4548 E SAN ANDREAS AVE 90065
Certificate Information: 4548 E SAN ANDREAS AVE 90065
- Application / Permit
- 18010-10000-06035
- Plan Check / Job No.
- B18LA26946
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SFD WITH ATTACHED GARAGE/BASEMENT
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2019 | RODOLFO ARIAS |
| Green Plans Picked Up | 1/17/2019 | APPLICANT |
| Corrections Issued | 1/23/2019 | EMMANUEL MARTINEZ |
| Quality Review Completed | 1/30/2019 | MOHAMMAD FIROUZBAKHT |
| Building Plans Picked Up | 1/31/2019 | APPLICANT |
| Applicant returned to address corrections | 7/31/2019 | EMMANUEL MARTINEZ |
| Applicant returned to address corrections | 8/14/2019 | EMMANUEL MARTINEZ |
| Applicant returned to address corrections | 11/23/2020 | MINA HABIB |
| Applicant returned to address corrections | 1/5/2021 | RODOLFO ARIAS |
| Applicant returned to address corrections | 1/27/2021 | RODOLFO ARIAS |
| Applicant returned to address corrections | 2/26/2021 | RODOLFO ARIAS |
| Applicant returned to address corrections | 5/19/2021 | RODOLFO ARIAS |
| Applicant returned to address corrections | 4/18/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 4/26/2022 | RODOLFO ARIAS |
| Plan Check Approved | 6/7/2022 | RODOLFO ARIAS |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 2/19/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 2/20/2025 | DEROLD HAUFF |
| CofO Issued | 2/20/2025 | DEROLD HAUFF |
| Permit Finaled | 2/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2019 | ELENA LOPEZ |
| BHO/Hillside ordinance | Cleared | 7/3/2019 | ELENA LOPEZ |
| Disturb/Remove Protected Trees | Cleared | 7/3/2019 | JOHN KIM |
| Permit | Cleared | 7/3/2019 | ELENA LOPEZ |
| Trees in Parkway | Cleared | 7/3/2019 | JOHN KIM |
| Green Code | Cleared | 7/30/2019 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 7/31/2019 | GILBERT URREA |
| Low Impact Development | Cleared | 7/31/2019 | ORVAL HERNANDEZ-MARCI |
| GPI Written Notices | Cleared | 8/14/2019 | EMMANUEL MARTINEZ |
| Grading Pre-Inspection | Cleared | 8/14/2019 | EMMANUEL MARTINEZ |
| Stormwater Pollution Mitigatn | Cleared | 10/27/2020 | ORVAL HERNANDEZ-MARCI |
| Encroachment in public way | Cleared | 10/28/2020 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 11/5/2020 | THAN WIN |
| Miscellaneous | Cleared | 11/6/2020 | JASON CHAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2020 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 11/9/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 11/10/2020 | ELENA LOPEZ |
| Building over 3-story or 36-ft | Cleared | 1/27/2021 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 1/27/2021 | CALOSHA APPROVED |
| BHO/Hillside ordinance | Cleared | 2/5/2021 | THAN WIN |
| Specific Plan | Cleared | 8/3/2021 | MAXFIELD VERMY |
| ZA Case | Cleared | 8/3/2021 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 4/21/2022 | MAXFIELD VERMY |
Contact Information
| Architect | , ; Lic. No.: C34339 | , |
| Contractor | A R G Construction & General Contractor Inc; Lic. No.: 495240-B | 11387 BIG DIPPER DRIVE MIRA LOMA, CA 91752 |
| Engineer | Melnyk,, Matthew John; Lic. No.: S5853 | 527 WEST 7TH ST STE 701 LOS ANGELES, CA 90014 |
| Engineer | Podegracz,, Joseph David; Lic. No.: C78425 | 3167 CARLTON DR THOUSAND OAKS, CA 91360 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
| Geologist | Robinson,, James Daniel; Lic. No.: EG2441 | P.O. BOX 1154 BONNERS FERRY, ID 83805 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/6/2022 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/12/2022 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/29/2022 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/13/2022 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/25/2022 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 10/26/2022 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/10/2022 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 11/28/2022 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 11/28/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 12/1/2022 | Partial Inspection | OSVALDO PARAMO |
| Sewer | 12/28/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 1/13/2023 | Partial Approval | JULIAN AMAYA |
| ELECTRICAL-Rough | 1/27/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 1/27/2023 | Conditional Approval | SCOTT FINNILA |
| PLUMBING-Rough | 1/27/2023 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 2/10/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Reinforced Concrete Frame | 2/10/2023 | Partial Approval | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 2/10/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/1/2023 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/12/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Corrections Issued | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/16/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Deputy Wood Construction | 10/26/2023 | Conditional Approval | JOSH MEISTER |
| Deputy Wood Construction | 11/2/2023 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 11/9/2023 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 11/9/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/14/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 11/14/2023 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 11/16/2023 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/16/2023 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 11/16/2023 | Approved | OSVALDO PARAMO |
| Sewer | 1/3/2024 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/8/2024 | Approved | OSVALDO PARAMO |
| Green Building Rough | 1/8/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 1/8/2024 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 2/9/2024 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/13/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Rough | 2/13/2024 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 2/13/2024 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/22/2024 | Corrections Issued | OSVALDO PARAMO |
| Insulation | 3/13/2024 | Approved | OSVALDO PARAMO |
| Shower Pan | 3/19/2024 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 4/18/2024 | Corrections Issued | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/18/2024 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/20/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Drywall Nailing | 5/20/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/20/2024 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/31/2024 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 8/7/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 8/7/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 8/7/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/7/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/7/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 9/30/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 9/30/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 10/3/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 10/3/2024 | Corrections Issued | OSVALDO PARAMO |
| Drywall Nailing | 11/1/2024 | Approved | OSVALDO PARAMO |
| Final | 11/1/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Final | 11/1/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Reinforced Concrete Frame | 11/1/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 11/1/2024 | SGSOV Not Ready | OSVALDO PARAMO |
| Service/Power Release | 11/1/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 11/1/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Final | 11/5/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/13/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 2/13/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/13/2025 | SGSOV Not Required | ALIZAH MAYAGOITIA |
| Service/Power Release | 2/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 2/13/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/20/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |