7560 WORLD WAY 90045
Certificate Information: 7560 WORLD WAY 90045
- Application / Permit
- 18010-10001-06324
- Plan Check / Job No.
- B19LA05640
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (3) Aircraft Hanger
- Work Description
- PROPOSED EARLY START PERMIT FOR FOUNDATION ONLY FOR 1-STORY L-SHAPED 287' X 232'-9" GROUND SUPPORT EQUIPMENT (GSE) MAINTANANCE BUILDING FOR DELTA HANGAR. See commnets.
- Permit Issued
- Issued on 4/8/2019
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2019 | EDUARDO RODRIGUEZ |
| Corrections Issued | 4/1/2019 | EDUARDO RODRIGUEZ |
| Plan Check Approved | 4/4/2019 | EDUARDO RODRIGUEZ |
| Issued | 4/8/2019 | LADBS |
| Permit Finaled-Status Void | 1/15/2020 | JONATHAN ALLEN |
| Re-Activate Permit | 2/26/2020 | JONATHAN ALLEN |
| Permit Finaled | 2/26/2020 | JONATHAN ALLEN |
Permit Application Clearance Information
| Abandoned oil well | Cleared | 3/20/2019 | JOHN CONNEALLY |
| Abandoned oil well approval | Cleared | 3/20/2019 | JOHN CONNEALLY |
| Address approval | Cleared | 3/20/2019 | ERIK BEASLEY |
| DAS Clearance | Cleared | 3/20/2019 | EDUARDO RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 3/20/2019 | PATRICK MISCHLICH |
| Green Code | Cleared | 3/20/2019 | EDUARDO RODRIGUEZ |
| Hydrant and Access approval | Cleared | 3/20/2019 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 3/20/2019 | MITESH PATEL |
| Miscellaneous | Cleared | 3/20/2019 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 3/20/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/20/2019 | ERIK BEASLEY |
| City owned building/parcel | Cleared | 3/21/2019 | HAROOT AVANESIAN |
| Airport buildings | Cleared | 3/22/2019 | ANDREW KO |
| Project Permit | Cleared | 3/26/2019 | EDUARDO RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/28/2019 | ROBYN STEELE |
| GPI Written Notices | Cleared | 3/28/2019 | EDUARDO RODRIGUEZ |
Contact Information
| Architect | Ganiere,, Christopher R; Lic. No.: C29178 | 2822 LA SALLE AVENUE COSTA MESA, CA 92626 |
| Contractor | Burns & Mc Donnell Engineering Company Inc; Lic. No.: 755238-B | 9400 WARD PARKWAY KANSAS CITY, MO 64114 |
| Engineer | Brettman,, Barie Blain; Lic. No.: S3348 | 11537 CARTER STREET OVERLAND PARK, KS 66210 |
| Engineer | Ingraham,, Clinton Curtis; Lic. No.: C44780 | 451 E VANDERBILT WY STE 200 SAN BERNARDINO, CA 92408 |
| Engineer | Saiki,, Garreth Masuo; Lic. No.: GE2509 | 27172 NEDA MISSION VIEJO, CA 92692 |
Inspector Information
| NICK LAROCCA, (213) 473-2153 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 4/9/2019 | Conditional Approval | ALAN NOVAK |
| Piling/Pier/Caisson | 4/9/2019 | Partial Approval | ALAN NOVAK |
| Deputy Grading | 4/10/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 4/10/2019 | Conditional Approval | ALAN NOVAK |
| Piling/Pier/Caisson | 4/10/2019 | Partial Approval | ALAN NOVAK |
| Deputy Grading | 4/11/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 4/11/2019 | Conditional Approval | ALAN NOVAK |
| Piling/Pier/Caisson | 4/11/2019 | Partial Approval | ALAN NOVAK |
| Deputy Grading | 4/12/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 4/12/2019 | Conditional Approval | ALAN NOVAK |
| Piling/Pier/Caisson | 4/12/2019 | Partial Approval | ALAN NOVAK |
| Deputy Grading | 4/15/2019 | Conditional Approval | ALAN NOVAK |
| Piling/Pier/Caisson | 4/15/2019 | Partial Approval | ALAN NOVAK |
| Deputy Grading | 4/16/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Grading | 4/17/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Grading | 4/22/2019 | Conditional Approval | ALAN NOVAK |
| Piling/Pier/Caisson | 4/22/2019 | Partial Approval | ALAN NOVAK |
| Deputy Grading | 4/23/2019 | Conditional Approval | ALAN NOVAK |
| Piling/Pier/Caisson | 4/23/2019 | Partial Approval | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 5/2/2019 | Partial Inspection | ALAN NOVAK |
| Excavation/Setback/Form/Re-Bar | 5/3/2019 | Not Ready for Inspection | TIMOTHY GRIFFITH |
| Excavation/Setback/Form/Re-Bar | 5/6/2019 | No Access for Inspection | ALAN NOVAK |
| Pre-Inspection | 5/7/2019 | Approved | ALAN NOVAK |
| Deputy Grading | 5/9/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Grading | 5/10/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 5/15/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Grading | 5/16/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Reinf. Concrete | 5/16/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Grading | 5/20/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Grading | 5/21/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Grading | 5/22/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Methane Barrier | 5/22/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Grading | 5/23/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Methane Barrier | 5/23/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Grading | 5/24/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Methane Barrier | 5/24/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Methane Barrier | 6/6/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Methane Barrier | 6/7/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 6/11/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Reinf. Concrete | 6/12/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Reinf. Concrete | 6/13/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Reinf. Concrete | 6/14/2019 | Conditional Approval | TIMOTHY GRIFFITH |
| Deputy Reinf. Concrete | 6/17/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 6/18/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 6/19/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 6/20/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 6/21/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 6/24/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 6/25/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 6/26/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 6/27/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 6/28/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/1/2019 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/2/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 7/3/2019 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/5/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/8/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 7/9/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 7/9/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Grading | 7/10/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 7/10/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 7/10/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Grading | 7/11/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 7/11/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 7/11/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Grading | 7/12/2019 | Conditional Approval | ALBERT COMISARI |
| Deputy Reinf. Concrete | 7/12/2019 | Conditional Approval | ALBERT COMISARI |
| Deputy Steel/Welding | 7/12/2019 | Conditional Approval | ALBERT COMISARI |
| Deputy Reinf. Concrete | 7/15/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 7/15/2019 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 7/16/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/16/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/17/2019 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/18/2019 | Approved | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/18/2019 | Partial Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/19/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/19/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/22/2019 | Approved | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/22/2019 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/23/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/23/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/24/2019 | Approved | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/24/2019 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/25/2019 | Approved | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/25/2019 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 7/26/2019 | Approved | JONATHAN ALLEN |
| Deputy Steel/Welding | 7/26/2019 | Approved | JONATHAN ALLEN |
| Deputy Drilled-In Anchors | 8/8/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Drilled-In Anchors | 8/9/2019 | Approved | JONATHAN ALLEN |
| Deputy Steel/Welding | 8/12/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 8/22/2019 | Conditional Approval | ALBERT COMISARI |
| Deputy Methane Barrier | 9/23/2019 | Approved | JONATHAN ALLEN |
| Deputy Methane Barrier | 9/24/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Methane Barrier | 9/25/2019 | Approved | JONATHAN ALLEN |
| Deputy Methane Barrier | 9/26/2019 | Approved | JONATHAN ALLEN |
| Deputy Methane Barrier | 9/27/2019 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Masonry | 10/30/2019 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Masonry | 10/31/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Masonry | 11/1/2019 | Conditional Approval | JONATHAN ALLEN |
| Deputy Reinf. Masonry | 11/8/2019 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 1/14/2020 | Conditional Approval | JONATHAN ALLEN |
| Final | 1/15/2020 | Partial Approval | JONATHAN ALLEN |
| Green Building Final | 1/15/2020 | Approved | JONATHAN ALLEN |
| SWPPP-Const. Storm Water | 1/15/2020 | Completed | JONATHAN ALLEN |
| Smoke Detectors | 1/15/2020 | Approved | JONATHAN ALLEN |