2641 S BUDLONG AVE 90007
Certificate Information: 2641 S BUDLONG AVE 90007
- Application / Permit
- 18010-10000-06349
- Plan Check / Job No.
- B18LA27806
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28'-5"x 26'-5", 2 STORY ACCESSORY DWELLING UNIT PER AB469 AND SB229
- Permit Issued
- Issued on 2/7/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2019 | VU NGUYEN |
| Corrections Issued | 1/16/2019 | VU NGUYEN |
| Quality Review Completed | 1/22/2019 | MICHAEL PEREZ |
| Building Plans Picked Up | 1/24/2019 | APPLICANT |
| Green Plans Picked Up | 4/12/2019 | APPLICANT |
| Plan Check Approved | 12/27/2019 | VU NGUYEN |
| Issued | 2/7/2020 | LADBS |
| CofO in Progress | 11/16/2020 | KATHRYN BUTTERWORTH |
| Permit Finaled | 11/19/2020 | DEROLD HAUFF |
| CofO Issued | 11/19/2020 | DEROLD HAUFF |
| Permit Finaled | 11/19/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 4/25/2019 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 4/25/2019 | MICAELA TORRES-GIL |
| ZI | Cleared | 10/16/2019 | RINA LARA |
| Address approval | Cleared | 10/23/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 10/23/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 10/23/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/23/2019 | ERIK BEASLEY |
| Green Code | Cleared | 10/28/2019 | SARAH ABOULHOSN |
Contact Information
| Architect | Tomalevski,, Vladimir Bogdanov; Lic. No.: C22417 | 2332 COTNER AVENUE SUITE 303 LOS ANGELES, CA 90064 |
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/31/2020 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 3/31/2020 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 3/31/2020 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 3/31/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 4/15/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Wood Frame | 4/23/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/23/2020 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 6/29/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 6/29/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/14/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/14/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Wood Frame | 7/14/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/20/2020 | Approved | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 7/20/2020 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 7/20/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 7/20/2020 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/20/2020 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 7/20/2020 | Approved | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 7/20/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 7/27/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/27/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 8/4/2020 | Approved | ELMER BLAND |
| Shower Pan | 8/6/2020 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 8/11/2020 | Approved | THOMAS LOGRASSO |
| Sewer | 8/14/2020 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 8/14/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Final | 9/21/2020 | Corrections Issued | DONALD CRICHLOW |
| Green Building Final | 9/21/2020 | Approved | DONALD CRICHLOW |
| SGSOV-Seismic Gas S/O Valve | 9/21/2020 | SGSOV Approved | DONALD CRICHLOW |
| Service/Power Release | 9/21/2020 | Corrections Issued | DONALD CRICHLOW |
| Smoke Detectors | 9/21/2020 | Approved | DONALD CRICHLOW |
| Final | 9/25/2020 | Conditional Approval | STUART CHAPMAN |
| Service/Power Release | 9/25/2020 | Approved | STUART CHAPMAN |