWAN HARDY
Construction within easement Cleared 3/20/2019 RIDWAN HARDY
Public Works-Highway Ded. Cleared 4/8/2019 JOHN LIN

Contact Information

Architect Glynn,, Frank Christopher; Lic. No.: C19159 233 CALIFORNIA STREET      EL SEGUNDO, CA 90245
Contractor Forza Construction Inc; Lic. No.: 914162-B 25243 AVENUE TIBBITS      VALENCIA, CA 91355
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 5/8/2019 Conditional Approval LARRY ARNICK
Deputy Methane Barrier 5/9/2019 Conditional Approval DAVID BURKHEAD
Pre-Inspection 5/9/2019 Approved DAVID BURKHEAD
Deputy Methane Barrier 5/17/2019 Conditional Approval DAVID BURKHEAD
Deputy Methane Barrier 5/20/2019 Conditional Approval DAVID BURKHEAD
Deputy Methane Barrier 5/22/2019 Conditional Approval DAVID BURKHEAD
Deputy Methane Barrier 5/23/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/29/2019 Approved HAMID PISHEHVAR
Footing/Foundation/Slab 5/29/2019 Approved HAMID PISHEHVAR
METHANE-Barrier 5/29/2019 Approved HAMID PISHEHVAR
METHANE-Subgrade 5/29/2019 Approved HAMID PISHEHVAR
Deputy Reinf. Masonry 6/6/2019 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 6/7/2019 Conditional Approval DAVID BURKHEAD
Masonry Wall/Backfill 6/7/2019 Partial Approval DAVID BURKHEAD
Reinforced Concrete Frame 6/7/2019 Partial Approval DAVID BURKHEAD
Deputy Reinf. Masonry 6/11/2019 Partial Approval FELIX CEBALLOS
Deputy Reinf. Concrete 6/12/2019 Partial Approval FELIX CEBALLOS
Deputy Reinf. Masonry 6/17/2019 Conditional Approval DAVID BURKHEAD
Masonry Wall/Backfill 6/17/2019 Partial Approval DAVID BURKHEAD
Deputy Reinf. Masonry 6/18/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 6/19/2019 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 6/26/2019 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/3/2019 Partial Approval DAVID BURKHEAD
Deputy Methane Barrier 7/16/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/23/2019 Partial Approval DAVID BURKHEAD
Deputy Methane Barrier 7/29/2019 Conditional Approval DAVID BURKHEAD
Deputy Methane Barrier 7/30/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 8/2/2019 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 8/29/2019 Partial Approval DAVID BURKHEAD
Green Building Rough 8/29/2019 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 8/29/2019 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 8/29/2019 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 9/11/2019 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 9/18/2019 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 9/19/2019 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 9/23/2019 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 9/25/2019 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 9/27/2019 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 10/1/2019 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/2/2019 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/7/2019 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/25/2019 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 10/28/2019 Partial Approval DAVID BURKHEAD
Green Building Rough 10/28/2019 Not Ready for Inspection DANIEL MC AULIFFE
METHANE-Rough 10/28/2019 Partial Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 10/28/2019 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 10/28/2019 Not Ready for Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 11/4/2019 Partial Inspection DAVID BURKHEAD
Masonry Wall/Backfill 11/6/2019 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/8/2019 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/22/2019 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/23/2019 Off-Hour Fees Due
Green Building Rough 11/23/2019 Not Ready for Inspection DANIEL MC AULIFFE
METHANE-Rough 11/23/2019 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 11/23/2019 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 11/23/2019 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Drilled-In Anchors 11/25/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 11/26/2019 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 12/19/2019 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 12/19/2019 Not Ready for Inspection DANIEL MC AULIFFE
METHANE-Rough 12/19/2019 Partial Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 12/19/2019 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 12/19/2019 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Other (see comments) 12/20/2019 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/8/2020 Partial Approval DAVID BURKHEAD
Masonry Wall/Backfill 1/10/2020 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 1/17/2020 Partial Approval DAVID BURKHEAD
Deputy Other (see comments) 1/21/2020 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 2/7/2020 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 2/10/2020 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 2/11/2020 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 2/14/2020 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 3/26/2020 Partial Approval DAVID BURKHEAD
Green Building Rough 4/20/2020 Not Ready for Inspection DAVID BURKHEAD
METHANE-Rough 4/20/2020 Not Ready for Inspection DAVID BURKHEAD
Structural Steel Frame 4/20/2020 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 4/20/2020 Not Ready for Inspection DAVID BURKHEAD
Light Gage Steel Frame 4/28/2020 Not Ready for Inspection DAVID BURKHEAD
Light Gage Steel Frame 6/10/2020 Partial Approval JONATHAN QUACH
Wood Frame 6/19/2020 Partial Approval JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 6/26/2020 Approved JONATHAN QUACH
Special/Order Compliance 7/13/2020 Approved JONATHAN QUACH
Light Gage Steel Frame 7/24/2020 Approved JONATHAN QUACH
Drywall Nailing 7/28/2020 Partial Approval JONATHAN QUACH
Green Building Rough 7/28/2020 Not Ready for Inspection JONATHAN QUACH
Light Gage Steel Frame 7/28/2020 Partial Approval JONATHAN QUACH
Drywall Nailing 8/3/2020 Not Ready for Inspection JONATHAN QUACH
Green Building Rough 8/3/2020 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 8/5/2020 Partial Approval JONATHAN QUACH
Drywall Nailing 8/10/2020 Partial Approval JONATHAN QUACH
Green Building Rough 8/10/2020 Not Ready for Inspection JONATHAN QUACH
Light Gage Steel Frame 8/12/2020 Partial Approval JONATHAN QUACH
Wood Frame 8/17/2020 Approved JONATHAN QUACH
Green Building Rough 8/19/2020 Not Ready for Inspection JONATHAN QUACH
Interior/Exterior Lathing 8/19/2020 Approved JONATHAN QUACH
Special/Order Compliance 8/24/2020 Approved JONATHAN QUACH
Drywall Nailing 9/16/2020 Partial Approval JONATHAN QUACH
Green Building Rough 9/16/2020 Approved JONATHAN QUACH
METHANE-Rough 10/20/2020 Not Ready for Inspection LARRY ARNICK
Structural Steel Frame 10/20/2020 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 10/20/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 10/30/2020 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 11/4/2020 Approved JONATHAN QUACH
Special/Order Compliance 11/16/2020 Partial Inspection EDWIN GREGORYONA
Final 12/4/2020 Not Ready for Inspection JONATHAN QUACH
Green Building Final 12/4/2020 Not Ready for Inspection JONATHAN QUACH
METHANE-Final 12/4/2020 Approved JONATHAN QUACH
METHANE-Rough 12/4/2020 Approved JONATHAN QUACH
Reinforced Concrete Frame 12/4/2020 Partial Inspection JONATHAN QUACH
Reinforced Masonry Frame 12/4/2020 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 12/4/2020 SGSOV Not Ready JONATHAN QUACH
Smoke Detectors 12/4/2020 Approved JONATHAN QUACH
Structural Steel Frame 12/4/2020 Not Ready for Inspection JONATHAN QUACH
Verify Sprinkler Sign Off 12/4/2020 Not Ready for Inspection JONATHAN QUACH
Special/Order Compliance 12/7/2020 Conditional Approval JONATHAN QUACH
Final 12/10/2020 OK for TCO EDWIN GREGORYONA
Green Building Final 12/10/2020 Partial Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 12/10/2020 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 12/10/2020 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 12/10/2020 SGSOV Not Ready EDWIN GREGORYONA
Structural Steel Frame 12/10/2020 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 12/10/2020 Approved EDWIN GREGORYONA
Final 12/18/2020 Not Ready for Inspection LARRY ARNICK
Green Building Final 12/18/2020 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 12/18/2020 SGSOV Approved LARRY ARNICK
Final 1/7/2021 Conditional Approval LARRY ARNICK
Green Building Final 1/7/2021 Approved LARRY ARNICK
Deputy Drilled-In Anchors 1/15/2021 Conditional Approval LARRY ARNICK
Final 5/14/2021 OK to Issue CofO EDWIN GREGORYONA
Special/Order Compliance 5/19/2021 Approved EDWIN GREGORYONA