1537 S WILTON PL 1-22 90019

Certificate Information: 1537 S WILTON PL 1-22 90019

Application / Permit
18010-10004-03493
Plan Check / Job No.
B22LA14007
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SUPPLEMENTAL PERMIT TO 18010-10000-03493. EXISITING GYM TO BE CONVERTED INTO ADU. EXISITING STUDIO UNIT TO BE CONVERTED TO 1 BEDROOM UNIT AND REVISE STRUCTURAL PLAN.
Permit Issued
Issued on 12/14/2022
Issuing Office
Metro
Current Status
Permit Finaled on 4/6/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/18/2022 APPLICANT
Assigned to Plan Check Engineer 7/28/2022 ERIC WONG
Corrections Issued 7/30/2022 ERIC WONG
Quality Review Completed 8/5/2022 PETER KIM
Green Plans Picked Up 8/8/2022 APPLICANT
Building Plans Picked Up 8/12/2022 APPLICANT
Disabled Access Plans Picked Up 9/8/2022 APPLICANT
Applicant returned to address corrections 9/30/2022 ERIC WONG
Plan Check Approved 12/2/2022 ERIC WONG
Issued 12/14/2022 APPLICANT
Permit Finaled 4/3/2026 JOEY BUCHANAN

Permit Application Clearance Information

Address approval Cleared 9/8/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 9/12/2022 CINDY QI
Sewer availability Cleared 9/12/2022 CINDY QI
Miscellaneous Cleared 9/13/2022 KENTON TRINH
Green Code Cleared 9/29/2022 AARON COSTA
Fire Marshal Fire Life Safety Cleared 10/28/2022 DOMINIQUE MEDINA
DAS Clearance Cleared 11/17/2022 ELIZABETH TOMS

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: C22356 3435 WILSHIRE BLVD #2905      LOS ANGELES, CA 90010
Contractor Fei Enterprises Inc; Lic. No.: 659252-B 5967 W 3RD ST   100    LOS ANGELES, CA 90036
Engineer Hill,, Edward Foster; Lic. No.: GE2126 27865 AMBERWOOD LANE      VALENCIA, CA 91354
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/21/2023 Partial Approval JAMES POWERS
Insulation 11/29/2023 Partial Inspection NICK DANERI
Wood Frame 11/29/2023 Conditional Approval NICK DANERI
Final 1/6/2025 Not Ready for Inspection NICK DANERI
Green Building Final 1/6/2025 Not Ready for Inspection NICK DANERI
Green Building Rough 1/6/2025 Approved NICK DANERI
METHANE-Final 1/6/2025 Not Ready for Inspection NICK DANERI
METHANE-Rough 1/6/2025 Approved NICK DANERI
Reinforced Concrete Frame 1/6/2025 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 1/6/2025 Not Ready for Inspection NICK DANERI
Smoke Detectors 1/6/2025 Not Ready for Inspection NICK DANERI
Final 4/3/2026 Permit Finaled JOEY BUCHANAN
Green Building Final 4/3/2026 Approved JOEY BUCHANAN
METHANE-Final 4/3/2026 Approved JOEY BUCHANAN
METHANE-Rough 4/3/2026 Approved JOEY BUCHANAN
Reinforced Concrete Frame 4/3/2026 Approved JOEY BUCHANAN
Reinforced Masonry Frame 4/3/2026 Approved JOEY BUCHANAN
Smoke Detectors 4/3/2026 Approved JOEY BUCHANAN