5307-5307 1/2 E OAKLAND ST 90032
Certificate Information: 5307-5307 1/2 E OAKLAND ST 90032
- Application / Permit
- 18010-10000-06077
- Plan Check / Job No.
- B18LA27142
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY 44'-6"x 35' DUPLEX AT FRONT OF LOT
- Permit Issued
- Issued on 5/1/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2018 | APPLICANT |
| Green Plans Picked Up | 12/28/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | VU NGUYEN |
| Corrections Issued | 1/7/2019 | VU NGUYEN |
| Quality Review Completed | 1/8/2019 | MICHAEL PEREZ |
| Building Plans Picked Up | 1/10/2019 | APPLICANT |
| Plan Check Approved | 3/20/2019 | VU NGUYEN |
| Issued | 5/1/2019 | LADBS |
| CofO in Progress | 1/22/2021 | COREY HUPP |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
| CofO Issued | 1/23/2021 | DEROLD HAUFF |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2019 | KARAN PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2019 | KARAN PATEL |
| Green Code | Cleared | 3/1/2019 | NEGAR NEJAD |
| Low Impact Development | Cleared | 3/1/2019 | RYAN HUDSON |
| Permit | Cleared | 3/1/2019 | KARAN PATEL |
| Roof/Waste drainage to street | Cleared | 3/1/2019 | KARAN PATEL |
| Sewer availability | Cleared | 3/1/2019 | KARAN PATEL |
| Trees in Parkway | Cleared | 3/12/2019 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 3/13/2019 | GILBERT URREA |
| GPI Written Notices | Cleared | 3/20/2019 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 3/20/2019 | VU NGUYEN |
Contact Information
| No Data Available. |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/7/2019 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/12/2019 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/25/2019 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 6/28/2019 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2019 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2019 | Partial Approval | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/30/2019 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 9/30/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 9/30/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/23/2019 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 10/23/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 10/23/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/9/2019 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 12/9/2019 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/9/2019 | Approved | ENRIQUE MIRELES |
| Insulation | 1/31/2020 | No Access for Inspection | ENRIQUE MIRELES |
| Insulation | 2/5/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 2/18/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 3/9/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/19/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 12/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 12/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Gas Test | 12/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 12/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 12/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 12/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 12/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/28/2020 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 12/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 12/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Gas Test | 12/30/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 12/30/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 1/4/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 1/4/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 1/5/2021 | Approved | COREY HUPP |
| Final | 1/5/2021 | Corrections Issued | COREY HUPP |
| Green Building Final | 1/5/2021 | Approved | COREY HUPP |
| Green Building Rough | 1/5/2021 | Approved | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 1/5/2021 | SGSOV Approved | COREY HUPP |
| Service/Power Release | 1/5/2021 | Not Ready for Inspection | COREY HUPP |
| Smoke Detectors | 1/5/2021 | Approved | COREY HUPP |
| Verify Sprinkler Sign Off | 1/5/2021 | Approved | COREY HUPP |
| Final | 1/7/2021 | Not Ready for Inspection | RUBEN SALAS |
| Service/Power Release | 1/7/2021 | Approved | RUBEN SALAS |
| Final | 1/22/2021 | OK to Issue CofO | COREY HUPP |