3092 N FRANKLIN CANYON DR 90210
Certificate Information: 3092 N FRANKLIN CANYON DR 90210
- Application / Permit
- 18010-20000-00115
- Plan Check / Job No.
- B18VN00658
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 14'-0"x 29'-0" IRR. SHAPED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 .PER ENGINEER.
- Permit Issued
- Issued on 7/20/2018
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2018 | APPLICANT |
| Green Plans Picked Up | 2/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2018 | TROY DEGUZMAN |
| Corrections Issued | 2/23/2018 | TROY DEGUZMAN |
| Quality Review Completed | 2/23/2018 | STEVEN KIM |
| Building Plans Picked Up | 2/28/2018 | APPLICANT |
| Applicant returned to address corrections | 4/6/2018 | TROY DEGUZMAN |
| Applicant returned to address corrections | 5/3/2018 | TROY DEGUZMAN |
| Applicant returned to address corrections | 5/15/2018 | TROY DEGUZMAN |
| Applicant returned to address corrections | 7/12/2018 | TROY DEGUZMAN |
| Plan Check Approved | 7/19/2018 | TROY DEGUZMAN |
| Issued | 7/20/2018 | LADBS |
| CofO in Progress | 3/30/2023 | RAUL BARAJAS |
| CofO in Progress | 3/31/2023 | RAUL BARAJAS |
| CofO in Progress | 4/18/2023 | STUART CHAPMAN |
| Permit Finaled | 4/23/2023 | DEROLD HAUFF |
| CofO Issued | 4/23/2023 | DEROLD HAUFF |
| Permit Finaled | 4/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2018 | MARKOS PEREZ-BRAN |
| Address approval | Cleared | 3/14/2018 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2018 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 3/14/2018 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 3/14/2018 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 3/20/2018 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 3/28/2018 | ROBERT DUFF |
| Low Impact Development | Cleared | 4/4/2018 | RYAN HUDSON |
| GPI Written Notices | Cleared | 5/3/2018 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 5/3/2018 | TROY DEGUZMAN |
| Specific Plan | Cleared | 6/21/2018 | ANDRE CALDERON |
| Drainage to Storm Drain | Cleared | 7/17/2018 | MAHELET GEBEYHU |
| Miscellaneous | Cleared | 7/17/2018 | MAHELET GEBEYHU |
| Watercourse | Cleared | 7/17/2018 | MAHELET GEBEYHU |
Contact Information
| Architect | Brouse, Jon Robert; Lic. No.: C22200 | 12930 VENTURA BLVD SUITE 214 STUDIO CITY, CA 91604 |
| Contractor | A G Builders & Development Corp; Lic. No.: 959503-B | 7657 WINNETKA AVE #341 WINNETKA, CA 91306 |
| Engineer | Arakelyan, Aram; Lic. No.: C82796 | 145 S GLENOAKS BLVD #328 BURBANK, CA 91502 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 8/15/2018 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 9/14/2018 | No Access for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 9/18/2018 | Not Ready for Inspection | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 9/27/2018 | Partial Approval | LUIS BARRALES |
| Footing/Foundation/Slab | 9/27/2018 | Partial Approval | LUIS BARRALES |
| Footing/Foundation/Slab | 10/4/2018 | Not Ready for Inspection | RAUL BARAJAS |
| Masonry Wall/Backfill | 10/4/2018 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 10/4/2018 | Partial Approval | RAUL BARAJAS |
| Masonry Wall/Backfill | 10/12/2018 | Partial Approval | RONALD COWAN |
| Reinforced Concrete Frame | 10/12/2018 | Partial Approval | RONALD COWAN |
| Reinforced Concrete Frame | 10/18/2018 | No Access for Inspection | RONALD COWAN |
| Deputy Steel/Welding | 11/13/2018 | Approved | RONALD COWAN |
| Deputy Steel/Welding | 11/20/2018 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2019 | Conditional Approval | RICHARD STEINBACH |
| Structural Steel Frame | 10/25/2019 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 12/12/2019 | Conditional Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 12/12/2019 | Approved | RICHARD STEINBACH |
| Green Building Rough | 12/12/2019 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 12/12/2019 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 12/12/2019 | Not Ready for Inspection | RICHARD STEINBACH |
| PLUMBING-Rough | 12/12/2019 | Approved | RICHARD STEINBACH |
| Insulation | 1/2/2020 | Not Ready for Inspection | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 1/10/2020 | Approved | RICHARD STEINBACH |
| Insulation | 1/10/2020 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 1/10/2020 | Partial Approval | RICHARD STEINBACH |
| Verify Sprinkler Sign Off | 1/10/2020 | Approved | RICHARD STEINBACH |
| Drywall Nailing | 1/24/2020 | Approved | RICHARD STEINBACH |
| Deputy Steel/Welding | 2/19/2020 | Conditional Approval | RICHARD STEINBACH |
| Final | 10/22/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/22/2021 | Approved | RAUL BARAJAS |
| Green Building Final | 10/22/2021 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 10/22/2021 | SGSOV Approved | RAUL BARAJAS |
| Service/Power Release | 10/22/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Smoke Detectors | 10/22/2021 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 10/14/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 10/19/2022 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 10/19/2022 | Approved | RAUL BARAJAS |
| Service/Power Release | 10/19/2022 | Corrections Issued | RAUL BARAJAS |
| Service/Power Release | 11/30/2022 | Partial Inspection | RAUL BARAJAS |
| Final | 12/5/2022 | Corrections Issued | RAUL BARAJAS |
| Service/Power Release | 3/17/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 3/20/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Service/Power Release | 3/20/2023 | Approved | RAUL BARAJAS |
| Final | 3/30/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 4/17/2023 | OK to Issue CofO | STUART CHAPMAN |