6044 E LA PRADA 90042
Certificate Information: 6044 E LA PRADA 90042
- Application / Permit
- 18010-10000-05863
- Plan Check / Job No.
- B18LA26196
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 4-UNIT, 2 STORY, TYPE VB APARTMENT BUIDLING
- Permit Issued
- Issued on 1/10/2020
- Issuing Office
- Metro
- Current Status
- Issued on 1/10/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2019 | VU NGUYEN |
| Corrections Issued | 1/8/2019 | MOHAMMAD FIROUZBAKHT |
| Quality Review Completed | 1/9/2019 | FELIX FIGUEROA |
| Green Plans Picked Up | 1/10/2019 | APPLICANT |
| Building Plans Picked Up | 1/14/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 2/5/2019 | APPLICANT |
| Applicant returned to address corrections | 5/7/2019 | VU NGUYEN |
| Applicant returned to address corrections | 12/4/2019 | VU NGUYEN |
| Plan Check Approved | 12/10/2019 | VU NGUYEN |
| Issued | 1/10/2020 | LADBS |
| CofO in Progress | 2/8/2022 | NICK DANERI |
| CofO Issued-Status Void | 2/10/2022 | ERNESTO CORRAL |
| Permit Finaled-Status Void | 2/10/2022 | ERNESTO CORRAL |
| Re-Activate Permit | 3/11/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Hold | Cleared | 1/3/2019 | LOURDES RAMIRO |
| Address approval | Cleared | 1/30/2019 | JEANETTE VONG |
| Highway dedication | Cleared | 1/30/2019 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 1/30/2019 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2019 | ZIXUAN CHEN |
| Sewer availability | Cleared | 2/8/2019 | ZIXUAN CHEN |
| Green Code | Cleared | 2/13/2019 | KHEDER ALRAZAA |
| GPI Written Notices | Cleared | 12/4/2019 | MOHAMMAD FIROUZBAKHT |
| Grading Pre-Inspection | Cleared | 12/4/2019 | MOHAMMAD FIROUZBAKHT |
| Low Impact Development | Cleared | 12/9/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/9/2019 | JEANIE LAM |
| DAS Clearance | Cleared | 12/10/2019 | MOHAMMAD FIROUZBAKHT |
Contact Information
| Engineer | Allen,, Thomas Christopher; Lic. No.: S5460 | 2 VENTURE, SUITE 200 IRVINE, CA 92618 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/18/2020 | Partial Inspection | ERNESTO CORRAL |
| Footing/Foundation/Slab | 3/5/2020 | Partial Inspection | ERNESTO CORRAL |
| Footing/Foundation/Slab | 4/6/2020 | Approved | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2020 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Rough | 5/6/2020 | Not Ready for Inspection | RONALD PACHECO |
| Verify Sprinkler Sign Off | 5/6/2020 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 5/6/2020 | Partial Approval | RONALD PACHECO |
| Green Building Rough | 5/19/2020 | Not Ready for Inspection | RONALD PACHECO |
| Verify Sprinkler Sign Off | 5/19/2020 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 5/19/2020 | Not Ready for Inspection | RONALD PACHECO |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2020 | Partial Approval | NICK DANERI |
| Interior/Exterior Lathing | 6/11/2020 | Not Ready for Inspection | NICK DANERI |
| Interior/Exterior Lathing | 6/12/2020 | Partial Approval | NICK DANERI |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2020 | Partial Approval | NICK DANERI |
| Green Building Rough | 6/30/2020 | Partial Approval | NICK DANERI |
| Wood Frame | 6/30/2020 | Partial Approval | NICK DANERI |
| Green Building Rough | 7/6/2020 | Approved | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 7/6/2020 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Wood Frame | 7/6/2020 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 7/9/2020 | Not Ready for Inspection | NICK DANERI |
| Insulation | 8/3/2020 | Partial Inspection | NICK DANERI |
| Insulation | 8/17/2020 | Partial Approval | NICK DANERI |
| Drywall Nailing | 8/26/2020 | Partial Approval | NICK DANERI |
| Drywall Nailing | 8/31/2020 | Not Ready for Inspection | NICK DANERI |
| Drywall Nailing | 9/2/2020 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 9/11/2020 | Partial Approval | NICK DANERI |
| Drywall Nailing | 9/24/2020 | Partial Approval | NICK DANERI |
| Pre-Inspection | 11/24/2020 | Conditional Approval | NICK DANERI |
| Final | 4/23/2021 | Not Ready for Inspection | NICK DANERI |
| Green Building Final | 4/23/2021 | Not Ready for Inspection | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 4/23/2021 | SGSOV Approved | NICK DANERI |
| Smoke Detectors | 4/23/2021 | Approved | NICK DANERI |
| Verify Sprinkler Sign Off | 4/23/2021 | Approved | NICK DANERI |
| Wood Frame | 4/23/2021 | Approved | NICK DANERI |
| Final | 2/8/2022 | OK to Issue CofO | NICK DANERI |
| Green Building Final | 2/8/2022 | Approved | NICK DANERI |