5340 E ALDAMA ST 90042

Certificate Information: 5340 E ALDAMA ST 90042

Application / Permit
18010-10000-06001
Plan Check / Job No.
B18LA26864
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 1-CAR GARAGE AND DRIVEWAY. "COMPLY WITH DEPARTMENT ORDER effective date 10/31/2016. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 741066. 1 OF 4
Permit Issued
Issued on 11/7/2019
Issuing Office
Metro
Current Status
Permit Closed on 9/11/2025
Certificate of Occupancy
Permit Closed More Information

Permit Application Status History

Submitted 12/13/2018 APPLICANT
Assigned to Plan Check Engineer 1/10/2019 ANA AVELAR
Corrections Issued 1/11/2019 ANA AVELAR
Green Plans Picked Up 1/29/2019 APPLICANT
Quality Review Completed 2/4/2019 KESETE HAREGOT
Building Plans Picked Up 2/5/2019 APPLICANT
Applicant returned to address corrections 3/19/2019 ANA AVELAR
Plan Check Approved 4/1/2019 ANA AVELAR
Issued 11/7/2019 LADBS
Permit Closed 9/11/2025 NICHOLAS LOPEZ

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/13/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 2/13/2019 GILBERT URREA
BHO/Hillside ordinance Cleared 2/21/2019 ERIK BEASLEY
BHO/Hillside ordinance Cleared 2/21/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 2/21/2019 ERIK BEASLEY
Green Code Cleared 2/21/2019 COLIN LOREDO
Roof/Waste drainage to street Cleared 2/21/2019 ERIK BEASLEY
Grading Pre-Inspection Cleared 3/19/2019 ANA AVELAR
HPOZ Cleared 3/27/2019 KATIE DEBIASE

Contact Information

Contractor Salgado Design & Construction Inc; Lic. No.: 1011670-B 4230 CENTER STREET      BALDWIN PARK, CA 91706
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Final 2/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 2/7/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 2/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 2/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Masonry Wall/Backfill 9/9/2025 Not Ready for Inspection NICHOLAS LOPEZ
Pre-Inspection 9/9/2025 Partial Approval NICHOLAS LOPEZ
Special/Order Compliance 9/11/2025 Permit Closed NICHOLAS LOPEZ