Piling/Pier/Caisson
|
5/5/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
6/11/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
6/12/2020
|
Conditional Approval
|
MATT KELLERMAN
|
|
Piling/Pier/Caisson
|
6/17/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
6/19/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/14/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/14/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
7/16/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/17/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
8/18/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
8/18/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
8/18/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
8/27/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
9/3/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/8/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Shotcrete
|
9/9/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/22/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
10/1/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
10/9/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
10/16/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
10/22/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
10/26/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
10/26/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
10/27/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
10/29/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
10/30/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
11/2/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
11/5/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
11/6/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/9/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
11/10/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/12/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
11/12/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
11/20/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Shotcrete
|
11/23/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
11/24/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
11/24/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/30/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Underground Mechanical
|
11/30/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Excavation/Setback/Form/Re-Bar
|
12/2/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
12/7/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
12/10/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
12/10/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/14/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
12/15/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Footing/Foundation/Slab
|
12/17/2020
|
Partial Approval
|
THOMAS FINNILA
|
|
Deputy Reinf. Concrete
|
12/18/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
1/11/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
1/13/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/13/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
1/14/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
1/19/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
1/19/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
1/21/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
1/26/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
1/28/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
2/2/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/3/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
2/4/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/5/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
2/5/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/12/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
2/12/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/17/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/18/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/18/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
2/18/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
2/19/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
2/22/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
2/22/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
2/23/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
2/25/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
3/9/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/19/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
3/23/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/24/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/25/2021
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
3/26/2021
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/1/2021
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/6/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/12/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/14/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
4/15/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
4/16/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
4/19/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
4/27/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/28/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/28/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
4/28/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
5/5/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
5/18/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
5/18/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/19/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
5/19/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
5/20/2021
|
Conditional Approval
|
WILLIAM ROSE
|
|
Deputy Steel/Welding
|
5/28/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/3/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
6/3/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Structural Steel Frame
|
6/3/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
6/3/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
6/4/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
BUILDING-Rough-Frame
|
6/21/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
6/21/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
6/21/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
6/28/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/28/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
6/28/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Rough-Elec/Plmb/HVAC
|
6/28/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
7/2/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/6/2021
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
7/6/2021
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/7/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
7/7/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
7/13/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
7/13/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/13/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
7/13/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Insulation
|
7/13/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
7/14/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/14/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
7/14/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
7/16/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/11/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
8/16/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
8/20/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/23/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/27/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
9/2/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Excavation/Setback/Form/Re-Bar
|
9/7/2021
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/23/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
9/23/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
9/23/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/28/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/29/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/30/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
10/6/2021
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
10/6/2021
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
10/6/2021
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
10/7/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
10/7/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
10/7/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
10/7/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
10/15/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
10/15/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
10/26/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
11/16/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/16/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
11/17/2021
|
Conditional Approval
|
RYAN SALAZAR
|
|
Deputy Reinf. Concrete
|
11/18/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
11/22/2021
|
Conditional Approval
|
RYAN SALAZAR
|
|
HVAC-Rough
|
11/23/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
12/1/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Rough-Elec/Plmb/HVAC
|
12/1/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
12/2/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
1/11/2022
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
1/14/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
1/20/2022
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
1/24/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/24/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
1/24/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
2/2/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
2/2/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/2/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
2/2/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
2/2/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
2/2/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
2/4/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
2/8/2022
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
2/11/2022
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Interior/Exterior Lathing
|
2/11/2022
|
Partial Approval
|
STEPHANIE SWANSON
|
|
HVAC-Rough
|
2/15/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
2/15/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
2/17/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Rough-Elec/Plmb/HVAC
|
2/17/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
2/17/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
2/24/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
2/25/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
2/25/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
3/1/2022
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
3/4/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Insulation
|
3/4/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
3/9/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
3/9/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
3/11/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
3/15/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
3/15/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
3/23/2022
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
3/25/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
3/29/2022
|
No Access for Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
3/30/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
4/11/2022
|
Partial Approval
|
BRENDAN LOONEY
|
|
Insulation
|
4/11/2022
|
Partial Approval
|
BRENDAN LOONEY
|
|
Shower Pan
|
5/3/2022
|
Partial Approval
|
RYAN SALAZAR
|
|
Underground Mechanical
|
5/10/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
8/4/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
8/4/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
8/17/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
8/30/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
8/30/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Rough-Elec/Plmb/HVAC
|
8/31/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
9/13/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
9/19/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
10/3/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
10/3/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Rough-Elec/Plmb/HVAC
|
10/3/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
10/3/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
10/5/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
10/5/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
10/5/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
10/5/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
10/18/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
10/20/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
10/20/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
10/31/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
11/7/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
11/7/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
11/9/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
11/18/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
11/23/2022
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Service/Power Release
|
11/30/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
12/13/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
12/13/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
2/6/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
2/23/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Rough-Elec/Plmb/HVAC
|
6/16/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
6/21/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
6/29/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
7/11/2023
|
Corrections Issued
|
MICHAEL PELHAM
|
|
ELECTRICAL-Rough
|
7/12/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
7/12/2023
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
8/25/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
9/6/2023
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/7/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/11/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
9/11/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/11/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/14/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
9/21/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
9/25/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
9/26/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
10/3/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Drywall Nailing
|
10/10/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
10/10/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
11/21/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
11/30/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
3/29/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
3/29/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
3/29/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
3/29/2024
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
3/29/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
3/29/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
5/29/2024
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
SGSOV-Seismic Gas S/O Valve
|
5/29/2024
|
SGSOV Not Ready
|
STEPHANIE SWANSON
|
|
Final
|
7/9/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
7/9/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
7/9/2024
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
7/9/2024
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
8/8/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Final
|
8/8/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
8/8/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
8/8/2024
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
8/8/2024
|
SGSOV Not Ready
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
8/8/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
8/16/2024
|
Partial Inspection
|
SEAN HAUPT
|
|
PLUMBING-Final
|
8/16/2024
|
Corrections Issued
|
SEAN HAUPT
|
|
SGSOV-Seismic Gas S/O Valve
|
8/16/2024
|
SGSOV Not Ready
|
SEAN HAUPT
|
|
Final
|
8/29/2024
|
Partial Inspection
|
SEAN HAUPT
|
|
SGSOV-Seismic Gas S/O Valve
|
8/29/2024
|
SGSOV Not Ready
|
SEAN HAUPT
|
|
ELECTRICAL-Final
|
9/5/2024
|
Approved
|
SEAN HAUPT
|
|
Final
|
9/5/2024
|
Corrections Issued
|
SEAN HAUPT
|
|
HVAC-Final
|
9/5/2024
|
Corrections Issued
|
SEAN HAUPT
|
|
PLUMBING-Final
|
9/5/2024
|
Corrections Issued
|
SEAN HAUPT
|
|
PLUMBING-Final
|
9/11/2024
|
Approved
|
SEAN HAUPT
|
|
HVAC-Final
|
9/24/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
10/9/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
10/9/2024
|
SGSOV Approved
|
CHRISTOPHER WILSON
|
|
Final
|
10/11/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Final
|
2/3/2025
|
OK to Issue CofO
|
CHRISTOPHER WILSON
|