935 N BEL-AIR ROAD 90077

Certificate Information: 935 N BEL-AIR ROAD 90077

Application / Permit
18010-10000-06356
Plan Check / Job No.
B18LA27856
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY RESIDENCE WITH BASEMENT
Permit Issued
Issued on 12/12/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2018 APPLICANT
Green Plans Picked Up 1/7/2019 APPLICANT
Assigned to Plan Check Engineer 1/10/2019 SHANGQIN XIE
Corrections Issued 1/16/2019 SHANGQIN XIE
Quality Review Completed 1/24/2019 FELIX FIGUEROA
Building Plans Picked Up 1/25/2019 APPLICANT
Applicant returned to address corrections 7/18/2019 SHANGQIN XIE
Applicant returned to address corrections 7/24/2019 SHANGQIN XIE
Applicant returned to address corrections 8/6/2019 SHANGQIN XIE
Plan Check Approved 11/26/2019 SHANGQIN XIE
Issued 12/12/2019 LADBS
CofO in Progress 2/8/2025 MICHAEL PELHAM
Permit Finaled 2/11/2025 RICHARD STEINBACH
CofO Issued 2/11/2025 RICHARD STEINBACH
Permit Finaled 2/11/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/8/2019 ZIXUAN CHEN
Eng Process Fee Ord 176,300 Cleared 4/9/2019 CELINA MORENO
Sewer availability Cleared 4/9/2019 CELINA MORENO
Hydrant and Access approval Cleared 4/11/2019 GILBERT URREA
Green Code Cleared 8/6/2019 DONALD CRICHLOW
CPC Cleared 8/7/2019 SOPHIE GABEL-SCHEINBAU
Low Impact Development Cleared 11/13/2019 RYAN HUDSON
GPI Written Notices Cleared 11/21/2019 SHANGQIN XIE
Grading Pre-Inspection Cleared 11/21/2019 SHANGQIN XIE
Roof/Waste drainage to street Cleared 11/21/2019 ERIK BEASLEY

Contact Information

Architect Radziner,, Ronald Mark; Lic. No.: C22228 MARMOL RADZINER & ASSOCIATES   12210 NEBRASKA AVE    LOS ANGELES, CA 90025
Contractor Marmol Radziner An Architectural Corporation; Lic. No.: 734381-B 12210 NEBRASKA AVENUE      LOS ANGELES, CA 90025
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Wavering,, Derek Evan; Lic. No.: S6239 1371 COLE LANE      UPLAND, CA 91784

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 5/5/2020 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 6/11/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/12/2020 Conditional Approval MATT KELLERMAN
Piling/Pier/Caisson 6/17/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/19/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/14/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/14/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 7/16/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 7/17/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 8/18/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/18/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/18/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/27/2020 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 9/3/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/8/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 9/9/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/22/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/1/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/9/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 10/16/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/22/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 10/26/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/26/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/27/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 10/29/2020 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 10/30/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/2/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/5/2020 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/6/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/9/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/10/2020 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/12/2020 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 11/12/2020 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/20/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 11/23/2020 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/24/2020 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 11/24/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/30/2020 Partial Approval ANTHONY MCDOWALL
Underground Mechanical 11/30/2020 Not Ready for Inspection ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 12/2/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 12/7/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 12/10/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 12/10/2020 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/14/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 12/15/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 12/17/2020 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 12/18/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 1/11/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 1/13/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/14/2021 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 1/19/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/19/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 1/21/2021 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 1/26/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 1/28/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 2/2/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 2/3/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/4/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 2/5/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/5/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/12/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/12/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 2/17/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/18/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/18/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/18/2021 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 2/19/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 2/22/2021 Conditional Approval CHRISTOPHER WILSON
Underground Mechanical 2/22/2021 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 2/23/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 2/25/2021 Conditional Approval CHRISTOPHER WILSON
Underground Mechanical 3/9/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/19/2021 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 3/23/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/25/2021 No Access for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/26/2021 No Access for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Corrections Issued ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 4/6/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/12/2021 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/14/2021 Partial Approval ANTHONY MCDOWALL
Deputy Steel/Welding 4/15/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/16/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/19/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/27/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/28/2021 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/28/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 4/28/2021 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 5/5/2021 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 5/18/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/18/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/19/2021 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 5/19/2021 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 5/20/2021 Conditional Approval WILLIAM ROSE
Deputy Steel/Welding 5/28/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/3/2021 Partial Approval ANTHONY MCDOWALL
Green Building Rough 6/3/2021 Not Ready for Inspection ANTHONY MCDOWALL
Structural Steel Frame 6/3/2021 Not Ready for Inspection ANTHONY MCDOWALL
Verify Sprinkler Sign Off 6/3/2021 Not Ready for Inspection ANTHONY MCDOWALL
Deputy Reinf. Concrete 6/4/2021 Partial Approval MATT KELLERMAN
BUILDING-Rough-Frame 6/21/2021 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 6/21/2021 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 6/21/2021 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/28/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Partial Approval CHRISTOPHER WILSON
Insulation 6/28/2021 Partial Approval CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 6/28/2021 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 7/2/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 No Access for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 7/6/2021 No Access for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/7/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/7/2021 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 7/13/2021 Conditional Approval CHRISTOPHER WILSON
Drywall Nailing 7/13/2021 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/13/2021 Partial Approval CHRISTOPHER WILSON
Green Building Rough 7/13/2021 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 7/13/2021 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 7/14/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Partial Approval CHRISTOPHER WILSON
Insulation 7/14/2021 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 7/16/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/11/2021 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 8/16/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 8/20/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/23/2021 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 9/2/2021 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 9/7/2021 No Access for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/23/2021 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 9/23/2021 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 9/23/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/28/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/29/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/30/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 10/6/2021 No Access for Inspection CHRISTOPHER WILSON
HVAC-Rough 10/6/2021 No Access for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 10/6/2021 No Access for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 10/7/2021 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 10/7/2021 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 10/7/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 10/7/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 10/15/2021 Partial Approval CHRISTOPHER WILSON
Insulation 10/15/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/26/2021 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/16/2021 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/16/2021 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/17/2021 Conditional Approval RYAN SALAZAR
Deputy Reinf. Concrete 11/18/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/22/2021 Conditional Approval RYAN SALAZAR
HVAC-Rough 11/23/2021 Conditional Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/1/2021 Partial Approval CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 12/1/2021 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 12/2/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 1/11/2022 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/14/2022 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 1/20/2022 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 1/24/2022 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/24/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 1/24/2022 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 2/2/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 2/2/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/2/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 2/2/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 2/2/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 2/2/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 2/4/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 2/8/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Insulation 2/11/2022 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 2/11/2022 Partial Approval STEPHANIE SWANSON
HVAC-Rough 2/15/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 2/15/2022 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 2/17/2022 Partial Approval CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 2/17/2022 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 2/17/2022 Partial Approval CHRISTOPHER WILSON
Insulation 2/24/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 2/25/2022 Approved CHRISTOPHER WILSON
PLUMBING-Rough 2/25/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 3/1/2022 No Access for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 3/4/2022 Corrections Issued CHRISTOPHER WILSON
Insulation 3/4/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/9/2022 Partial Approval CHRISTOPHER WILSON
Insulation 3/9/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 3/11/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/15/2022 Partial Approval CHRISTOPHER WILSON
Insulation 3/15/2022 Partial Approval CHRISTOPHER WILSON
Insulation 3/23/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Insulation 3/25/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/29/2022 No Access for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 3/30/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 4/11/2022 Partial Approval BRENDAN LOONEY
Insulation 4/11/2022 Partial Approval BRENDAN LOONEY
Shower Pan 5/3/2022 Partial Approval RYAN SALAZAR
Underground Mechanical 5/10/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 8/4/2022 Partial Approval CHRISTOPHER WILSON
Green Building Rough 8/4/2022 Approved CHRISTOPHER WILSON
Drywall Nailing 8/17/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 8/30/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 8/30/2022 Partial Approval CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 8/31/2022 Partial Approval CHRISTOPHER WILSON
Insulation 9/13/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 9/19/2022 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/3/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 10/3/2022 Partial Approval CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 10/3/2022 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 10/3/2022 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/5/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 10/5/2022 Approved CHRISTOPHER WILSON
HVAC-Rough 10/5/2022 Approved CHRISTOPHER WILSON
PLUMBING-Rough 10/5/2022 Approved CHRISTOPHER WILSON
Pre-Inspection 10/18/2022 Partial Approval CHRISTOPHER WILSON
Insulation 10/20/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 10/20/2022 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 10/31/2022 Corrections Issued CHRISTOPHER WILSON
Structural Steel Frame 11/7/2022 Partial Approval CHRISTOPHER WILSON
Wood Frame 11/7/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 11/9/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 11/18/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 11/23/2022 Not Ready for Inspection CARLOS MATAMOROS
Service/Power Release 11/30/2022 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 12/13/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 12/13/2022 Not Ready for Inspection CHRISTOPHER WILSON
Shower Pan 2/6/2023 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 2/23/2023 Partial Approval CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 6/16/2023 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 6/21/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 6/29/2023 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 7/11/2023 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Rough 7/12/2023 Not Ready for Inspection CHRISTOPHER WILSON
Structural Steel Frame 7/12/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 8/25/2023 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 9/6/2023 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/7/2023 Corrections Issued CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/11/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 9/11/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/11/2023 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/14/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 9/21/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 9/25/2023 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 9/26/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Concrete 10/3/2023 Conditional Approval MICHAEL PELHAM
Drywall Nailing 10/10/2023 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 10/10/2023 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 11/21/2023 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 11/30/2023 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 3/29/2024 Approved CHRISTOPHER WILSON
Green Building Final 3/29/2024 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 3/29/2024 Partial Approval CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 3/29/2024 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 3/29/2024 Not Ready for Inspection CHRISTOPHER WILSON
Structural Steel Frame 3/29/2024 Approved CHRISTOPHER WILSON
Final 5/29/2024 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Not Ready STEPHANIE SWANSON
Final 7/9/2024 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 7/9/2024 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 7/9/2024 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 7/9/2024 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 8/8/2024 Partial Approval CHRISTOPHER WILSON
Final 8/8/2024 Corrections Issued CHRISTOPHER WILSON
Green Building Final 8/8/2024 Approved CHRISTOPHER WILSON
PLUMBING-Final 8/8/2024 Partial Approval CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 8/8/2024 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 8/8/2024 Approved CHRISTOPHER WILSON
Final 8/16/2024 Partial Inspection SEAN HAUPT
PLUMBING-Final 8/16/2024 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/16/2024 SGSOV Not Ready SEAN HAUPT
Final 8/29/2024 Partial Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/29/2024 SGSOV Not Ready SEAN HAUPT
ELECTRICAL-Final 9/5/2024 Approved SEAN HAUPT
Final 9/5/2024 Corrections Issued SEAN HAUPT
HVAC-Final 9/5/2024 Corrections Issued SEAN HAUPT
PLUMBING-Final 9/5/2024 Corrections Issued SEAN HAUPT
PLUMBING-Final 9/11/2024 Approved SEAN HAUPT
HVAC-Final 9/24/2024 Approved CHRISTOPHER WILSON
Final 10/9/2024 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 10/9/2024 SGSOV Approved CHRISTOPHER WILSON
Final 10/11/2024 Corrections Issued CHRISTOPHER WILSON
Final 2/3/2025 OK to Issue CofO CHRISTOPHER WILSON