1176 E NELROSE AVE 90291

Certificate Information: 1176 E NELROSE AVE 90291

Application / Permit
18010-10000-06292
Plan Check / Job No.
B18LA27549
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3 STORY 3 UNIT APARTMENT WITH ATTACHED 4 CAR CARPORT
Permit Issued
Issued on 2/11/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2018 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 VU NGUYEN
Corrections Issued 1/29/2019 VU NGUYEN
Green Plans Picked Up 1/30/2019 APPLICANT
Quality Review Completed 2/5/2019 MICHAEL PEREZ
Building Plans Picked Up 2/7/2019 APPLICANT
Applicant returned to address corrections 11/25/2019 VU NGUYEN
Applicant returned to address corrections 12/20/2019 VU NGUYEN
Applicant returned to address corrections 1/9/2020 VU NGUYEN
Applicant returned to address corrections 1/16/2020 VU NGUYEN
Plan Check Approved 1/23/2020 VU NGUYEN
Issued 2/11/2020 LADBS
TCO Issued (Expire Date: 01-08-2023) 7/12/2022 HENRY BAGHDASSARIAN
TCO Issued (Expire Date: 07-17-2023) 1/18/2023 HENRY BAGHDASSARIAN
CofO in Progress 4/26/2023 SORIN CIRSTOIU
Permit Finaled 4/26/2023 DAVID TSAU
CofO Issued 4/26/2023 DAVID TSAU
Permit Finaled 4/26/2023 DAVID TSAU

Permit Application Clearance Information

Low Impact Development Cleared 2/27/2019 SARAH YOUSSEF
Address approval Cleared 3/20/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/20/2019 JEANIE LAM
Roof/Waste drainage to street Cleared 3/20/2019 JEANIE LAM
Hydrant and Access approval Cleared 8/29/2019 JOHN CONNEALLY
Sewer availability Cleared 9/4/2019 ERIK BEASLEY
Green Code Cleared 9/23/2019 NEGAR NEJAD
Specific Plan Cleared 11/15/2019 PEDRO AYALA
Fire Marshall Fire Life Safety Cleared 1/22/2020 DOMINIQUE MEDINA

Contact Information

Architect Gibbs,, Kurt Robert; Lic. No.: C22275 3575 LONG BEACH BLVD      LONG BEACH, CA 90807
Contractor Gibbs Kurt R; Lic. No.: 1053572-B 3575 LONG BEACH BLVD      LONG BEACH, CA 90807
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/27/2020 Conditional Approval JEFF BYTHEWAY
Footing/Foundation/Slab 5/8/2020 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 5/22/2020 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 7/2/2020 Corrections Issued JEFF BYTHEWAY
Special/Order Compliance 7/7/2020 Approved JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 7/10/2020 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 7/27/2020 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Approved DERRICK SPENCER
Deputy Wood Construction 1/15/2021 Conditional Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Partial Inspection SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 1/20/2021 Partial Approval PAUL DAVIDSON
Green Building Final 1/29/2021 Not Ready for Inspection PAUL DAVIDSON
Green Building Rough 1/29/2021 Not Ready for Inspection PAUL DAVIDSON
Reinforced Masonry Frame 1/29/2021 Not Ready for Inspection PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 1/29/2021 SGSOV Not Ready PAUL DAVIDSON
Smoke Detectors 1/29/2021 Not Ready for Inspection PAUL DAVIDSON
Verify Sprinkler Sign Off 1/29/2021 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 1/29/2021 Corrections Issued PAUL DAVIDSON
Wood Frame 2/4/2021 Corrections Issued JEFF BYTHEWAY
Wood Frame 2/23/2021 Partial Inspection JEFF BYTHEWAY
Interior/Exterior Lathing 3/22/2021 Not Ready for Inspection JEFF BYTHEWAY
Interior/Exterior Lathing 3/25/2021 Partial Approval JEFF BYTHEWAY
Drywall Nailing 4/6/2021 Partial Approval JEFF BYTHEWAY
Insulation 4/22/2021 Conditional Approval JEFF BYTHEWAY
Drywall Nailing 5/28/2021 Partial Approval SORIN CIRSTOIU
Final 5/18/2022 Not Ready for Inspection JEFF BYTHEWAY
Green Building Final 5/18/2022 Not Ready for Inspection JEFF BYTHEWAY
Green Building Rough 5/18/2022 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 5/18/2022 Approved JEFF BYTHEWAY
SGSOV-Seismic Gas S/O Valve 5/18/2022 SGSOV Approved JEFF BYTHEWAY
Smoke Detectors 5/18/2022 Approved JEFF BYTHEWAY
Verify Sprinkler Sign Off 5/18/2022 Approved JEFF BYTHEWAY
Final 6/22/2022 Corrections Issued JEFF BYTHEWAY
Green Building Final 6/22/2022 Not Ready for Inspection JEFF BYTHEWAY
Pre-Inspection 6/24/2022 Not Ready for Inspection JEFF BYTHEWAY
Final 6/28/2022 Not Ready for Inspection JEFF BYTHEWAY
Green Building Final 6/28/2022 Not Ready for Inspection JEFF BYTHEWAY
Special/Order Compliance 12/14/2022 Approved DERRICK SPENCER
Final 4/10/2023 Partial Inspection SORIN CIRSTOIU
Green Building Final 4/10/2023 Partial Inspection SORIN CIRSTOIU
Final 4/18/2023 Partial Inspection SORIN CIRSTOIU
Green Building Final 4/18/2023 Partial Inspection SORIN CIRSTOIU
Final 4/26/2023 OK to Issue CofO SORIN CIRSTOIU
Green Building Final 4/26/2023 Approved SORIN CIRSTOIU