1923 1/2 E PENNSYLVANIA AVE 90033

Certificate Information: 1923 1/2 E PENNSYLVANIA AVE 90033

Application / Permit
18010-10001-01290
Plan Check / Job No.
B20LA02353
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLMENTAL PERMIT TO #18010-10000-01290 TO ENLARGE, RELOCATE, AND REDESIGN PROPOSED DETACHED ACCESSORY DWELLING UNIT
Permit Issued
Issued on 8/10/2022
Issuing Office
Metro
Current Status
Permit Finaled on 3/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 GEORGE ALVAREZ
Corrections Issued 3/23/2020 GEORGE ALVAREZ
Quality Review Completed 3/31/2020 STANLEY RAAP
Building Plans Picked Up 4/8/2020 APPLICANT
Green Plans Picked Up 5/26/2020 APPLICANT
Plan Check Approved 6/24/2022 GEORGE ALVAREZ
Issued 8/10/2022 APPLICANT
Permit Finaled 3/6/2026 FREDDIE RIVERA

Permit Application Clearance Information

Sewer availability Cleared 5/11/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 5/13/2020 ELAINE LEI
Green Code Cleared 5/26/2020 GEORGE ALVAREZ
Green Code Cleared 5/26/2020 KHEDER ALRAZAA
Low Impact Development Cleared 8/18/2021 SARAH YOUSSEF
Miscellaneous Cleared 5/25/2022 DANIEL CORONADO
Roof/Waste drainage to street Cleared 6/3/2022 CINDY QI
Grading Pre-Inspection Cleared 6/9/2022 KIRK LINKLATER
Address approval Cleared 6/27/2022 CINDY QI

Contact Information

Contractor Dhs Ventures Inc; Lic. No.: 1047699-B 3575 CAHUENGA BLVD #350      LOS ANGELES, CA 90068
Engineer , ; Lic. No.: C88965 16526 BLACKHAWK ST      GRANADA HILLS, CA 91344

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/1/2022 Conditional Approval FREDDIE RIVERA
Pre-Inspection 9/9/2022 Approved FREDDIE RIVERA
Footing/Foundation/Slab 9/20/2022 Approved FREDDIE RIVERA
Pre-Inspection 9/22/2022 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/30/2022 Not Ready for Inspection THOMAS LOGRASSO
Wood Frame 1/17/2023 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 2/9/2023 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 2/9/2023 Approved FREDDIE RIVERA
Green Building Rough 2/9/2023 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 2/9/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 2/9/2023 Corrections Issued FREDDIE RIVERA
HVAC-Rough 7/27/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 7/27/2023 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 10/12/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/19/2023 Partial Inspection FREDDIE RIVERA
Green Building Rough 10/19/2023 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 10/19/2023 Partial Inspection FREDDIE RIVERA
Wood Frame 10/19/2023 Partial Inspection FREDDIE RIVERA
Insulation 10/31/2023 Approved FREDDIE RIVERA
Drywall Nailing 11/14/2023 Approved FREDDIE RIVERA
Green Building Rough 11/14/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 12/4/2023 Approved FREDDIE RIVERA