2350 N LANDA ST 90039
Certificate Information: 2350 N LANDA ST 90039
- Application / Permit
- 18010-10000-05537
- Plan Check / Job No.
- B18LA24658
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONSTRUCT NEW 1353 SF SFR W/2 CAR 407 SF ATTACHED GARAGE
- Permit Issued
- Issued on 2/13/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2018 | APPLICANT |
| Green Plans Picked Up | 12/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2018 | VU NGUYEN |
| Corrections Issued | 12/27/2018 | VU NGUYEN |
| Quality Review Completed | 12/28/2018 | MICHAEL PEREZ |
| Building Plans Picked Up | 1/3/2019 | APPLICANT |
| Applicant returned to address corrections | 9/18/2019 | VU NGUYEN |
| Applicant returned to address corrections | 10/28/2019 | VU NGUYEN |
| Plan Check Approved | 2/3/2020 | VU NGUYEN |
| Issued | 2/13/2020 | LADBS |
| CofO in Progress | 5/17/2022 | STUART CHAPMAN |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
| CofO Issued | 5/21/2022 | DEROLD HAUFF |
| Permit Finaled | 5/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 8/5/2019 | SARAH ABOULHOSN |
| Hydrant and Access approval | Cleared | 8/28/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 8/28/2019 | MITESH PATEL |
| Address approval | Cleared | 8/30/2019 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 8/30/2019 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 8/30/2019 | JEANETTE VONG |
| Permit | Cleared | 8/30/2019 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 8/30/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2019 | THOMAS LANG |
| Sewer availability | Cleared | 10/15/2019 | THOMAS LANG |
| Trees in Parkway | Cleared | 10/15/2019 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 10/28/2019 | EMIL KYUPELYAN |
| GPI Written Notices | Cleared | 10/28/2019 | VU NGUYEN |
| Grading Pre-Inspection | Cleared | 10/28/2019 | VU NGUYEN |
| Disturb/Remove Protected Trees | Cleared | 2/3/2020 | STEPHEN DUPREY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
| Engineer | Jones,, Ryan Keith; Lic. No.: GE2852 | 1253 W MASLINE ST COVINA, CA 91722 |
| Geologist | Yang,, Raymond; Lic. No.: EG2459 | 21552 CARRISO ROAD DIAMOND BAR, CA 91765 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2020 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 7/14/2020 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/28/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 8/4/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 8/11/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 8/20/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2020 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/3/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 12/3/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 12/3/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/7/2020 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 12/7/2020 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 1/14/2021 | Not Ready for Inspection | COREY HUPP |
| HVAC-Rough | 1/14/2021 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 1/14/2021 | Partial Approval | COREY HUPP |
| MERV13>=Rough | 1/14/2021 | Approved | COREY HUPP |
| Verify Sprinkler Sign Off | 1/14/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 1/21/2021 | Conditional Approval | COREY HUPP |
| Green Building Rough | 1/21/2021 | Approved | COREY HUPP |
| Insulation | 1/27/2021 | Conditional Approval | SCOTT FINNILA |
| Drywall Nailing | 2/5/2021 | Conditional Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 2/22/2021 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/20/2021 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 5/20/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/9/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 12/9/2021 | Corrections Issued | STUART CHAPMAN |
| Final | 12/9/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/9/2021 | Approved | STUART CHAPMAN |
| Green Building Final | 12/9/2021 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 12/9/2021 | Corrections Issued | STUART CHAPMAN |
| MERV13>=Final | 12/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 12/9/2021 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 12/9/2021 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 12/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 12/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 12/17/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Gas Test | 12/17/2021 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 12/17/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 1/19/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 1/19/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 1/19/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 1/19/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 1/19/2022 | Approved | THOMAS LOGRASSO |
| Final | 1/28/2022 | Partial Approval | STUART CHAPMAN |
| Green Building Final | 1/28/2022 | Approved | STUART CHAPMAN |
| MERV13>=Final | 1/28/2022 | Approved | STUART CHAPMAN |
| Service/Power Release | 1/28/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 5/6/2022 | Approved | STUART CHAPMAN |
| HVAC-Final | 5/6/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Final | 5/6/2022 | Approved | STUART CHAPMAN |
| Final | 5/17/2022 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 5/17/2022 | Approved | STUART CHAPMAN |