6041 W CADILLAC AVE 90034

Certificate Information: 6041 W CADILLAC AVE 90034

Application / Permit
18010-10000-05623
Plan Check / Job No.
B18LA25217
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
STATE APPROVED MRI TRAILER. (OSHPD 1 JURISDICTION). PRE-FAB. NEW FOUNDATION (14' X 64') ZONING AND FOUNDATION CHECK ONLY.
Permit Issued
Issued on 9/14/2020
Issuing Office
Current Status
CofO Issued on 5/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2018 APPLICANT
Assigned to Plan Check Engineer 12/6/2018 KEVIN MORALES
Corrections Issued 12/12/2018 KEVIN MORALES
Disabled Access Plans Picked Up 12/18/2018 APPLICANT
Quality Review Completed 12/19/2018 FELIX FIGUEROA
Building Plans Picked Up 12/20/2018 APPLICANT
Plan Check Approved 9/14/2020 KEVIN MORALES
Issued 9/14/2020 APPLICANT
CofO in Progress 2/4/2021 TIMOTHY BUXTON
CofO in Progress 5/10/2021 EDWIN GREGORYONA
Permit Finaled 5/11/2021 ERNESTO CORRAL
CofO Issued 5/11/2021 ERNESTO CORRAL
Permit Finaled 5/11/2021 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 1/9/2019 SOPHIE GABEL-SCHEINBAU
Prkng lot landscape/Water mgmt Cleared 1/9/2019 SOPHIE GABEL-SCHEINBAU
Roof/Waste drainage to street Cleared 1/9/2019 JEANETTE VONG
Sewer availability Cleared 1/9/2019 JEANETTE VONG
ZA Case Cleared 1/9/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 1/9/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 1/9/2019 SOPHIE GABEL-SCHEINBAU
DAS Clearance Cleared 1/14/2019 SHINE LIN
Eng Process Fee Ord 176,300 Cleared 1/31/2019 ROBYN STEELE
ZA Case Cleared 2/22/2019 ANNA VAN
Low Impact Development Cleared 8/14/2020 ORVAL HERNANDEZ-MARCI

Contact Information

Architect Shen,, Perry Po-Li; Lic. No.: C21154 14469 MERCED AVE      BALDWIN PARK, CA 91706
Contractor Kaiser Foundation Health Plan Inc; Lic. No.: 370871-B 4175 E LA PALMA AVE STE 200      ANAHEIM, CA 92807

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/24/2020 Approved EDWIN GREGORYONA
Footing/Foundation/Slab 11/24/2020 Partial Approval EDWIN GREGORYONA
Grading Pre-Inspection 11/24/2020 Approved EDWIN GREGORYONA
Pre-Inspection 11/24/2020 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 11/24/2020 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 12/1/2020 Conditional Approval TIMOTHY BUXTON
Final 2/1/2021 Conditional Approval TIMOTHY BUXTON
Final 3/18/2021 Conditional Approval EDWIN GREGORYONA
Final 5/10/2021 OK to Issue CofO EDWIN GREGORYONA