21742 W CHATSWORTH ST 91311
Certificate Information: 21742 W CHATSWORTH ST 91311
- Application / Permit
- 18010-20000-00240
- Plan Check / Job No.
- B18VN01124
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 PER ENGINEERING
- Permit Issued
- Issued on 12/16/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2018 | APPLICANT |
| Green Plans Picked Up | 2/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2018 | JEFFREY TANGONAN |
| Corrections Issued | 3/1/2018 | JEFFREY TANGONAN |
| Quality Review Completed | 3/1/2018 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 3/6/2018 | APPLICANT |
| Plan Check Approved | 12/10/2019 | JEFFREY TANGONAN |
| Issued | 12/16/2019 | LADBS |
| CofO in Progress | 6/17/2024 | JEFFREY HARTLINE |
| Permit Finaled | 6/28/2024 | JOHN JANSON |
| CofO Issued | 6/28/2024 | JOHN JANSON |
| Permit Finaled | 6/28/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/13/2018 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/13/2018 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/13/2018 | LEE GUILBEAUX |
| Green Code | Cleared | 12/11/2018 | PARISA ZAHABI |
| Hydrant and Access approval | Cleared | 1/29/2019 | JOHN DALLAS |
| Miscellaneous | Cleared | 4/5/2019 | TOM HENRY |
| Low Impact Development | Cleared | 4/10/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 11/27/2019 | MARKOS PEREZ-BRAN |
| GPI Written Notices | Cleared | 12/10/2019 | JEFFREY TANGONAN |
| Grading Pre-Inspection | Cleared | 12/10/2019 | JEFFREY TANGONAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 91316, |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/20/2020 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 4/28/2020 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/11/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 6/11/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/22/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 6/22/2020 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/25/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 6/25/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Verify Sprinkler Sign Off | 6/25/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 7/30/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/20/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 10/20/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 10/29/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 10/29/2020 | Approved | DAVID SCANTLIN |
| Sewer | 10/29/2020 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 11/4/2020 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 11/4/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 11/4/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 11/4/2020 | Partial Approval | DAVID STEPANYAN |
| Interior/Exterior Lathing | 11/4/2020 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 11/12/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 11/12/2020 | Approved | DAVID STEPANYAN |
| Insulation | 11/12/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 11/17/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 11/17/2020 | Partial Approval | DAVID STEPANYAN |
| Interior/Exterior Lathing | 2/1/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 9/17/2021 | Approved | DAVID STEPANYAN |
| HVAC-Final | 9/17/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Final | 9/17/2021 | Corrections Issued | DAVID STEPANYAN |
| Final | 12/27/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 12/27/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/27/2021 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 12/27/2021 | Approved | TROY SANDERS |
| Smoke Detectors | 12/27/2021 | Approved | TROY SANDERS |
| Final | 6/14/2024 | OK to Issue CofO | JEFFREY HARTLINE |
| HVAC-Final | 6/14/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 6/14/2024 | Approved | JEFFREY HARTLINE |