5768 W 3RD ST 90036

Certificate Information: 5768 W 3RD ST 90036

Application / Permit
18010-10000-05554
Plan Check / Job No.
B18LA24747
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
(N) 46 UNIT 5 STORY APARTMENT. TYPE III-A OVER 1 GRADE LEVEL PARKING GARAGE AND 1 LEVEL OF BASEMENT PARKING. 41 MARKET RATE AND 5 EXTREMELY LOW INCOME UNITS
Permit Issued
Issued on 5/14/2021
Issuing Office
Metro
Current Status
CofO Issued on 2/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2018 APPLICANT
Assigned to Plan Check Engineer 1/3/2019 HERNAN ARREOLA
Corrections Issued 1/7/2019 MOHAMMAD FIROUZBAKHT
Quality Review Completed 1/17/2019 FELIX FIGUEROA
Building Plans Picked Up 1/22/2019 APPLICANT
Applicant returned to address corrections 7/23/2019 HERNAN ARREOLA
Applicant returned to address corrections 1/9/2020 HERNAN ARREOLA
Applicant returned to address corrections 9/28/2020 HERNAN ARREOLA
Applicant returned to address corrections 1/11/2021 HERNAN ARREOLA
Plan Check Approved 5/13/2021 HERNAN ARREOLA
Issued 5/14/2021 APPLICANT
CofO in Progress 2/13/2024 EDWIN GREGORYONA
CofO Issued 2/13/2024 ERNESTO CORRAL
Permit Finaled 2/13/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 2/6/2019 JAMES KHO
Bicycle Parking Cleared 2/6/2019 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 2/6/2019 JAMES KHO
Abandoned oil well Cleared 6/13/2019 ROBERT DUFF
Abandoned oil well approval Cleared 6/13/2019 ROBERT DUFF
Hydrant and Access approval Cleared 6/13/2019 ROBERT DUFF
DAS Clearance Cleared 11/14/2019 MOHAMMAD FIROUZBAKHT
Green Code Cleared 11/18/2019 KHEDER ALRAZAA
Encroachment in public way Cleared 1/9/2020 ELAINE LEI
Fire Marshall Fire Life Safety Cleared 1/23/2020 ANDREW KO
Encroachment in public way Cleared 1/27/2020 ELENA LOPEZ
Miscellaneous Cleared 2/11/2020 TERRI OSBORNE
Miscellaneous Cleared 2/11/2020 TERRI OSBORNE
Sewer availability Cleared 2/19/2020 THOMAS LANG
Building over 3-story or 36-ft Cleared 3/26/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/26/2020 CALOSHA APPROVED
Density Bonus 12.22.A.31 Cleared 5/5/2020 JAMES MCCARTHY
Highway dedication Cleared 7/28/2020 CELINA MORENO
Construction near power lines Cleared 9/10/2020 RIDWAN HARDY
Low Impact Development Cleared 11/5/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/17/2020 WALLIE JONG
Mechanical Car Lift Cleared 1/7/2021 ANDREW KO
Methane Ordinance Cleared 2/22/2021 ANDREW KO
Work Adjacent to Public Way Cleared 4/1/2021 CHIU TAM

Contact Information

Architect Carlson,, Edward Xavier; Lic. No.: C18577 710 E VERDUGO AVENUE # 102      BURBANK, CA 91501
Contractor Owner-Builder       ,
Engineer Dejban,, Masoud; Lic. No.: S2521 17200 VENTURA BLVD STE 213A      ENCINO, CA 91316

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 9/1/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 9/7/2021 Conditional Approval LANNY MERRICK
Deputy Methane Barrier 9/8/2021 Conditional Approval LANNY MERRICK
Deputy Methane Barrier 9/9/2021 Conditional Approval LANNY MERRICK
Footing/Foundation/Slab 9/9/2021 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 9/9/2021 Partial Approval EDWIN GREGORYONA
METHANE-Subgrade 9/9/2021 Approved EDWIN GREGORYONA
Deputy Methane Barrier 9/10/2021 Conditional Approval LANNY MERRICK
Deputy Reinf. Concrete 9/10/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 9/10/2021 Partial Approval EDWIN GREGORYONA
METHANE-Rough 9/10/2021 Partial Approval EDWIN GREGORYONA
Piling/Pier/Caisson 9/10/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 9/16/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 9/16/2021 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 9/16/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 9/22/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 9/23/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 9/24/2021 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 9/24/2021 Partial Approval EDWIN GREGORYONA
Deputy Methane Barrier 9/27/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/21/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 10/25/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/4/2021 Conditional Approval TED RIES
Deputy Shotcrete 11/4/2021 Conditional Approval TED RIES
Deputy Reinf. Concrete 11/10/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/23/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/23/2021 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 12/7/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/13/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 12/13/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/16/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 12/28/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/18/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/19/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/25/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/22/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 3/18/2022 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 3/18/2022 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 3/18/2022 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/6/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/6/2022 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 4/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 4/18/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 4/25/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 5/10/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/11/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/11/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 5/11/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 6/8/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 7/6/2022 Conditional Approval ERNESTO CORRAL
Green Building Rough 7/7/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 7/7/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 7/7/2022 Partial Inspection EDWIN GREGORYONA
Insulation 8/11/2022 Partial Inspection EDWIN GREGORYONA
Wall Anchors 8/11/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/7/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 9/7/2022 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 9/7/2022 Approved EDWIN GREGORYONA
Insulation 10/3/2022 Partial Approval GREGORY POMISH
Drywall Nailing 10/26/2022 Approved EDWIN GREGORYONA
Insulation 10/26/2022 Partial Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 11/1/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 11/2/2022 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 11/10/2022 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 12/14/2022 Approved EDWIN GREGORYONA
Green Building Final 5/8/2023 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 8/4/2023 Approved EDWIN GREGORYONA
Final 8/4/2023 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 8/4/2023 Approved EDWIN GREGORYONA
Green Building Final 8/4/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Barrier 8/4/2023 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 8/4/2023 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 8/4/2023 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 8/4/2023 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 8/4/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 8/4/2023 Approved EDWIN GREGORYONA
Final 1/18/2024 Partial Inspection EDWIN GREGORYONA
Green Building Final 1/18/2024 Partial Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 1/18/2024 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 1/18/2024 Approved EDWIN GREGORYONA
Final 2/9/2024 Conditional Approval EDWIN GREGORYONA
Green Building Final 2/9/2024 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 2/9/2024 SGSOV Approved EDWIN GREGORYONA