20524 W LASSEN ST 91311

Certificate Information: 20524 W LASSEN ST 91311

Application / Permit
18010-10001-02097
Plan Check / Job No.
B20LA12735
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
SUPPLEMENTAL TO PERMIT #18010-10000-02097 TO REVISE ROOF TOP SCREEN & REDUSE THE WIDTH OF EXIT STAIRS #1 TO MATCH UPPER FLOORS STAIRS & INSTALL GLASS CURTAIN WALLS @ 3 STAIRS TOWERS.
Permit Issued
Issued on 12/23/2020
Issuing Office
Current Status
Permit Finaled on 3/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2020 APPLICANT
Assigned to Plan Check Engineer 8/13/2020 GARO TELMI
Corrections Issued 8/19/2020 GARO TELMI
Quality Review Completed 8/20/2020 CHAD DOI
Applicant returned to address corrections 10/21/2020 GARO TELMI
Applicant returned to address corrections 10/23/2020 GARO TELMI
Applicant returned to address corrections 10/27/2020 GARO TELMI
Applicant returned to address corrections 11/10/2020 GARO TELMI
Plan Check Approved 12/18/2020 GARO TELMI
Issued 12/23/2020 APPLICANT
Building Plans Picked Up 12/28/2020 APPLICANT
Permit Finaled 3/1/2024 JEFFREY DURAN

Permit Application Clearance Information

Fire Marshall Fire Life Safety Cleared 11/18/2020 OSCAR SALGADO JR
CPC Cleared 12/8/2020 DANIEL CORONADO
Green Code Cleared 12/8/2020 GARO TELMI

Contact Information

Architect Tuttle,, Robert F; Lic. No.: C18724 33533 PEBBLE BROOK CIRCLE      TEMECULA, CA 92592
Contractor Bodar Enterprises; Lic. No.: 536360-B P O BOX 89-2110      TEMECULA, CA 92589
Engineer Hatch,, Robert Joseph; Lic. No.: S4634 1677 EUREKA RD STE 101      ROSEVILLE, CA 95661

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Masonry Wall/Backfill 3/31/2021 Approved HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 4/13/2021 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 7/12/2021 Not Ready for Inspection DANIEL VARNUM
Final 2/9/2023 Not Ready for Inspection JEFFREY FULTON
Smoke Detectors 2/9/2023 Approved JEFFREY FULTON
Final 10/26/2023 Conditional Approval JEFFREY FULTON
Final 3/1/2024 Permit Finaled JEFFREY DURAN