2968 W 7TH ST 90005

Certificate Information: 2968 W 7TH ST 90005

Application / Permit
18010-10000-05557
Plan Check / Job No.
B18LA24768
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
TOC TIER 3, New 7-story 228 units apartment and 1st floor retail and restaurant mixed-use building with 5-levels of Type IIIA over 2-levels of Type IA (restaurant and retail use are core and shell only)
Permit Issued
Issued on 9/18/2019
Issuing Office
Metro
Current Status
CofO Issued on 8/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2018 APPLICANT
Assigned to Plan Check Engineer 12/6/2018 LARRY LEE
Corrections Issued 12/18/2018 LARRY LEE
Quality Review Completed 1/3/2019 CHARLES CHANG
Building Plans Picked Up 1/7/2019 APPLICANT
Plan Check Approved 8/29/2019 LARRY LEE
Issued 9/18/2019 LADBS
TCO Issued (Expire Date: 12-28-2022) 7/1/2022 ERNESTO CORRAL
CofO in Progress 8/11/2022 RAFAEL ESPINOZA
CofO Issued 8/11/2022 ERNESTO CORRAL
Permit Finaled 8/11/2022 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/22/2019 KARAN PATEL
Hydrant and Access approval Cleared 2/6/2019 GEORGE SUCHAND
Highway dedication Cleared 3/6/2019 JAMES MORALEZ
Address approval Cleared 4/25/2019 CELINA MORENO
CPC Cleared 5/23/2019 BLAYNE SUTTON-WILLS
Building over 3-story or 36-ft Cleared 5/28/2019 CALOSHA APPROVED
Internal circulation Cleared 5/31/2019 MOHAMMAD HASAN
Density Bonus 12.22.A.31 Cleared 6/11/2019 MICHAEL ZIRBES
Excavation more than 5-ft deep Cleared 6/11/2019 CALOSHA APPROVED
Project located in CRA area Cleared 6/14/2019 JIM URQUHART
Food Service Establishment Cleared 8/1/2019 RAMESHBHAIR PATEL
Bicycle Parking Cleared 8/2/2019 ELENA LOPEZ
Green Code Cleared 8/2/2019 DONALD CRICHLOW
Encroachment in public way Cleared 8/14/2019 KAREN LE
Encroachment in public way Cleared 8/14/2019 KAREN LE
DAS Clearance Cleared 8/16/2019 LARRY LEE
CPC Cleared 8/27/2019 JOE LUCKEY
Miscellaneous Cleared 8/27/2019 JOE LUCKEY
Opn space landscape/Water mgmt Cleared 8/27/2019 JOE LUCKEY
Site Plan review Cleared 8/27/2019 JOE LUCKEY
Methane Ordinance Cleared 8/28/2019 WILLIAM JOHNS
Permit Cleared 8/28/2019 NGOC KIEM
Fire Marshall Fire Life Safety Cleared 8/29/2019 WILLIAM JOHNS
Low Impact Development Cleared 8/29/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/29/2019 ELENA LOPEZ
Sewer availability Cleared 8/29/2019 ELENA LOPEZ
Trees in Parkway Cleared 9/13/2019 ADRIAN SANCHEZ

Contact Information

Contractor Wilshire Construction L P; Lic. No.: 1048091-B 3470 WILSHIRE STE 1010      LOS ANGELES, CA 90010

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/19/2019 Corrections Issued LESLIE TRUJILLO
Deputy Grading 10/15/2019 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/15/2019 Partial Approval JAMES POWERS
METHANE-Barrier 10/15/2019 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 10/15/2019 Not Ready for Inspection JAMES POWERS
Deputy Grading 10/16/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/16/2019 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/16/2019 Partial Approval JAMES POWERS
Deputy Grading 10/17/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/17/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/17/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/17/2019 Partial Approval JAMES POWERS
METHANE-Barrier 10/17/2019 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 10/17/2019 Not Ready for Inspection JAMES POWERS
Deputy Grading 10/18/2019 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/18/2019 Partial Approval JAMES POWERS
Deputy Grading 10/21/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/21/2019 Conditional Approval LESLIE TRUJILLO
Structural Steel Frame 10/21/2019 Partial Inspection LESLIE TRUJILLO
Deputy Grading 10/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Grading 10/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Grading 10/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Grading 10/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/28/2019 Conditional Approval LESLIE TRUJILLO
Deputy Grading 10/29/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/29/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/31/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/1/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Grading 11/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Grading 11/14/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/14/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 12/19/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 12/19/2019 Conditional Approval LESLIE TRUJILLO
METHANE-Subgrade 12/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/6/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/7/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/8/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/8/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/9/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/9/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/10/2020 Conditional Approval LESLIE TRUJILLO
Green Building Rough 1/10/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 1/10/2020 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 1/10/2020 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 1/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/14/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/17/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/17/2020 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 1/17/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/23/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/27/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 1/27/2020 Partial Inspection RAFAEL ESPINOZA
METHANE-Subgrade 1/27/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 1/28/2020 Approved RAFAEL ESPINOZA
Deputy Shotcrete 1/31/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/5/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 2/5/2020 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 2/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 2/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 2/5/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 2/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/6/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 2/6/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/7/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 2/7/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 2/11/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 2/12/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 2/13/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 2/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Methane Barrier 2/18/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 2/18/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 2/18/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Subgrade 2/18/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/19/2020 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 2/24/2020 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 2/26/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 2/28/2020 Approved RAFAEL ESPINOZA
Masonry Wall/Backfill 2/28/2020 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 3/4/2020 Partial Approval RAFAEL ESPINOZA
Piling/Pier/Caisson 3/4/2020 Partial Approval RAFAEL ESPINOZA
Green Building Rough 3/9/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 3/9/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 3/9/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/9/2020 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 3/20/2020 Partial Approval RAFAEL ESPINOZA
Green Building Rough 3/20/2020 Approved RAFAEL ESPINOZA
METHANE-Rough 3/20/2020 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/20/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/23/2020 Conditional Approval LESLIE TRUJILLO
METHANE-Barrier 3/23/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 3/23/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/24/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 3/25/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Barrier 3/25/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Subgrade 3/25/2020 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 3/26/2020 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 4/1/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/2/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/2/2020 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 4/2/2020 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 4/3/2020 Partial Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 4/3/2020 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 4/14/2020 Partial Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 4/14/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 4/15/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 4/16/2020 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 4/16/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 4/17/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/24/2020 Partial Inspection RAFAEL ESPINOZA
METHANE-Barrier 4/24/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Subgrade 4/24/2020 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 4/27/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/28/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/28/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Rough 4/28/2020 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 4/28/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/29/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/30/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/1/2020 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 5/4/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/5/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/6/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/6/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 5/6/2020 Partial Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 5/6/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/7/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/7/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/8/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/8/2020 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 5/8/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/12/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/12/2020 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 5/12/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/13/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/13/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/14/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/14/2020 Conditional Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 5/14/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/15/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/15/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/18/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/18/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/18/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Barrier 5/18/2020 Approved RAFAEL ESPINOZA
METHANE-Rough 5/18/2020 Partial Inspection RAFAEL ESPINOZA
METHANE-Subgrade 5/18/2020 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 5/18/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/18/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/20/2020 Conditional Approval RAFAEL ESPINOZA
METHANE-Rough 5/21/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 5/21/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/21/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 5/26/2020 Not Ready for Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 5/26/2020 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 5/26/2020 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/26/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Drilled-In Anchors 5/27/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/27/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/27/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 5/27/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 5/27/2020 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 5/28/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/28/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/28/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 5/28/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/28/2020 Partial Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 5/29/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/29/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 5/29/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 5/29/2020 Conditional Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 5/29/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/1/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 6/3/2020 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/3/2020 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 6/3/2020 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 6/4/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/5/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 6/5/2020 Conditional Approval RAFAEL ESPINOZA
METHANE-Rough 6/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 6/5/2020 Partial Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 6/5/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/5/2020 Not Ready for Inspection RAFAEL ESPINOZA
METHANE-Rough 6/10/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 6/10/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/10/2020 Not Ready for Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 6/11/2020 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/23/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/24/2020 Conditional Approval NICK DANERI
Footing/Foundation/Slab 7/7/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/9/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 7/9/2020 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 7/14/2020 Conditional Approval RAFAEL ESPINOZA
METHANE-Rough 7/17/2020 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 7/17/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/17/2020 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/3/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/10/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/24/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Partial Approval RAFAEL ESPINOZA
METHANE-Rough 9/4/2020 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 9/4/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 9/9/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/9/2020 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/24/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Partial Approval RAFAEL ESPINOZA
Insulation 10/5/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 10/5/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/6/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/21/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/21/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/23/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/23/2020 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 11/25/2020 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 12/1/2020 Partial Approval RAFAEL ESPINOZA
Insulation 12/11/2020 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 12/15/2020 Conditional Approval RAFAEL ESPINOZA
Special/Order Compliance 12/15/2020 Corrections Issued RAFAEL ESPINOZA
Drywall Nailing 12/16/2020 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 12/16/2020 Approved RAFAEL ESPINOZA
Drywall Nailing 12/28/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 1/4/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 1/4/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 1/6/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 1/20/2021 Partial Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 2/2/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/17/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/4/2021 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 3/10/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/10/2021 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 3/17/2021 Partial Approval RAFAEL ESPINOZA
METHANE-Rough 3/24/2021 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 3/24/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 3/24/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/30/2021 Partial Approval NICK DANERI
Drywall Nailing 4/7/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 4/7/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/13/2021 Partial Approval NICK DANERI
Deputy Steel/Welding 4/15/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/16/2021 Partial Approval JAMES POWERS
Drywall Nailing 4/23/2021 Partial Approval DAVID BURKHEAD
Drywall Nailing 5/11/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/21/2021 Partial Approval NICK DANERI
Reinforced Masonry Frame 5/26/2021 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 5/26/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 6/1/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/14/2021 Partial Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 6/23/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/1/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/8/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 7/8/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/9/2021 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 7/15/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 7/15/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 7/19/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/19/2021 Partial Approval JAMES POWERS
Drywall Nailing 7/28/2021 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 7/28/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 7/28/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 7/28/2021 Not Ready for Inspection JAMES POWERS
Drywall Nailing 8/5/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/5/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 8/18/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/18/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 8/25/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 8/25/2021 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 8/27/2021 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 10/5/2021 Partial Approval TIMOTHY BUXTON
Pre-Inspection 10/8/2021 Corrections Issued RAFAEL ESPINOZA
Light Gage Steel Frame 11/29/2021 Partial Approval NICK DANERI
Drywall Nailing 12/6/2021 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 1/11/2022 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 1/26/2022 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 1/26/2022 Approved RAFAEL ESPINOZA
Drywall Nailing 2/8/2022 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 2/23/2022 Partial Inspection RAFAEL ESPINOZA
Pre-Inspection 5/10/2022 Partial Inspection RAFAEL ESPINOZA
Special/Order Compliance 6/3/2022 Approved RAFAEL ESPINOZA
Pre-Inspection 6/27/2022 Partial Inspection RAFAEL ESPINOZA
Drywall Nailing 6/29/2022 Approved RAFAEL ESPINOZA
Final 6/29/2022 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 6/29/2022 Approved RAFAEL ESPINOZA
Green Building Final 6/29/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 6/29/2022 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 6/29/2022 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 6/29/2022 SGSOV Not Ready RAFAEL ESPINOZA
Smoke Detectors 6/29/2022 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 6/29/2022 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 6/29/2022 Not Ready for Inspection RAFAEL ESPINOZA
Final 8/11/2022 OK to Issue CofO RAFAEL ESPINOZA
Green Building Final 8/11/2022 Approved RAFAEL ESPINOZA
Reinforced Concrete Frame 8/11/2022 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 8/11/2022 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 8/11/2022 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/11/2022 Approved RAFAEL ESPINOZA
Wood Frame 8/11/2022 Approved RAFAEL ESPINOZA