6044 E LA PRADA 90042

Certificate Information: 6044 E LA PRADA 90042

Application / Permit
18010-10000-05863
Plan Check / Job No.
B18LA26196
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 4-UNIT, 2 STORY, TYPE VB APARTMENT BUIDLING
Permit Issued
Issued on 1/10/2020
Issuing Office
Metro
Current Status
Issued on 1/10/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/6/2018 APPLICANT
Assigned to Plan Check Engineer 1/3/2019 VU NGUYEN
Corrections Issued 1/8/2019 MOHAMMAD FIROUZBAKHT
Quality Review Completed 1/9/2019 FELIX FIGUEROA
Green Plans Picked Up 1/10/2019 APPLICANT
Building Plans Picked Up 1/14/2019 APPLICANT
Disabled Access Plans Picked Up 2/5/2019 APPLICANT
Applicant returned to address corrections 5/7/2019 VU NGUYEN
Applicant returned to address corrections 12/4/2019 VU NGUYEN
Plan Check Approved 12/10/2019 VU NGUYEN
Issued 1/10/2020 LADBS
CofO in Progress 2/8/2022 NICK DANERI
CofO Issued-Status Void 2/10/2022 ERNESTO CORRAL
Permit Finaled-Status Void 2/10/2022 ERNESTO CORRAL
Re-Activate Permit 3/11/2025 ERNESTO CORRAL

Permit Application Clearance Information

Hold Cleared 1/3/2019 LOURDES RAMIRO
Address approval Cleared 1/30/2019 JEANETTE VONG
Highway dedication Cleared 1/30/2019 JEANETTE VONG
Hydrant and Access approval Cleared 1/30/2019 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 2/8/2019 ZIXUAN CHEN
Sewer availability Cleared 2/8/2019 ZIXUAN CHEN
Green Code Cleared 2/13/2019 KHEDER ALRAZAA
GPI Written Notices Cleared 12/4/2019 MOHAMMAD FIROUZBAKHT
Grading Pre-Inspection Cleared 12/4/2019 MOHAMMAD FIROUZBAKHT
Low Impact Development Cleared 12/9/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/9/2019 JEANIE LAM
DAS Clearance Cleared 12/10/2019 MOHAMMAD FIROUZBAKHT

Contact Information

Engineer Allen,, Thomas Christopher; Lic. No.: S5460 2 VENTURE, SUITE 200      IRVINE, CA 92618

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2020 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 3/5/2020 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 4/6/2020 Approved RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 5/5/2020 Not Ready for Inspection RONALD PACHECO
Green Building Rough 5/6/2020 Not Ready for Inspection RONALD PACHECO
Verify Sprinkler Sign Off 5/6/2020 Not Ready for Inspection RONALD PACHECO
Wood Frame 5/6/2020 Partial Approval RONALD PACHECO
Green Building Rough 5/19/2020 Not Ready for Inspection RONALD PACHECO
Verify Sprinkler Sign Off 5/19/2020 Not Ready for Inspection RONALD PACHECO
Wood Frame 5/19/2020 Not Ready for Inspection RONALD PACHECO
Floor/Roof Diaphrgm/Shear Wall 6/8/2020 Partial Approval NICK DANERI
Interior/Exterior Lathing 6/11/2020 Not Ready for Inspection NICK DANERI
Interior/Exterior Lathing 6/12/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/23/2020 Partial Approval NICK DANERI
Green Building Rough 6/30/2020 Partial Approval NICK DANERI
Wood Frame 6/30/2020 Partial Approval NICK DANERI
Green Building Rough 7/6/2020 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/6/2020 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 7/6/2020 Partial Approval RAFAEL ESPINOZA
Insulation 7/9/2020 Not Ready for Inspection NICK DANERI
Insulation 8/3/2020 Partial Inspection NICK DANERI
Insulation 8/17/2020 Partial Approval NICK DANERI
Drywall Nailing 8/26/2020 Partial Approval NICK DANERI
Drywall Nailing 8/31/2020 Not Ready for Inspection NICK DANERI
Drywall Nailing 9/2/2020 Partial Approval RONALD PACHECO
Drywall Nailing 9/11/2020 Partial Approval NICK DANERI
Drywall Nailing 9/24/2020 Partial Approval NICK DANERI
Pre-Inspection 11/24/2020 Conditional Approval NICK DANERI
Final 4/23/2021 Not Ready for Inspection NICK DANERI
Green Building Final 4/23/2021 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 4/23/2021 SGSOV Approved NICK DANERI
Smoke Detectors 4/23/2021 Approved NICK DANERI
Verify Sprinkler Sign Off 4/23/2021 Approved NICK DANERI
Wood Frame 4/23/2021 Approved NICK DANERI
Final 2/8/2022 OK to Issue CofO NICK DANERI
Green Building Final 2/8/2022 Approved NICK DANERI