236 1/2 E 24TH ST 90011

Certificate Information: 236 1/2 E 24TH ST 90011

Application / Permit
18010-10000-05508
Plan Check / Job No.
B18LA24480
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ACCESSORY DWELLING UNIT WITH ROOFTOP DECK OVER ATTACHED CARPORT PER AB 494 & SB 229
Permit Issued
Issued on 4/20/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2018 APPLICANT
Assigned to Plan Check Engineer 12/13/2018 PRANITA SHAH
Green Plans Picked Up 12/20/2018 APPLICANT
Corrections Issued 1/9/2019 PRANITA SHAH
Quality Review Completed 1/25/2019 BILL STUTSMAN
Building Plans Picked Up 2/8/2019 APPLICANT
Applicant returned to address corrections 7/11/2019 PRANITA SHAH
Applicant returned to address corrections 9/9/2019 PRANITA SHAH
Plan Check Approved 9/27/2019 PRANITA SHAH
Issued 4/20/2020 LADBS
CofO in Progress 11/28/2022 HORACE FULTZ
Permit Finaled 12/22/2022 DEROLD HAUFF
CofO Issued 12/22/2022 DEROLD HAUFF
Permit Finaled 12/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/27/2019 JEANIE LAM
Construction near power lines Cleared 4/4/2019 RIDWAN HARDY
Green Code Cleared 4/25/2019 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 7/10/2019 ELAINE LEI
Hydrant and Access approval Cleared 7/10/2019 GEORGE SUCHAND
Low Impact Development Cleared 7/10/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/10/2019 ELAINE LEI
Sewer availability Cleared 7/10/2019 ELAINE LEI

Contact Information

Contractor Owner-Builder       ,
Engineer Velasco,, Jose Luis; Lic. No.: C76091 8371 BENJAMIN DR      HUNTINGTON BEACH, CA 92647

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/28/2020 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 9/11/2020 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 9/15/2020 Approved COREY HUPP
Deputy Reinf. Concrete 9/17/2020 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 9/24/2020 Partial Approval ROBERT MCDOWELL
BUILDING-Rough-Frame 9/29/2020 Partial Approval DAVID FEILER
Green Building Rough 9/29/2020 Not Ready for Inspection DAVID FEILER
METHANE-Rough 9/29/2020 Not Ready for Inspection DAVID FEILER
Verify Sprinkler Sign Off 9/29/2020 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/19/2020 Partial Approval ROBERT MCDOWELL
Green Building Rough 10/19/2020 Not Ready for Inspection ROBERT MCDOWELL
METHANE-Rough 10/19/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 10/19/2020 Partial Approval ROBERT MCDOWELL
Verify Sprinkler Sign Off 10/19/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 11/25/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 11/25/2020 Approved ROBERT MCDOWELL
Gas Test 11/25/2020 Partial Approval ROBERT MCDOWELL
Green Building Rough 11/25/2020 Approved ROBERT MCDOWELL
HVAC-Rough 11/25/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 11/25/2020 Approved ROBERT MCDOWELL
Insulation 12/2/2020 Not Ready for Inspection DAVID FEILER
Insulation 12/7/2020 Corrections Issued DAVID FEILER
Insulation 12/15/2020 Approved FREDDIE RIVERA
Drywall Nailing 12/29/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 12/29/2020 Approved ROBERT MCDOWELL
Gas Test 5/20/2021 Partial Approval ROBERT MCDOWELL
Sewer 5/20/2021 Approved ROBERT MCDOWELL
Special/Order Compliance 7/6/2021 Approved HORACE FULTZ
Special/Order Compliance 7/8/2021 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 8/19/2021 Approved JOAQUIN GREENOUGH
Final 10/6/2022 Partial Inspection SHAVONNE ESPINOZA
Footing/Foundation/Slab 10/6/2022 Partial Inspection SHAVONNE ESPINOZA
Green Building Final 10/6/2022 Partial Inspection SHAVONNE ESPINOZA
METHANE-Barrier 10/6/2022 Partial Inspection SHAVONNE ESPINOZA
METHANE-Subgrade 10/6/2022 Partial Inspection SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Not Ready SHAVONNE ESPINOZA
Service/Power Release 10/6/2022 Partial Inspection SHAVONNE ESPINOZA
Smoke Detectors 10/6/2022 Partial Inspection SHAVONNE ESPINOZA
Final 11/21/2022 Partial Inspection JULIAN AMAYA
Footing/Foundation/Slab 11/21/2022 Partial Inspection JULIAN AMAYA
Green Building Final 11/21/2022 Partial Inspection JULIAN AMAYA
METHANE-Barrier 11/21/2022 Partial Inspection JULIAN AMAYA
METHANE-Subgrade 11/21/2022 Partial Inspection JULIAN AMAYA
SGSOV-Seismic Gas S/O Valve 11/21/2022 SGSOV Not Ready JULIAN AMAYA
Service/Power Release 11/21/2022 Partial Inspection JULIAN AMAYA
Smoke Detectors 11/21/2022 Approved JULIAN AMAYA
ELECTRICAL-Final 11/23/2022 Approved HORACE FULTZ
Final 11/23/2022 OK to Issue CofO HORACE FULTZ
Footing/Foundation/Slab 11/23/2022 Approved HORACE FULTZ
Green Building Final 11/23/2022 Approved HORACE FULTZ
HVAC-Final 11/23/2022 Approved HORACE FULTZ
MERV13>=Final 11/23/2022 Approved HORACE FULTZ
METHANE-Barrier 11/23/2022 No Access for Inspection HORACE FULTZ
METHANE-Subgrade 11/23/2022 Approved HORACE FULTZ
PLUMBING-Final 11/23/2022 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Approved HORACE FULTZ
Service/Power Release 11/23/2022 Approved HORACE FULTZ