10412 S CROESUS AVE 90002
Certificate Information: 10412 S CROESUS AVE 90002
- Application / Permit
- 18010-10000-05476
- Plan Check / Job No.
- B18LA22804
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 2-CAR GARAGE AT REAR OF LOT. PERMIT 2 OF 2
- Permit Issued
- Issued on 6/14/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2018 | APPLICANT |
| Green Plans Picked Up | 10/30/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/8/2018 | JEFFREY MACHADO |
| Corrections Issued | 11/13/2018 | JEFFREY MACHADO |
| Quality Review Completed | 11/28/2018 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 11/30/2018 | APPLICANT |
| Plan Check Approved | 4/18/2019 | JEFFREY MACHADO |
| Issued | 6/14/2019 | LADBS |
| CofO in Progress | 5/11/2020 | WILLIAM ROSE |
| No Progress | 5/14/2020 | BOB DUNN |
| CofO in Progress | 5/26/2020 | BOB DUNN |
| Permit Finaled | 5/26/2020 | BOB DUNN |
| CofO Issued | 5/26/2020 | BOB DUNN |
| Permit Finaled | 5/26/2020 | BOB DUNN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/2/2019 | STEVE MELGAR |
| Green Code | Cleared | 3/14/2019 | NEGAR NEJAD |
| Low Impact Development | Cleared | 4/5/2019 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 4/5/2019 | ELAINE LEI |
| Construction near power lines | Cleared | 4/8/2019 | WALTER RAMIREZ |
Contact Information
| Contractor | Nelson General Building Contractor; Lic. No.: 649194-B | 4227 S WESTERN AVE LOS ANGELES, CA 90062 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 26851 GRAYSLAKE ROAD RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/12/2019 | Corrections Issued | WILLIAM ROSE |
| Footing/Foundation/Slab | 7/17/2019 | Approved | WILLIAM ROSE |
| BUILDING-Rough-Frame | 10/3/2019 | Approved | WILLIAM ROSE |
| Drywall Nailing | 11/6/2019 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/6/2019 | Approved | EUGENE CASSIDY |
| Final | 2/20/2020 | Not Ready for Inspection | WILLIAM ROSE |
| SGSOV-Seismic Gas S/O Valve | 2/20/2020 | SGSOV Approved | WILLIAM ROSE |
| Service/Power Release | 2/20/2020 | Not Required | WILLIAM ROSE |
| Smoke Detectors | 2/20/2020 | Approved | WILLIAM ROSE |
| Final | 3/17/2020 | OK to Issue CofO | WILLIAM ROSE |