1176 E NELROSE AVE 90291
Certificate Information: 1176 E NELROSE AVE 90291
- Application / Permit
- 18010-10000-06292
- Plan Check / Job No.
- B18LA27549
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3 STORY 3 UNIT APARTMENT WITH ATTACHED 4 CAR CARPORT
- Permit Issued
- Issued on 2/11/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | VU NGUYEN |
| Corrections Issued | 1/29/2019 | VU NGUYEN |
| Green Plans Picked Up | 1/30/2019 | APPLICANT |
| Quality Review Completed | 2/5/2019 | MICHAEL PEREZ |
| Building Plans Picked Up | 2/7/2019 | APPLICANT |
| Applicant returned to address corrections | 11/25/2019 | VU NGUYEN |
| Applicant returned to address corrections | 12/20/2019 | VU NGUYEN |
| Applicant returned to address corrections | 1/9/2020 | VU NGUYEN |
| Applicant returned to address corrections | 1/16/2020 | VU NGUYEN |
| Plan Check Approved | 1/23/2020 | VU NGUYEN |
| Issued | 2/11/2020 | LADBS |
| TCO Issued (Expire Date: 01-08-2023) | 7/12/2022 | HENRY BAGHDASSARIAN |
| TCO Issued (Expire Date: 07-17-2023) | 1/18/2023 | HENRY BAGHDASSARIAN |
| CofO in Progress | 4/26/2023 | SORIN CIRSTOIU |
| Permit Finaled | 4/26/2023 | DAVID TSAU |
| CofO Issued | 4/26/2023 | DAVID TSAU |
| Permit Finaled | 4/26/2023 | DAVID TSAU |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/27/2019 | SARAH YOUSSEF |
| Address approval | Cleared | 3/20/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2019 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 3/20/2019 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 8/29/2019 | JOHN CONNEALLY |
| Sewer availability | Cleared | 9/4/2019 | ERIK BEASLEY |
| Green Code | Cleared | 9/23/2019 | NEGAR NEJAD |
| Specific Plan | Cleared | 11/15/2019 | PEDRO AYALA |
| Fire Marshall Fire Life Safety | Cleared | 1/22/2020 | DOMINIQUE MEDINA |
Contact Information
| Architect | Gibbs,, Kurt Robert; Lic. No.: C22275 | 3575 LONG BEACH BLVD LONG BEACH, CA 90807 |
| Contractor | Gibbs Kurt R; Lic. No.: 1053572-B | 3575 LONG BEACH BLVD LONG BEACH, CA 90807 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/27/2020 | Conditional Approval | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 5/8/2020 | Partial Approval | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 5/22/2020 | Approved | JEFF BYTHEWAY |
| Excavation/Setback/Form/Re-Bar | 7/2/2020 | Corrections Issued | JEFF BYTHEWAY |
| Special/Order Compliance | 7/7/2020 | Approved | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2020 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2020 | Partial Approval | JEFF BYTHEWAY |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2020 | Partial Approval | SORIN CIRSTOIU |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Approved | DERRICK SPENCER |
| Deputy Wood Construction | 1/15/2021 | Conditional Approval | SORIN CIRSTOIU |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2021 | Partial Inspection | SORIN CIRSTOIU |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2021 | Partial Approval | PAUL DAVIDSON |
| Green Building Final | 1/29/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Rough | 1/29/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Reinforced Masonry Frame | 1/29/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 1/29/2021 | SGSOV Not Ready | PAUL DAVIDSON |
| Smoke Detectors | 1/29/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Verify Sprinkler Sign Off | 1/29/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 1/29/2021 | Corrections Issued | PAUL DAVIDSON |
| Wood Frame | 2/4/2021 | Corrections Issued | JEFF BYTHEWAY |
| Wood Frame | 2/23/2021 | Partial Inspection | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 3/22/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Interior/Exterior Lathing | 3/25/2021 | Partial Approval | JEFF BYTHEWAY |
| Drywall Nailing | 4/6/2021 | Partial Approval | JEFF BYTHEWAY |
| Insulation | 4/22/2021 | Conditional Approval | JEFF BYTHEWAY |
| Drywall Nailing | 5/28/2021 | Partial Approval | SORIN CIRSTOIU |
| Final | 5/18/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Green Building Final | 5/18/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Green Building Rough | 5/18/2022 | Approved | JEFF BYTHEWAY |
| Reinforced Masonry Frame | 5/18/2022 | Approved | JEFF BYTHEWAY |
| SGSOV-Seismic Gas S/O Valve | 5/18/2022 | SGSOV Approved | JEFF BYTHEWAY |
| Smoke Detectors | 5/18/2022 | Approved | JEFF BYTHEWAY |
| Verify Sprinkler Sign Off | 5/18/2022 | Approved | JEFF BYTHEWAY |
| Final | 6/22/2022 | Corrections Issued | JEFF BYTHEWAY |
| Green Building Final | 6/22/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Pre-Inspection | 6/24/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Final | 6/28/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Green Building Final | 6/28/2022 | Not Ready for Inspection | JEFF BYTHEWAY |
| Special/Order Compliance | 12/14/2022 | Approved | DERRICK SPENCER |
| Final | 4/10/2023 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 4/10/2023 | Partial Inspection | SORIN CIRSTOIU |
| Final | 4/18/2023 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 4/18/2023 | Partial Inspection | SORIN CIRSTOIU |
| Final | 4/26/2023 | OK to Issue CofO | SORIN CIRSTOIU |
| Green Building Final | 4/26/2023 | Approved | SORIN CIRSTOIU |