6101 W 96TH ST ITF-WEST-FACILITY 90045

Certificate Information: 6101 W 96TH ST ITF-WEST-FACILITY 90045

Application / Permit
18010-10008-06022
Plan Check / Job No.
B20LA07853
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(7) Parking Garage
Work Description
**LAX APM** ITFW FACILITY DEFERRED SUBMITTAL FOR POST TENSION "PORTION C" FOR FLOORS 2 TO 4.
Permit Issued
Issued on 7/16/2020
Issuing Office
Current Status
Permit Finaled on 7/21/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/4/2020 APPLICANT
Assigned to Plan Check Engineer 5/5/2020 CATHERINE CHEN
Corrections Issued 5/12/2020 CATHERINE CHEN
Applicant returned to address corrections 5/28/2020 CATHERINE CHEN
Applicant returned to address corrections 6/26/2020 CATHERINE CHEN
Plan Check Approved 7/16/2020 CATHERINE CHEN
Issued 7/16/2020 APPLICANT
Permit Finaled 7/21/2021 JEFF BYTHEWAY

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Swinerton Builders; Lic. No.: 92-A 260 TOWNSEND ST 5TH FL-LEGAL      SAN FRANCISCO, CA 94107
Engineer Haney,, Norman Lee; Lic. No.: C36532 PO BOX 10516      GLENDALE, AZ 85318

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Pre-Stress Concrete 7/21/2020 Conditional Approval JONATHAN ALLEN
Deputy Reinf. Concrete 7/21/2020 Conditional Approval JONATHAN ALLEN
Deputy Pre-Stress Concrete 7/22/2020 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/22/2020 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 7/23/2020 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/23/2020 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 7/24/2020 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/24/2020 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 7/27/2020 Conditional Approval ALAN NOVAK
Deputy Reinf. Concrete 7/27/2020 Conditional Approval ALAN NOVAK
Excavation/Setback/Form/Re-Bar 7/27/2020 Partial Approval JEFF BYTHEWAY
Deputy Pre-Stress Concrete 7/28/2020 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/28/2020 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 7/29/2020 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/29/2020 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 7/30/2020 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/30/2020 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 7/30/2020 Partial Approval JEFF BYTHEWAY
Deputy Pre-Stress Concrete 7/31/2020 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/31/2020 Approved JEFF BYTHEWAY
Deputy Pre-Stress Concrete 8/3/2020 Conditional Approval TED RIES
Deputy Reinf. Concrete 8/3/2020 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 8/3/2020 Partial Approval TED RIES
Deputy Pre-Stress Concrete 9/4/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 9/4/2020 Approved NICK LAROCCA
Deputy Drilled-In Anchors 9/8/2020 Approved NICK LAROCCA
Deputy Pre-Stress Concrete 9/8/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 9/8/2020 Approved NICK LAROCCA
Deputy Steel/Welding 9/8/2020 Approved NICK LAROCCA
Reinforced Concrete Frame 9/8/2020 Partial Approval TED RIES
Structural Steel Frame 9/8/2020 Not Ready for Inspection NICK LAROCCA
Deputy Drilled-In Anchors 9/9/2020 Approved NICK LAROCCA
Deputy Pre-Stress Concrete 9/9/2020 Approved NICK LAROCCA
Deputy Reinf. Concrete 9/9/2020 Approved NICK LAROCCA
Deputy Steel/Welding 9/9/2020 Approved NICK LAROCCA
Deputy Drilled-In Anchors 9/10/2020 Conditional Approval ALAN NOVAK
Deputy Pre-Stress Concrete 9/10/2020 Conditional Approval ALAN NOVAK
Deputy Reinf. Concrete 9/10/2020 Conditional Approval ALAN NOVAK
Deputy Steel/Welding 9/10/2020 Conditional Approval ALAN NOVAK
Deputy Drilled-In Anchors 9/11/2020 Conditional Approval TED RIES
Deputy Pre-Stress Concrete 9/11/2020 Conditional Approval TED RIES
Deputy Reinf. Concrete 9/11/2020 Conditional Approval TED RIES
Deputy Steel/Welding 9/11/2020 Conditional Approval TED RIES
Reinforced Concrete Frame 9/11/2020 Partial Approval TED RIES
Deputy Drilled-In Anchors 9/14/2020 Approved JONATHAN ALLEN
Deputy Pre-Stress Concrete 9/14/2020 Approved JONATHAN ALLEN
Deputy Reinf. Concrete 9/14/2020 Partial Approval JONATHAN ALLEN
Deputy Drilled-In Anchors 9/15/2020 Conditional Approval ALAN NOVAK
Deputy Pre-Stress Concrete 9/15/2020 Conditional Approval ALAN NOVAK
Deputy Reinf. Concrete 9/15/2020 Conditional Approval ALAN NOVAK
Deputy Drilled-In Anchors 9/16/2020 Approved JONATHAN ALLEN
Deputy Pre-Stress Concrete 9/16/2020 Approved JONATHAN ALLEN
Deputy Reinf. Concrete 9/16/2020 Approved JONATHAN ALLEN
Deputy Steel/Welding 9/16/2020 Approved JONATHAN ALLEN
Deputy Drilled-In Anchors 9/17/2020 Approved JONATHAN ALLEN
Deputy Pre-Stress Concrete 9/17/2020 Approved JONATHAN ALLEN
Deputy Reinf. Concrete 9/17/2020 Approved JONATHAN ALLEN
Deputy Steel/Welding 9/17/2020 Approved JONATHAN ALLEN
Reinforced Concrete Frame 9/17/2020 Partial Approval JONATHAN ALLEN
Deputy Drilled-In Anchors 9/18/2020 Approved JONATHAN ALLEN
Deputy Pre-Stress Concrete 9/18/2020 Approved JONATHAN ALLEN
Deputy Reinf. Concrete 9/18/2020 Approved JONATHAN ALLEN
Deputy Steel/Welding 9/18/2020 Approved JONATHAN ALLEN
Deputy Drilled-In Anchors 9/21/2020 Conditional Approval TED RIES
Deputy Pre-Stress Concrete 9/21/2020 Conditional Approval TED RIES
Deputy Steel/Welding 9/21/2020 Conditional Approval TED RIES
Reinforced Concrete Frame 9/21/2020 Partial Approval TED RIES
Deputy Drilled-In Anchors 9/22/2020 Conditional Approval TED RIES
Deputy Pre-Stress Concrete 9/22/2020 Conditional Approval TED RIES
Deputy Steel/Welding 9/22/2020 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 10/5/2020 Partial Approval NICK LAROCCA
Final 7/21/2021 Permit Finaled JEFF BYTHEWAY