2330 W CARLYLE PL 90065

Certificate Information: 2330 W CARLYLE PL 90065

Application / Permit
18010-10000-05502
Plan Check / Job No.
B18LA24468
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ACCESSORY DWELLING UNIT
Permit Issued
Issued on 7/26/2021
Issuing Office
Current Status
CofO Issued on 12/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2018 APPLICANT
Assigned to Plan Check Engineer 12/13/2018 PRANITA SHAH
Green Plans Picked Up 12/21/2018 APPLICANT
Corrections Issued 12/26/2018 PRANITA SHAH
Quality Review Completed 1/4/2019 MINYE PAK
Building Plans Picked Up 1/7/2019 APPLICANT
Applicant returned to address corrections 6/18/2019 PRANITA SHAH
Applicant returned to address corrections 4/7/2020 PRANITA SHAH
Applicant returned to address corrections 8/5/2020 PRANITA SHAH
Applicant returned to address corrections 11/24/2020 PRANITA SHAH
Applicant returned to address corrections 6/9/2021 PRANITA SHAH
Plan Check Approved 7/22/2021 PRANITA SHAH
Issued 7/26/2021 APPLICANT
CofO in Progress 12/21/2023 HAMIK HARTOUNIAN
Permit Finaled 12/28/2023 DEROLD HAUFF
CofO Issued 12/28/2023 DEROLD HAUFF
Permit Finaled 12/28/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/5/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/5/2019 JEANIE LAM
Permit Cleared 3/5/2019 JEANIE LAM
Hydrant and Access approval Cleared 5/30/2019 GILBERT URREA
GPI Written Notices Cleared 11/25/2020 PRANITA SHAH
Grading Pre-Inspection Cleared 11/25/2020 PRANITA SHAH
Specific Plan Cleared 3/30/2021 OLGA RUANO
ZI Cleared 3/30/2021 OLGA RUANO
Sewer availability Cleared 4/9/2021 JEANIE LAM
Low Impact Development Cleared 5/6/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/14/2021 ROSA SILVA

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/17/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/16/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/19/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/8/2022 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 2/8/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2022 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/25/2022 Not Ready for Inspection AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 6/7/2022 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 7/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 7/7/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 7/7/2022 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 7/7/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/15/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/26/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 7/26/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/26/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 7/26/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/1/2022 Partial Approval HAMIK HARTOUNIAN
Insulation 8/26/2022 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 9/16/2022 Corrections Issued HAMIK HARTOUNIAN
Insulation 9/16/2022 Partial Approval HAMIK HARTOUNIAN
Shower Pan 9/16/2022 Approved HAMIK HARTOUNIAN
Insulation 9/20/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/20/2022 Approved HAMIK HARTOUNIAN
Shower Pan 9/20/2022 Partial Approval HAMIK HARTOUNIAN
Insulation 10/27/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/15/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 12/15/2023 Approved HAMIK HARTOUNIAN
Final 12/15/2023 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 12/15/2023 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 12/15/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Final 12/15/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/15/2023 SGSOV Gas Company HAMIK HARTOUNIAN
Service/Power Release 12/15/2023 Approved HAMIK HARTOUNIAN
Smoke Detectors 12/15/2023 Approved HAMIK HARTOUNIAN
Final 12/21/2023 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 12/21/2023 Approved HAMIK HARTOUNIAN