150 W CENTER WAY CTA-East-Station 90045
Certificate Information: 150 W CENTER WAY CTA-East-Station 90045
- Application / Permit
- 18010-10004-04778
- Plan Check / Job No.
- B19LA07905
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (3) Airport Building
- Work Description
- LAX APM: EARLY START FOR FOUNDATION PERMIT (CIDH PILE, LOWER COLUMN AND CONCOURSE BENT CAPS) FOR NEW CENTRAL TERMINAL AREA (CTA) EAST STATION FOR LAX AUTOMATED PEOPLE MOVER PROJECT.
- Permit Issued
- Issued on 8/14/2019
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/22/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2019 | JOHN FRANCIA |
| Plan Check Approved | 8/13/2019 | JOHN FRANCIA |
| Issued | 8/14/2019 | LADBS |
| Permit Finaled | 9/22/2021 | JONATHAN ALLEN |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2019 | MARYAM AZARBAYJANI |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2019 | MARYAM AZARBAYJANI |
| City owned building/parcel | Cleared | 6/21/2019 | HAROOT AVANESIAN |
| ZA Case | Cleared | 6/25/2019 | KIT AWAKUNI |
| ZA Case | Cleared | 6/25/2019 | KIT AWAKUNI |
| ZA Case | Cleared | 6/25/2019 | KIT AWAKUNI |
| ZA Case | Cleared | 6/25/2019 | KIT AWAKUNI |
| Hydrant and Access approval | Cleared | 6/27/2019 | JOHN CONNEALLY |
| Project Permit | Cleared | 7/9/2019 | MINYE PAK |
| Highway dedication | Cleared | 7/10/2019 | MARYAM AZARBAYJANI |
| Permit | Cleared | 7/10/2019 | MARYAM AZARBAYJANI |
| Roof/Waste drainage to street | Cleared | 7/10/2019 | MARYAM AZARBAYJANI |
| Sewer availability | Cleared | 7/10/2019 | MARYAM AZARBAYJANI |
| Tract Map conditions | Cleared | 7/11/2019 | SOPHIE GABEL-SCHEINBAU |
| Construction near power lines | Cleared | 7/15/2019 | OSCAR CASTRO |
| Driveway location | Cleared | 7/17/2019 | PEDRO AYALA |
| Internal circulation | Cleared | 7/17/2019 | PEDRO AYALA |
| Specific Plan | Cleared | 7/17/2019 | PEDRO AYALA |
| Tract Map conditions | Cleared | 7/17/2019 | DIANA JIMENEZ |
| Low Impact Development | Cleared | 7/18/2019 | ORVAL HERNANDEZ-MARCI |
| Stormwater Pollution Mitigatn | Cleared | 7/22/2019 | ORVAL HERNANDEZ-MARCI |
| Trees in Parkway | Cleared | 7/24/2019 | ADRIAN SANCHEZ |
| DAS Clearance | Cleared | 7/29/2019 | JOHN FRANCIA |
| Airport buildings | Cleared | 7/30/2019 | ANDREW KO |
| Green Code | Cleared | 8/1/2019 | DONALD CRICHLOW |
| Building over 3-story or 36-ft | Cleared | 8/13/2019 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 8/13/2019 | CALOSHA APPROVED |
Contact Information
| Architect | Gonzales,, Anthony Chris; Lic. No.: C19409 | 452 35TH STREET MANHATTAN BEACH, CA 90266 |
| Architect | Youn,, Heesik; Lic. No.: C32969 | 4770 ARBORS CIRCLE MUKILTEO, WA 98275 |
| Contractor | Fluor Flatiron Balfour Beatty Dragados; Lic. No.: 1036344-B | 5050 BUSINESS CENTER DRIVE SUITE 250 FAIRFIELD, CA 94534 |
| Engineer | Fontaine,, Eric Stuart; Lic. No.: S5930 | 870 ANTILLA WAY SAN MARCOS, CA 92078 |
| Engineer | Kashighandi,, Pirooz; Lic. No.: GE3104 | 1417 S WESTGATE AVE 207 LOS ANGELES, CA 90025 |
| Engineer | Kavianipour,, Fatemeh; Lic. No.: C85374 | 550 WEST C STREET STE 1200 SAN DIEGO, CA 92101 |
| Engineer | Werts,, Chester Anthony; Lic. No.: C49861 | 5449 40TH AVE SW OLYMPIA, WA 98512 |
Inspector Information
| NICK LAROCCA, (213) 473-2153 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 10/31/2019 | Approved | JONATHAN ALLEN |
| Final | 10/31/2019 | Off-Hour Fees Due | |
| Final | 10/31/2019 | Partial Approval | JONATHAN ALLEN |
| Green Building Final | 10/31/2019 | Approved | JONATHAN ALLEN |
| Green Building Final | 10/31/2019 | Off-Hour Fees Due | |
| Piling/Pier/Caisson | 10/31/2019 | Off-Hour Fees Due | |
| Piling/Pier/Caisson | 10/31/2019 | Partial Approval | JONATHAN ALLEN |
| Smoke Detectors | 10/31/2019 | Approved | JONATHAN ALLEN |
| Smoke Detectors | 10/31/2019 | Off-Hour Fees Due | |
| Piling/Pier/Caisson | 11/2/2019 | Partial Approval | JONATHAN ALLEN |
| Deputy Grading | 11/5/2019 | Approved | JONATHAN ALLEN |
| Final | 11/8/2019 | Not Ready for Inspection | NICK LAROCCA |
| Grading Pre-Inspection | 11/8/2019 | Approved | NICK LAROCCA |
| Green Building Final | 11/8/2019 | Not Ready for Inspection | NICK LAROCCA |
| Piling/Pier/Caisson | 11/8/2019 | Partial Approval | NICK LAROCCA |
| Smoke Detectors | 11/8/2019 | Not Ready for Inspection | NICK LAROCCA |
| Deputy Other (see comments) | 11/19/2019 | Approved | JONATHAN ALLEN |
| Deputy Grading | 11/21/2019 | Approved | JONATHAN ALLEN |
| Final | 12/19/2019 | Off-Hour Fees Due | |
| Green Building Final | 12/19/2019 | Off-Hour Fees Due | |
| Piling/Pier/Caisson | 12/19/2019 | Off-Hour Fees Due | |
| Smoke Detectors | 12/19/2019 | Off-Hour Fees Due | |
| Final | 12/24/2019 | Not Ready for Inspection | JONATHAN ALLEN |
| Final | 12/24/2019 | Off-Hour Fees Due | |
| Green Building Final | 12/24/2019 | Approved | JONATHAN ALLEN |
| Green Building Final | 12/24/2019 | Off-Hour Fees Due | |
| Piling/Pier/Caisson | 12/24/2019 | Not Ready for Inspection | JONATHAN ALLEN |
| Piling/Pier/Caisson | 12/24/2019 | Off-Hour Fees Due | |
| Smoke Detectors | 12/24/2019 | Approved | JONATHAN ALLEN |
| Smoke Detectors | 12/24/2019 | Off-Hour Fees Due | |
| Piling/Pier/Caisson | 1/22/2020 | Partial Approval | JONATHAN ALLEN |
| Reinforced Concrete Frame | 1/22/2020 | Partial Approval | JONATHAN ALLEN |
| Piling/Pier/Caisson | 1/23/2020 | Partial Approval | JONATHAN ALLEN |
| Piling/Pier/Caisson | 1/24/2020 | Partial Approval | JONATHAN ALLEN |
| Piling/Pier/Caisson | 1/28/2020 | Partial Approval | JONATHAN ALLEN |
| Piling/Pier/Caisson | 1/30/2020 | No Result Entered | JONATHAN ALLEN |
| Piling/Pier/Caisson | 1/30/2020 | Partial Approval | JONATHAN ALLEN |
| Footing/Foundation/Slab | 2/18/2020 | Partial Approval | JONATHAN ALLEN |
| Piling/Pier/Caisson | 2/20/2020 | Partial Approval | JONATHAN ALLEN |
| Reinforced Concrete Frame | 3/5/2020 | Partial Approval | JONATHAN ALLEN |
| Pre-Inspection | 3/12/2020 | Approved | JONATHAN ALLEN |
| Pre-Inspection | 3/16/2020 | Approved | JONATHAN ALLEN |
| Pre-Inspection | 3/21/2020 | Partial Approval | JONATHAN ALLEN |
| Pre-Inspection | 4/15/2020 | Approved | JONATHAN ALLEN |
| Pre-Inspection | 4/16/2020 | Partial Approval | JONATHAN ALLEN |
| Pre-Inspection | 4/17/2020 | Approved | JONATHAN ALLEN |
| Pre-Inspection | 4/20/2020 | Partial Approval | JONATHAN ALLEN |
| Pre-Inspection | 4/21/2020 | Partial Approval | JONATHAN ALLEN |
| Pre-Inspection | 4/22/2020 | Approved | JONATHAN ALLEN |
| Pre-Inspection | 4/23/2020 | Partial Approval | JONATHAN ALLEN |
| Pre-Inspection | 4/24/2020 | Conditional Approval | ALBERT COMISARI |
| Pre-Inspection | 4/28/2020 | Approved | JONATHAN ALLEN |
| Pre-Inspection | 4/29/2020 | Approved | JONATHAN ALLEN |
| Pre-Inspection | 5/1/2020 | Approved | JONATHAN ALLEN |
| Reinforced Concrete Frame | 5/1/2020 | Partial Approval | JONATHAN ALLEN |
| Pre-Inspection | 5/4/2020 | Partial Approval | JONATHAN ALLEN |
| Pre-Inspection | 5/5/2020 | Not Ready for Inspection | JONATHAN ALLEN |
| Reinforced Concrete Frame | 5/5/2020 | Not Ready for Inspection | JONATHAN ALLEN |
| Pre-Inspection | 5/6/2020 | Not Ready for Inspection | JONATHAN ALLEN |
| Pre-Inspection | 5/7/2020 | Approved | JONATHAN ALLEN |
| Pre-Inspection | 8/3/2020 | Partial Approval | JONATHAN ALLEN |
| Pre-Inspection | 8/4/2020 | Approved | JONATHAN ALLEN |
| Pre-Inspection | 10/20/2020 | Approved | JONATHAN ALLEN |