2840 E LUGO ST 90023

Certificate Information: 2840 E LUGO ST 90023

Application / Permit
18010-10001-01412
Plan Check / Job No.
B21LA22829
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
SUPPLEMENTAL TO PERMIT 18010-10000-01412 FOR DEFERRED SUBMISSION OF ROOF TRUSS.
Permit Issued
Issued on 2/28/2022
Issuing Office
Current Status
Permit Finaled on 1/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 HERNAN ARREOLA
Corrections Issued 12/22/2021 HERNAN ARREOLA
Quality Review Completed 12/29/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 12/30/2021 APPLICANT
Plan Check Approved 2/28/2022 HERNAN ARREOLA
Issued 2/28/2022 APPLICANT
Permit Finaled 1/11/2023 RAFAEL ESPINOZA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Anvil Construction Company Inc; Lic. No.: 998987-B 8895 RESEARCH DRIVE      IRVINE, CA 92618
Engineer Bushra, Rafeek L; Lic. No.: S4490 2564 W WOODLAND DR      ANAHEIM, CA 92801
Engineer Eskelsen,, Valerie Tripp; Lic. No.: C54939 2915 KENTBROOK COURT      KENNEWICK, WA 99338

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Approved RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 4/14/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/14/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/19/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/28/2022 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/28/2022 Partial Approval RAFAEL ESPINOZA
Insulation 5/5/2022 Approved NICK DANERI
Light Gage Steel Frame 5/5/2022 Partial Approval NICK DANERI
Drywall Nailing 5/23/2022 Approved RAFAEL ESPINOZA
Insulation 5/23/2022 Approved RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 6/9/2022 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/18/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 7/18/2022 Partial Approval RAFAEL ESPINOZA
T-Bar Ceiling 7/18/2022 Not Ready for Inspection RAFAEL ESPINOZA
T-Bar Ceiling 7/28/2022 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 8/9/2022 Partial Approval TED RIES
Light Gage Steel Frame 8/9/2022 Partial Inspection TED RIES
T-Bar Ceiling 8/9/2022 Approved TED RIES
Light Gage Steel Frame 8/25/2022 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 9/9/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 1/11/2023 Permit Finaled RAFAEL ESPINOZA
Smoke Detectors 1/11/2023 Approved RAFAEL ESPINOZA