601 S COMSTOCK AVE 90024
Certificate Information: 601 S COMSTOCK AVE 90024
- Application / Permit
- 18010-20000-00150
- Plan Check / Job No.
- B18VN00743
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (125'5" x 69'3") IRR. SHAPE 2 STORY DWELLING WITH ATTACHED 3-CAR GARAGE
- Permit Issued
- Issued on 9/6/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/25/2018 | JEFFREY TANGONAN |
| Corrections Issued | 1/29/2018 | JEFFREY TANGONAN |
| Quality Review Completed | 1/30/2018 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 1/31/2018 | APPLICANT |
| Green Plans Picked Up | 1/31/2018 | APPLICANT |
| Applicant returned to address corrections | 7/20/2018 | JEFFREY TANGONAN |
| Plan Check Approved | 8/15/2018 | JEFFREY TANGONAN |
| Issued | 9/6/2018 | LADBS |
| CofO in Progress | 2/24/2026 | ANDREW NAVE |
| Permit Finaled | 2/26/2026 | RICHARD STEINBACH |
| CofO Issued | 2/26/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/26/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2018 | LEE GUILBEAUX |
| CPC | Cleared | 7/18/2018 | DAISY BENICIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2018 | LEE GUILBEAUX |
| Permit | Cleared | 7/18/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/18/2018 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 7/20/2018 | JEFFREY TANGONAN |
| Grading Pre-Inspection | Cleared | 7/20/2018 | JEFFREY TANGONAN |
| Hydrant and Access approval | Cleared | 7/24/2018 | JOHN DALLAS |
| Low Impact Development | Cleared | 7/24/2018 | MITESH PATEL |
| Green Code | Cleared | 7/25/2018 | DAVID MATSON |
| Roof/Waste drainage to street | Cleared | 8/2/2018 | JOSEPH RHYU |
Contact Information
| Contractor | Ceilbright Services Inc; Lic. No.: 957706-B | 250 S BEVERLY DRIVE BEVERLY HILLS, CA 90212 |
| Engineer | Minas, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
| Engineer | Yuzon, Benigno S Jr; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
| Geologist | Minas, Shant; Lic. No.: EG2607 | 566 RIVERDALE DRIVE , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/25/2019 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 12/18/2019 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 1/27/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Steel/Welding | 2/6/2020 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Steel/Welding | 2/7/2020 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 2/28/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 2/28/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 4/24/2020 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 2/19/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Rough-Elec/Plmb/HVAC | 3/24/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 3/26/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 3/26/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 3/26/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deck | 4/5/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 4/5/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 4/5/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 4/7/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 4/12/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 4/12/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/13/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 6/10/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 6/10/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 7/14/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Insulation | 7/22/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Wood Frame | 7/22/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 7/23/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/25/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 8/25/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 9/3/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 9/16/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 9/16/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 9/16/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 9/29/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 10/13/2021 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/13/2021 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/14/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 10/19/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/22/2021 | Partial Approval | BRENDAN LOONEY |
| HVAC-Rough | 10/28/2021 | Approved | BRENDAN LOONEY |
| Wood Frame | 11/5/2021 | Partial Approval | BRENDAN LOONEY |
| Insulation | 11/15/2021 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 12/6/2021 | Partial Approval | KRISTEN CAUSEY |
| Green Building Rough | 12/6/2021 | Not Ready for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 12/7/2021 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 12/7/2021 | Partial Approval | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 12/7/2021 | Approved | BRENDAN LOONEY |
| Deputy Wood Construction | 12/9/2021 | Conditional Approval | MICHAEL PELHAM |
| Insulation | 12/13/2021 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 12/17/2021 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 12/23/2021 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 12/23/2021 | Approved | CHRISTOPHER WILSON |
| Pre-Inspection | 2/17/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 2/24/2022 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 3/30/2022 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 3/30/2022 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 4/11/2022 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 4/12/2022 | Approved | BRENDAN LOONEY |
| Gas Test | 4/15/2022 | Partial Approval | BRENDAN LOONEY |
| Deputy Wood Construction | 4/27/2022 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 5/6/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 5/6/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 5/6/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Rough-Elec/Plmb/HVAC | 5/13/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 6/14/2022 | Not Ready for Inspection | MICHAEL PELHAM |
| HVAC-Final | 6/17/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 6/23/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 6/24/2022 | Conditional Approval | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Not Ready | MICHAEL PELHAM |
| ELECTRICAL-Final | 9/12/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 9/21/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 11/15/2022 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 11/15/2022 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 11/15/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 11/18/2022 | Approved | STEPHANIE SWANSON |
| Final | 11/18/2022 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/18/2022 | Approved | STEPHANIE SWANSON |
| Green Building Final | 11/18/2022 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Approved | STEPHANIE SWANSON |
| Service/Power Release | 11/18/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Smoke Detectors | 11/18/2022 | Approved | STEPHANIE SWANSON |
| Final | 5/8/2024 | Corrections Issued | MICHAEL PELHAM |
| Service/Power Release | 5/13/2024 | Approved | MICHAEL PELHAM |
| Final | 2/24/2026 | OK to Issue CofO | ANDREW NAVE |