4220 W MONT CLAIR ST 90018

Certificate Information: 4220 W MONT CLAIR ST 90018

Application / Permit
18010-10000-05791
Plan Check / Job No.
B18LA25744
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5-STORY APARTMENT BUILDING PROVIDING SUPPORTIVE AFFORDABLE HOUSING (see comments) CONSISTS OF (45) STUDIO UNITS AND (1) TWO BED ROOM MANAGERS UNIT. 4-STORIES OF TYPE VA ABOVE 1-STORY TYPE IA PODIUM.
Permit Issued
Issued on 1/14/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2018 APPLICANT
Assigned to Plan Check Engineer 12/6/2018 TEODORO DIAZ RODRIGUEZ
Corrections Issued 1/4/2019 TEODORO DIAZ RODRIGUEZ
Green Plans Picked Up 1/4/2019 APPLICANT
Quality Review Completed 1/15/2019 SIAVOSH POURSABAHIAN
Building Plans Picked Up 1/15/2019 APPLICANT
Applicant returned to address corrections 1/23/2019 TEODORO DIAZ RODRIGUEZ
Disabled Access Plans Picked Up 1/28/2019 APPLICANT
Applicant returned to address corrections 2/27/2019 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 3/14/2019 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 4/16/2019 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 1/14/2020 TEODORO DIAZ RODRIGUEZ
Issued 1/14/2020 LADBS
TCO Issued (Expire Date: 08-15-2022) 2/16/2022 ERNESTO CORRAL
CofO in Progress 6/28/2022 JAMES POWERS
CofO in Progress 6/28/2022 JAMES POWERS
CofO in Progress 6/28/2022 JAMES POWERS
CofO Issued 6/30/2022 TERRY HERR
Permit Finaled 6/30/2022 TERRY HERR

Permit Application Clearance Information

Address approval Cleared 1/23/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/23/2019 ERIK BEASLEY
Permit Cleared 1/23/2019 ERIK BEASLEY
Trees in Parkway Cleared 2/13/2019 ADRIAN SANCHEZ
Miscellaneous Cleared 2/20/2019 LATANYA ROUX
Opn space landscape/Water mgmt Cleared 2/20/2019 LATANYA ROUX
Specific Plan Cleared 2/20/2019 LATANYA ROUX
ZA Case Cleared 2/20/2019 LATANYA ROUX
ZA Case Cleared 2/20/2019 LATANYA ROUX
Food establishment approval Cleared 3/5/2019 LACDHS APPROVED
Sewer availability Cleared 3/5/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 3/8/2019 JOHN CONNEALLY
Fire Marshall Fire Life Safety Cleared 4/2/2019 VIDAL GARCIA
Construction within easement Cleared 4/10/2019 RIDWAN HARDY
DAS Clearance Cleared 4/17/2019 TEODORO DIAZ RODRIGUEZ
Highway dedication Cleared 4/22/2019 JEANETTE VONG
Roof/Waste drainage to street Cleared 4/22/2019 JEANETTE VONG
Green Code Cleared 4/23/2019 DONALD CRICHLOW
Building over 3-story or 36-ft Cleared 4/24/2019 CALOSHA APPROVED
Project located in CRA area Cleared 5/2/2019 JIM URQUHART
Density Bonus 12.22.A.25 Cleared 5/14/2019 JAMES MCCARTHY

Contact Information

Architect Barar,, Ali; Lic. No.: C25584 624 SOUTH ORANGE GROVE BLVD.      PASADENA, CA 91105
Contractor Westport Construction Inc; Lic. No.: 712732-B 125 W MAPLE AVE      MONROVIA, CA 91016
Engineer Yeh,, Ming-Yang; Lic. No.: S2587 131 WEST GREEN ST      PASADENA, CA 911059886

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/29/2020 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/1/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/1/2020 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 6/5/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/5/2020 Partial Approval JAMES POWERS
METHANE-Barrier 6/5/2020 Approved JAMES POWERS
METHANE-Subgrade 6/5/2020 Approved JAMES POWERS
Footing/Foundation/Slab 6/26/2020 Partial Approval RAFAEL ESPINOZA
Green Building Rough 6/26/2020 Approved RAFAEL ESPINOZA
METHANE-Rough 6/26/2020 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 6/26/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/26/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 6/30/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/30/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/6/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/14/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/14/2020 Not Ready for Inspection JAMES POWERS
Masonry Wall/Backfill 7/29/2020 Partial Approval DAVID BURKHEAD
Reinforced Concrete Frame 7/29/2020 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 7/29/2020 Not Ready for Inspection DAVID BURKHEAD
Masonry Wall/Backfill 7/31/2020 Partial Approval NICK DANERI
Masonry Wall/Backfill 8/5/2020 Partial Approval NICK DANERI
Footing/Foundation/Slab 9/9/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/9/2020 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 9/9/2020 Not Ready for Inspection JAMES POWERS
Insulation 9/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/11/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 10/23/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/27/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 11/2/2020 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 11/5/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/5/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/13/2020 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 12/4/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/15/2020 Partial Approval JAMES POWERS
Insulation 12/16/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 12/17/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/18/2020 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 12/21/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 12/21/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 2/8/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/9/2021 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 2/11/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 2/11/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/11/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 2/17/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 2/17/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/25/2021 Partial Approval JAMES POWERS
Wood Frame 3/2/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/11/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/30/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 3/30/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 3/31/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/1/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/5/2021 Partial Approval JAMES POWERS
Drywall Nailing 4/6/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/20/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/21/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/22/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/27/2021 Approved JOEY BUCHANAN
Deputy Steel/Welding 4/28/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/29/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/30/2021 Approved JOEY BUCHANAN
Deputy Steel/Welding 5/4/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/5/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/6/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/7/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/12/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 5/12/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/14/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/17/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/18/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/19/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/19/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 5/19/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/20/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/21/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/25/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/26/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/27/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/28/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/28/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 7/6/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/14/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/24/2021 Partial Approval JAMES POWERS
T-Bar Ceiling 9/7/2021 Partial Approval JAMES POWERS
Deputy Fireproofing 9/22/2021 Partial Approval JAMES POWERS
Deputy Fireproofing 9/23/2021 Partial Approval JAMES POWERS
Deputy Fireproofing 9/27/2021 Partial Approval JAMES POWERS
Deputy Fireproofing 10/14/2021 Partial Approval JAMES POWERS
Insulation 10/20/2021 Conditional Approval JONATHAN QUACH
Deputy Fireproofing 10/21/2021 Conditional Approval JONATHAN QUACH
Deputy Fireproofing 10/22/2021 Conditional Approval ERNESTO CORRAL
Insulation 10/27/2021 Approved JAMES POWERS
Special/Order Compliance 12/6/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/6/2022 Partial Approval JAMES POWERS
Final 2/8/2022 OK for TCO JAMES POWERS
Footing/Foundation/Slab 2/8/2022 Approved JAMES POWERS
Green Building Final 2/8/2022 Approved JAMES POWERS
Reinforced Concrete Frame 2/8/2022 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 2/8/2022 SGSOV Not Ready JAMES POWERS
Smoke Detectors 2/8/2022 Approved JAMES POWERS
Verify Sprinkler Sign Off 2/8/2022 Approved JAMES POWERS
Wood Frame 2/8/2022 Approved JAMES POWERS
Final 6/13/2022 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 6/13/2022 SGSOV Approved JAMES POWERS
Final 6/27/2022 OK to Issue CofO JAMES POWERS