2042 N MEADOW VALLEY TER 90039

Certificate Information: 2042 N MEADOW VALLEY TER 90039

Application / Permit
18010-10000-06278
Plan Check / Job No.
B18LA27478
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 12/24/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2018 APPLICANT
Assigned to Plan Check Engineer 1/10/2019 MICHAEL LOPEZ
Green Plans Picked Up 1/10/2019 APPLICANT
Corrections Issued 1/15/2019 MICHAEL LOPEZ
Quality Review Completed 1/15/2019 FELIX FIGUEROA
Building Plans Picked Up 1/17/2019 APPLICANT
Applicant returned to address corrections 6/13/2019 MICHAEL LOPEZ
Applicant returned to address corrections 10/10/2019 MICHAEL LOPEZ
Plan Check Approved 11/1/2019 MICHAEL LOPEZ
Issued 12/24/2019 LADBS
CofO in Progress 9/9/2022 JOSEPH MCGARRY
No Progress 9/28/2022 JOSEPH MCGARRY
CofO in Progress 10/19/2022 JOSEPH MCGARRY
CofO in Progress 10/20/2022 JOSEPH MCGARRY
Permit Finaled 10/29/2022 DEROLD HAUFF
CofO Issued 10/29/2022 DEROLD HAUFF
Permit Finaled 10/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/13/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 3/13/2019 ERIK BEASLEY
Roof/Waste drainage to street Cleared 3/13/2019 ERIK BEASLEY
Sewer availability Cleared 3/13/2019 ERIK BEASLEY
Hydrant and Access approval Cleared 5/17/2019 JOHN CONNEALLY
Low Impact Development Cleared 5/20/2019 MARTIN FRAGOSO
Green Code Cleared 6/5/2019 COLIN LOREDO
Low Impact Development Cleared 10/15/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/15/2019 ERIK BEASLEY
Sewer availability Cleared 10/15/2019 ERIK BEASLEY
GPI Written Notices Cleared 11/1/2019 ROBERT HUGHES
Grading Pre-Inspection Cleared 11/1/2019 ROBERT HUGHES

Contact Information

Architect Wahlroos-Ritter,, Ingalill; Lic. No.: C24938 2020 LEMOYNE STREET      LOS ANGELES, CA 90026
Contractor A B C Advance Builder & Constructor Inc; Lic. No.: 989468-B 18017 CHATSWORTH STREET #140      GRANADA HILLS, CA 91344
Engineer Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 4215 TOLAND WAY      LOS ANGELES, CA 90065
Engineer Tsai,, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201
Geologist Carnegie,, Vincent John; Lic. No.: EG1608 P.O. BOX 5444      GLENDALE, CA 912012036

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/15/2020 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 4/3/2020 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 5/8/2020 Partial Approval JOSEPH MCGARRY
Reinforced Masonry Frame 5/22/2020 Approved ARTHUR SARGSYAN
Masonry Wall/Backfill 6/2/2020 Partial Approval JOSEPH MCGARRY
Masonry Wall/Backfill 6/10/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 6/19/2020 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/24/2020 Partial Approval JOSEPH MCGARRY
Reinforced Masonry Frame 6/30/2020 Approved JOSEPH MCGARRY
Reinforced Masonry Frame 7/15/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 9/24/2020 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 9/24/2020 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 9/24/2020 Partial Approval JOSEPH MCGARRY
Sewer 9/24/2020 Approved JOSEPH MCGARRY
Underground Mechanical 9/24/2020 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 10/9/2020 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/19/2020 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 5/20/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 5/20/2021 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 5/20/2021 Approved JOSEPH MCGARRY
Gas Test 5/20/2021 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 5/20/2021 Approved JOSEPH MCGARRY
HVAC-Rough 5/20/2021 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 5/20/2021 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 5/20/2021 Approved JOSEPH MCGARRY
Wood Frame 5/20/2021 Conditional Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 8/16/2021 Approved JOSEPH MCGARRY
HVAC-Rough 8/16/2021 Approved JOSEPH MCGARRY
Insulation 8/16/2021 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 8/16/2021 Partial Approval JOSEPH MCGARRY
Shower Pan 8/16/2021 Approved JOSEPH MCGARRY
Drywall Nailing 9/10/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/10/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Final 8/4/2022 Approved JOSEPH MCGARRY
Final 8/4/2022 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 8/4/2022 Approved JOSEPH MCGARRY
Green Building Final 8/4/2022 Approved JOSEPH MCGARRY
HVAC-Final 8/4/2022 Approved JOSEPH MCGARRY
PLUMBING-Final 8/4/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 8/4/2022 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 8/4/2022 Not Required JOSEPH MCGARRY
Smoke Detectors 8/4/2022 Approved JOSEPH MCGARRY
Final 9/6/2022 OK to Issue CofO JOSEPH MCGARRY
Special/Order Compliance 9/29/2022 Corrections Issued JOSEPH MCGARRY
Final 10/18/2022 OK to Issue CofO JOSEPH MCGARRY