10069 N LEV AVE 91331

Certificate Information: 10069 N LEV AVE 91331

Application / Permit
18010-20000-00105
Plan Check / Job No.
B18VN00584
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 29'4"X31'8" IRREGULAR SHAPED 2-STORY ADU WITH 29'4"X28'8" IRREGULAR SHAPED DECK PER AB 494 AND SB 229
Permit Issued
Issued on 2/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2018 APPLICANT
Assigned to Plan Check Engineer 1/18/2018 MARVEL DELACRUZ
Corrections Issued 1/20/2018 MARVEL DELACRUZ
Green Plans Picked Up 1/23/2018 APPLICANT
Quality Review Completed 1/25/2018 DOUGLAS NAKATANI
Building Plans Picked Up 1/26/2018 APPLICANT
Applicant returned to address corrections 10/17/2019 MARVEL DELACRUZ
Applicant returned to address corrections 12/6/2019 MARVEL DELACRUZ
Plan Check Approved 12/9/2019 MARVEL DELACRUZ
Issued 2/12/2020 LADBS
CofO in Progress 7/25/2022 MICHEL ABAJAN
Permit Finaled 7/29/2022 DANIEL ORRANTE
CofO Issued 7/29/2022 DANIEL ORRANTE
Permit Finaled 7/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/13/2018 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 6/13/2018 CHRISTINE REUSCH
Green Code Cleared 6/13/2018 SARKIS HARABEDIAN
Sewer availability Cleared 7/3/2018 EDUARDO PEDROZA
Construction near power lines Cleared 6/13/2019 RIDWAN HARDY
Low Impact Development Cleared 10/16/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 10/16/2019 ERIK BEASLEY

Contact Information

Contractor Powerful General Construction Inc; Lic. No.: 1047342-B 10069 LEV AVE      ARLETA, CA 91331
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/18/2020 Corrections Issued MICHEL ABAJAN
METHANE-Barrier 5/18/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Subgrade 5/18/2020 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 6/17/2020 Approved MICHEL ABAJAN
METHANE-Barrier 6/17/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 6/17/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 7/8/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 7/21/2020 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/21/2020 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 7/23/2020 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 7/27/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/7/2020 Partial Approval MICHEL ABAJAN
Gas Test 10/7/2020 Partial Approval MICHEL ABAJAN
Underground Mechanical 10/7/2020 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 4/27/2021 Approved MICHEL ABAJAN
HVAC-Rough 4/27/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 4/27/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/30/2021 Approved MICHEL ABAJAN
Green Building Rough 4/30/2021 Approved MICHEL ABAJAN
METHANE-Rough 4/30/2021 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 4/30/2021 Approved MICHEL ABAJAN
Insulation 5/12/2021 Approved JAVIER RAMOS JR
Pre-Inspection 5/12/2021 Partial Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 5/27/2021 Approved MICHEL ABAJAN
Drywall Nailing 8/18/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/7/2022 SGSOV Not Ready MICHEL ABAJAN
ELECTRICAL-Final 7/13/2022 Approved MICHEL ABAJAN
Final 7/13/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 7/13/2022 Approved MICHEL ABAJAN
HVAC-Final 7/13/2022 Approved MICHEL ABAJAN
PLUMBING-Final 7/13/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/13/2022 SGSOV Approved MICHEL ABAJAN
Service/Power Release 7/13/2022 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 7/13/2022 Approved MICHEL ABAJAN
Final 7/25/2022 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 7/25/2022 Approved MICHEL ABAJAN