2401 N TRACY TER 90027
Certificate Information: 2401 N TRACY TER 90027
- Application / Permit
- 18010-10000-05644
- Plan Check / Job No.
- B18LA25323
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 17'-0'' X 27'-0'' DETACHED ACCESSORY DWELLING UNIT (424 SQFT.0 PER AB 2299 AND SB 1069. STATE APPROVED FACTORY BUILT HOUSING WITH 500 SQFT. BASEMENT GARAGE.
- Permit Issued
- Issued on 4/2/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2018 | APPLICANT |
| Green Plans Picked Up | 12/11/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2018 | ADAM HEGAZI |
| Corrections Issued | 12/26/2018 | ADAM HEGAZI |
| Quality Review Completed | 12/27/2018 | MOHAMMAD FIROUZBAKHT |
| Building Plans Picked Up | 1/8/2019 | APPLICANT |
| Plan Check Approved | 3/15/2019 | ADAM HEGAZI |
| Issued | 4/2/2019 | LADBS |
| CofO in Progress | 5/7/2021 | JOSEPH MCGARRY |
| Permit Finaled | 5/11/2021 | DEROLD HAUFF |
| CofO Issued | 5/11/2021 | DEROLD HAUFF |
| Permit Finaled | 5/11/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/23/2019 | PATRICK MISCHLICH |
| Address approval | Cleared | 2/8/2019 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 2/8/2019 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2019 | JAMES MORALEZ |
| Permit | Cleared | 2/8/2019 | JAMES MORALEZ |
| Sewer availability | Cleared | 2/8/2019 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 2/22/2019 | GEORGE SUCHAND |
| Trees in Parkway | Cleared | 2/26/2019 | JOHN KIM |
| Green Code | Cleared | 3/12/2019 | ADAM HEGAZI |
| BHO/Hillside ordinance | Cleared | 3/13/2019 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 3/13/2019 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 3/13/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/13/2019 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 3/15/2019 | ADAM HEGAZI |
Contact Information
| Contractor | Cover Technologies Inc Dba Cover Building Technologies; Lic. No.: 1039029-B | 1219 W 135TH STREET GARDENA, CA 90247 |
| Engineer | Behnam,, Peter George; Lic. No.: S4678 | 722 N LUCIA AVE UNIT A REDONDO BEACH, CA 90277 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/2/2019 | Corrections Issued | BRAD BESCOS |
| Deputy Reinf. Concrete | 1/15/2020 | No Access for Inspection | BRAD BESCOS |
| ELECTRICAL-Rough | 1/15/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 1/15/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Piling/Pier/Caisson | 1/15/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 1/24/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/24/2020 | Partial Approval | JOSEPH MCGARRY |
| Piling/Pier/Caisson | 1/24/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 1/27/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 1/30/2020 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 2/27/2020 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/9/2020 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 3/9/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 3/11/2020 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 4/17/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 4/22/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 6/11/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/11/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Gas Test | 6/19/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/19/2020 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 7/20/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 8/31/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 9/3/2020 | Conditional Approval | DAVID FEILER |
| Deputy Reinf. Concrete | 9/22/2020 | No Access for Inspection | ELMER BLAND |
| PLUMBING-Rough | 11/19/2020 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 11/19/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Steel/Welding | 12/11/2020 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2021 | Approved | JOSEPH MCGARRY |
| Light Gage Steel Frame | 2/16/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/16/2021 | Approved | JOSEPH MCGARRY |
| Structural Steel Frame | 2/16/2021 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/4/2021 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/4/2021 | Off-Hour Fees Due | |
| Drywall Nailing | 3/27/2021 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 3/27/2021 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 3/27/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/27/2021 | Off-Hour Fees Due | |
| Insulation | 3/27/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 3/27/2021 | Off-Hour Fees Due | |
| PLUMBING-Rough | 3/27/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/27/2021 | Off-Hour Fees Due | |
| Drywall Nailing | 3/28/2021 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 3/30/2021 | Approved | JOSEPH MCGARRY |
| Final | 3/30/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Final | 3/30/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 3/30/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/30/2021 | SGSOV Not Ready | JOSEPH MCGARRY |
| Service/Power Release | 3/30/2021 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 3/30/2021 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 3/30/2021 | Approved | JOSEPH MCGARRY |
| Final | 3/31/2021 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/31/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Final | 4/7/2021 | Corrections Issued | JOSEPH MCGARRY |
| Final | 5/5/2021 | OK to Issue CofO | JOSEPH MCGARRY |