2641 S BUDLONG AVE 90007

Certificate Information: 2641 S BUDLONG AVE 90007

Application / Permit
18010-10000-06349
Plan Check / Job No.
B18LA27806
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-5"x 26'-5", 2 STORY ACCESSORY DWELLING UNIT PER AB469 AND SB229
Permit Issued
Issued on 2/7/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2018 APPLICANT
Assigned to Plan Check Engineer 1/10/2019 VU NGUYEN
Corrections Issued 1/16/2019 VU NGUYEN
Quality Review Completed 1/22/2019 MICHAEL PEREZ
Building Plans Picked Up 1/24/2019 APPLICANT
Green Plans Picked Up 4/12/2019 APPLICANT
Plan Check Approved 12/27/2019 VU NGUYEN
Issued 2/7/2020 LADBS
CofO in Progress 11/16/2020 KATHRYN BUTTERWORTH
Permit Finaled 11/19/2020 DEROLD HAUFF
CofO Issued 11/19/2020 DEROLD HAUFF
Permit Finaled 11/19/2020 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 4/25/2019 MICAELA TORRES-GIL
Miscellaneous Cleared 4/25/2019 MICAELA TORRES-GIL
ZI Cleared 10/16/2019 RINA LARA
Address approval Cleared 10/23/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 10/23/2019 ERIK BEASLEY
Low Impact Development Cleared 10/23/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 10/23/2019 ERIK BEASLEY
Sewer availability Cleared 10/23/2019 ERIK BEASLEY
Green Code Cleared 10/28/2019 SARAH ABOULHOSN

Contact Information

Architect Tomalevski,, Vladimir Bogdanov; Lic. No.: C22417 2332 COTNER AVENUE SUITE 303      LOS ANGELES, CA 90064
Contractor Owner-Builder       ,
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/31/2020 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 3/31/2020 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 3/31/2020 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 3/31/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 4/15/2020 Partial Approval KATHRYN BUTTERWORTH
Wood Frame 4/23/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/29/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/8/2020 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 6/23/2020 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 6/29/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 6/29/2020 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/14/2020 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Rough 7/14/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 7/14/2020 Corrections Issued KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/20/2020 Approved KATHRYN BUTTERWORTH
Deputy Wood Construction 7/20/2020 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 7/20/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 7/20/2020 Approved KATHRYN BUTTERWORTH
HVAC-Rough 7/20/2020 Approved KATHRYN BUTTERWORTH
METHANE-Rough 7/20/2020 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 7/20/2020 Approved KATHRYN BUTTERWORTH
Insulation 7/27/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/27/2020 Partial Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 8/4/2020 Approved ELMER BLAND
Shower Pan 8/6/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 8/11/2020 Approved THOMAS LOGRASSO
Sewer 8/14/2020 Approved KATHRYN BUTTERWORTH
Underground Mechanical 8/14/2020 Partial Approval KATHRYN BUTTERWORTH
Final 9/21/2020 Corrections Issued DONALD CRICHLOW
Green Building Final 9/21/2020 Approved DONALD CRICHLOW
SGSOV-Seismic Gas S/O Valve 9/21/2020 SGSOV Approved DONALD CRICHLOW
Service/Power Release 9/21/2020 Corrections Issued DONALD CRICHLOW
Smoke Detectors 9/21/2020 Approved DONALD CRICHLOW
Final 9/25/2020 Conditional Approval STUART CHAPMAN
Service/Power Release 9/25/2020 Approved STUART CHAPMAN