724 N CRANE BLVD 90065
Certificate Information: 724 N CRANE BLVD 90065
- Application / Permit
- 18010-20000-00047
- Plan Check / Job No.
- B18VN00214
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2 story single family dwelling with 2-car carport at basement and roof deck.
- Permit Issued
- Issued on 1/8/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/28/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 2/8/2018 | DANNY MORALES |
| Corrections Issued | 2/21/2018 | DANNY MORALES |
| Quality Review Completed | 2/23/2018 | STEVEN KIM |
| Building Plans Picked Up | 2/27/2018 | APPLICANT |
| Green Plans Picked Up | 2/27/2018 | APPLICANT |
| Applicant returned to address corrections | 11/29/2018 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 12/12/2018 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 12/21/2018 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 1/3/2019 | JEFFREY TANGONAN |
| Plan Check Approved | 1/8/2019 | JEFFREY TANGONAN |
| Issued | 1/8/2019 | LADBS |
| CofO in Progress | 8/24/2020 | OSVALDO PARAMO |
| Permit Finaled | 9/28/2020 | DEROLD HAUFF |
| CofO Issued | 9/28/2020 | DEROLD HAUFF |
| Permit Finaled | 9/28/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/28/2018 | KENNETH PHAM |
| BHO/Hillside ordinance | Cleared | 3/28/2018 | KENNETH PHAM |
| BHO/Hillside ordinance | Cleared | 3/28/2018 | KENNETH PHAM |
| BHO/Hillside ordinance | Cleared | 3/28/2018 | KENNETH PHAM |
| Permit | Cleared | 3/28/2018 | KENNETH PHAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2018 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 4/11/2018 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 4/11/2018 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 4/11/2018 | ADRIAN SANCHEZ |
| Green Code | Cleared | 4/19/2018 | PARISA ZAHABI |
| Miscellaneous | Cleared | 11/6/2018 | DENNIS CHEW |
| Specific Plan | Cleared | 11/6/2018 | DENNIS CHEW |
| Distance to fire station | Cleared | 12/20/2018 | GILBERT URREA |
| Hydrant and Access approval | Cleared | 12/20/2018 | GILBERT URREA |
| Miscellaneous | Cleared | 12/20/2018 | HERMINIGILDO AGUSTIN |
| GPI Written Notices | Cleared | 12/21/2018 | DANNY MORALES |
| Grading Pre-Inspection | Cleared | 12/21/2018 | DANNY MORALES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jitechian, Ara; Lic. No.: C54893 | 9433 VIA PATRICIA BURBANK, CA 91504 |
| Engineer | Paniagua, Cristobal; Lic. No.: C72894 | 1538 W 92ND ST LOS ANGELES, CA 90047 |
| Geologist | Miller, Steven Burl; Lic. No.: EG1303 | 23890 COPPERHILL DRIVE #111 VALENCIA, CA 91354 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/10/2019 | Partial Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/15/2019 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/23/2019 | Partial Approval | BRIAN SULLIVAN |
| Masonry Wall/Backfill | 6/10/2019 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/21/2019 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/1/2019 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/15/2019 | No Access for Inspection | RAUL BARAJAS |
| Masonry Wall/Backfill | 7/19/2019 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/23/2019 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 8/27/2019 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/12/2019 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/17/2019 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/29/2019 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 11/7/2019 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2019 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 12/13/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 12/13/2019 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2020 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 1/24/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 1/24/2020 | Corrections Issued | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 1/24/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 2/24/2020 | No Access for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 2/26/2020 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/9/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 4/9/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 4/9/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 4/9/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 4/13/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 4/14/2020 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 4/16/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 4/16/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 4/16/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/20/2020 | Partial Inspection | OSVALDO PARAMO |
| Green Building Rough | 4/20/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 4/20/2020 | Approved | OSVALDO PARAMO |
| Wood Frame | 4/20/2020 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/21/2020 | Approved | OSVALDO PARAMO |
| Green Building Rough | 4/21/2020 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 5/7/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/7/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/14/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/14/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 6/10/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Underground Mechanical | 6/15/2020 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 7/2/2020 | Approved | ROBERT VORHIS |
| PLUMBING-Final | 7/2/2020 | Partial Approval | ROBERT VORHIS |
| Final | 7/8/2020 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/8/2020 | Approved | OSVALDO PARAMO |
| Green Building Final | 7/8/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Final | 7/8/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 7/8/2020 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/8/2020 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 7/8/2020 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 7/8/2020 | Approved | OSVALDO PARAMO |
| Final | 7/10/2020 | Corrections Issued | OSVALDO PARAMO |
| Final | 7/24/2020 | Partial Inspection | RUBEN SALAS |
| Green Building Final | 7/24/2020 | Partial Inspection | RUBEN SALAS |
| Service/Power Release | 7/24/2020 | Not Ready for Inspection | RUBEN SALAS |
| Service/Power Release | 7/29/2020 | Approved | OSVALDO PARAMO |
| Final | 8/24/2020 | OK to Issue CofO | OSVALDO PARAMO |
| Green Building Final | 8/24/2020 | Approved | OSVALDO PARAMO |