4335-4335 1/2 E RAYNOL ST 90032

Certificate Information: 4335-4335 1/2 E RAYNOL ST 90032

Application / Permit
18010-10000-05778
Plan Check / Job No.
B18LA25659
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING W/ ATTACHED GARAGE (2-CAR), AND ACCESSORY DWELLING UNIT. ADU @ LOWER. building is fully sprinkler, NFPA-13D
Permit Issued
Issued on 1/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2018 APPLICANT
Assigned to Plan Check Engineer 1/3/2019 SAM CHANG
Corrections Issued 1/11/2019 SAM CHANG
Quality Review Completed 1/17/2019 QUAN NGHIEM
Green Plans Picked Up 1/17/2019 APPLICANT
Building Plans Picked Up 1/22/2019 APPLICANT
Applicant returned to address corrections 4/16/2019 SAM CHANG
Applicant returned to address corrections 4/29/2019 SAM CHANG
Applicant returned to address corrections 9/30/2019 SAM CHANG
Applicant returned to address corrections 10/11/2019 SAM CHANG
Applicant returned to address corrections 12/5/2019 SAM CHANG
Plan Check Approved 1/16/2020 SAM CHANG
Issued 1/16/2020 LADBS
CofO in Progress 9/26/2025 ALIZAH MAYAGOITIA
Permit Finaled 9/28/2025 DEROLD HAUFF
CofO Issued 9/28/2025 DEROLD HAUFF
Permit Finaled 9/28/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/5/2019 JEANETTE VONG
BHO/Hillside ordinance Cleared 6/5/2019 JEANETTE VONG
BHO/Hillside ordinance Cleared 6/5/2019 JEANETTE VONG
Certificate of Compliance Cleared 6/5/2019 JOE LUCKEY
Green Code Cleared 6/25/2019 SARAH ABOULHOSN
Low Impact Development Cleared 7/23/2019 JORGE MEJIA LEMUS
CPC Cleared 8/20/2019 DIANA JIMENEZ
"D" conditions Cleared 9/6/2019 DIANA JIMENEZ
"Q" conditions Cleared 9/6/2019 DIANA JIMENEZ
ZI Cleared 9/6/2019 DIANA JIMENEZ
Eng Process Fee Ord 176,300 Cleared 9/23/2019 DINAH GARIN
Sewer availability Cleared 9/23/2019 DINAH GARIN
Roof/Waste drainage to street Cleared 9/25/2019 JEANETTE VONG
Hydrant and Access approval Cleared 9/26/2019 ROBERT DUFF
GPI Written Notices Cleared 9/30/2019 SAM CHANG
Grading Pre-Inspection Cleared 9/30/2019 SAM CHANG
Disturb/Remove Protected Trees Cleared 12/18/2019 JOHN KIM
Trees in Parkway Cleared 12/20/2019 JOHN KIM
Permit Cleared 1/2/2020 JAMES KHO

Contact Information

Contractor Owner-Builder       ,
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367
Geologist Irvine,, Jon A; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 8/24/2020 Not Ready for Inspection OSVALDO PARAMO
Deputy Reinf. Concrete 9/1/2020 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 9/2/2020 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/4/2020 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 10/8/2020 Partial Approval OSVALDO PARAMO
Deputy Reinf. Masonry 10/20/2020 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/20/2020 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 10/20/2020 Partial Approval OSVALDO PARAMO
Deputy Reinf. Masonry 10/21/2020 Partial Approval OSVALDO PARAMO
Deputy Reinf. Masonry 10/22/2020 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 10/23/2020 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 10/29/2020 Partial Approval OSVALDO PARAMO
Deputy Reinf. Masonry 11/4/2020 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 11/5/2020 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 11/5/2020 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 12/10/2020 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 3/5/2021 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 3/15/2021 No Access for Inspection OSVALDO PARAMO
Masonry Wall/Backfill 3/19/2021 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 3/25/2021 Approved OSVALDO PARAMO
Footing/Foundation/Slab 4/20/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/17/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 8/27/2021 Approved OSVALDO PARAMO
HVAC-Rough 8/27/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 8/27/2021 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/31/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 8/31/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 9/3/2021 Approved OSVALDO PARAMO
Green Building Rough 9/3/2021 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 9/3/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/10/2021 Approved WILLIAM WREN
Insulation 9/14/2021 Approved OSVALDO PARAMO
Drywall Nailing 9/17/2021 Not Ready for Inspection COREY HUPP
Drywall Nailing 9/21/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/28/2021 Approved OSVALDO PARAMO
Shower Pan 9/28/2021 Approved OSVALDO PARAMO
ELECTRICAL-Final 11/8/2022 No Access for Inspection OSVALDO PARAMO
Gas Test 11/8/2022 No Access for Inspection OSVALDO PARAMO
Final 6/30/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 6/30/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 6/30/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 6/30/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 6/30/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 8/19/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 8/19/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Pre-Inspection 8/19/2025 Partial Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 8/19/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 8/19/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 8/26/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 9/2/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 9/2/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 9/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 9/2/2025 Approved ALIZAH MAYAGOITIA
Final 9/9/2025 Conditional Approval ALIZAH MAYAGOITIA
Service/Power Release 9/9/2025 Approved ALIZAH MAYAGOITIA
Final 9/26/2025 OK to Issue CofO ALIZAH MAYAGOITIA