5265 N CARTWRIGHT AVE 1-3 91601

Certificate Information: 5265 N CARTWRIGHT AVE 1-3 91601

Application / Permit
18010-10000-05957
Plan Check / Job No.
B18LA26618
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 48'9" X 30'4" 4-STORY 3-UNIT APARTMENT BUILDING WITH ATTACHED GARAGE. FIRE SPRINKLER REQUIRED; NFPA 13R.
Permit Issued
Issued on 1/6/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2018 APPLICANT
Assigned to Plan Check Engineer 12/27/2018 STANLEY RAAP
Corrections Issued 12/31/2018 STANLEY RAAP
Disabled Access Plans Picked Up 1/4/2019 APPLICANT
Green Plans Picked Up 1/4/2019 APPLICANT
Quality Review Completed 1/17/2019 FELIX FIGUEROA
Building Plans Picked Up 2/28/2019 APPLICANT
Applicant returned to address corrections 11/26/2019 STANLEY RAAP
Plan Check Approved 12/4/2019 STANLEY RAAP
Issued 1/6/2020 LADBS
CofO in Progress 6/4/2026 DEANDRE HOFFMAN
Permit Finaled 6/5/2026 JEFFREY DURAN
CofO Issued 6/5/2026 JEFFREY DURAN
Permit Finaled 6/5/2026 JEFFREY DURAN

Permit Application Clearance Information

Hydrant and Access approval Cleared 8/5/2019 GILBERT URREA
Green Code Cleared 8/13/2019 KHEDER ALRAZAA
Green Code Cleared 8/13/2019 STANLEY RAAP
Low Impact Development Cleared 10/11/2019 JORGE MEJIA LEMUS
Project located in CRA area Cleared 10/29/2019 JIM URQUHART
Address approval Cleared 11/4/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 11/4/2019 ERIK BEASLEY
Permit Cleared 11/4/2019 ERIK BEASLEY
Sewer availability Cleared 11/4/2019 ERIK BEASLEY
ZI Cleared 11/4/2019 SOPHIE GABEL-SCHEINBAU
Roof/Waste drainage to street Cleared 11/5/2019 ARMEN MEHRABIAN
DAS Clearance Cleared 12/5/2019 ELIZABETH TOMS

Contact Information

Architect Tavasci,, Robert J; Lic. No.: C26023 3351 ORANGEWOOD AVENUE      LOS ALAMITOS, CA 90720
Contractor Clc Builders Inc; Lic. No.: 580175-B 22916 ELKWOOD STREET      WEST HILLS, CA 91304
Engineer Christenson,, Paul Scott; Lic. No.: C57182 3529 COASTVIEW CT      CARLSBAD, CA 92010

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/13/2020 Partial Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 8/17/2020 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 8/17/2020 Not Ready for Inspection JOHN KITCKO
METHANE-Barrier 8/17/2020 Not Ready for Inspection JOHN KITCKO
METHANE-Subgrade 8/17/2020 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 8/17/2020 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 9/30/2020 No Access for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 10/8/2020 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 10/8/2020 Not Ready for Inspection JOHN KITCKO
METHANE-Barrier 10/8/2020 Approved JOHN KITCKO
METHANE-Subgrade 10/8/2020 Approved JOHN KITCKO
Pre-Inspection 10/8/2020 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 11/19/2020 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 11/19/2020 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 1/14/2021 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 1/14/2021 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 1/14/2021 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 1/15/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 1/15/2021 Not Ready for Inspection JOE VELASQUEZ
Pre-Inspection 1/15/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 1/20/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 2/24/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 3/5/2021 Approved HAMID PISHEHVAR
Deputy Wood Construction 3/18/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 3/18/2021 Partial Approval JOHN KITCKO
Deputy Wood Construction 4/15/2021 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 4/15/2021 Partial Approval JOHN KITCKO
Green Building Rough 7/15/2021 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 7/15/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/15/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 7/15/2021 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 10/28/2021 Not Ready for Inspection JOHN KITCKO
METHANE-Rough 10/28/2021 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 10/28/2021 Not Ready for Inspection JOHN KITCKO
Wood Frame 10/28/2021 Corrections Issued JOHN KITCKO
Special/Order Compliance 4/15/2022 Partial Inspection ROBERT DAVIS
Green Building Rough 6/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 6/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/1/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 6/1/2022 Corrections Issued DANNY RODRIGUEZ
Green Building Rough 6/28/2022 Not Ready for Inspection ROBERT DAVIS
METHANE-Rough 6/28/2022 Not Ready for Inspection ROBERT DAVIS
Verify Sprinkler Sign Off 6/28/2022 Partial Inspection ROBERT DAVIS
Wood Frame 6/28/2022 Corrections Issued ROBERT DAVIS
Green Building Rough 12/8/2022 Not Ready for Inspection DANNY RODRIGUEZ
METHANE-Rough 12/8/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/8/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/8/2022 Corrections Issued DANNY RODRIGUEZ
Green Building Rough 1/17/2023 Not Ready for Inspection JOHN KITCKO
METHANE-Rough 1/17/2023 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 1/17/2023 Not Ready for Inspection JOHN KITCKO
Wood Frame 1/17/2023 Not Ready for Inspection JOHN KITCKO
Green Building Rough 1/24/2023 Not Ready for Inspection JOHN KITCKO
METHANE-Rough 1/24/2023 Partial Inspection JOHN KITCKO
Verify Sprinkler Sign Off 1/24/2023 Approved JOHN KITCKO
Wood Frame 1/24/2023 Not Ready for Inspection JOHN KITCKO
Green Building Rough 2/1/2023 Not Ready for Inspection ANDREW DORSO
METHANE-Rough 2/1/2023 Not Ready for Inspection ANDREW DORSO
Wood Frame 2/1/2023 Corrections Issued ANDREW DORSO
Green Building Rough 2/16/2023 Not Ready for Inspection JOHN KITCKO
METHANE-Rough 2/16/2023 Approved JOHN KITCKO
Wood Frame 2/16/2023 Partial Approval JOHN KITCKO
Insulation 2/23/2023 Approved BRIAN KELLY
Interior/Exterior Lathing 3/29/2023 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 4/3/2023 Partial Approval ANDREW DORSO
Drywall Nailing 6/29/2023 Corrections Issued JOHN KITCKO
Green Building Rough 6/29/2023 Approved JOHN KITCKO
Drywall Nailing 8/17/2023 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 8/20/2024 Partial Inspection JOHN KITCKO
Drywall Nailing 12/11/2025 Approved JOHN KITCKO
Final 12/11/2025 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 12/11/2025 Approved JOHN KITCKO
Green Building Final 12/11/2025 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 12/11/2025 Not Ready for Inspection JOHN KITCKO
Wood Frame 12/11/2025 Approved JOHN KITCKO
Final 5/28/2026 Not Ready for Inspection ROBERT DAVIS
Green Building Final 5/28/2026 No Access for Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 5/28/2026 SGSOV Not Ready ROBERT DAVIS
Smoke Detectors 5/28/2026 Not Ready for Inspection ROBERT DAVIS
Final 6/1/2026 Not Ready for Inspection EDWIN GREGORYONA
Green Building Final 6/1/2026 Not Ready for Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 6/1/2026 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 6/1/2026 Not Ready for Inspection EDWIN GREGORYONA
Final 6/3/2026 OK to Issue CofO DEANDRE HOFFMAN
Green Building Final 6/3/2026 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 6/3/2026 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 6/3/2026 Approved DEANDRE HOFFMAN