1423 E MITCHELL PL 90033

Certificate Information: 1423 E MITCHELL PL 90033

Application / Permit
18010-10000-05349
Plan Check / Job No.
B18LA23477
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW IRREGULAR SHAPED (33' X 26.17') POOL GAZEBO WITH STORAGE ROOM, HALF BATHROOM AND OUTDOOR SHOWER .
Permit Issued
Issued on 1/2/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2018 APPLICANT
Assigned to Plan Check Engineer 11/30/2018 LUIS RINCON
Corrections Issued 12/4/2018 LUIS RINCON
Quality Review Completed 12/5/2018 MOHAMMAD FIROUZBAKHT
Green Plans Picked Up 12/11/2018 APPLICANT
Building Plans Picked Up 3/14/2019 APPLICANT
Plan Check Approved 12/18/2019 LUIS RINCON
Issued 1/2/2020 LADBS
CofO in Progress 3/2/2022 OSVALDO PARAMO
CofO in Progress 3/2/2022 OSVALDO PARAMO
Permit Finaled 6/18/2022 DEROLD HAUFF
CofO Issued 6/18/2022 DEROLD HAUFF
Permit Finaled 6/18/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 3/14/2019 KHEDER ALRAZAA
Clean Up Green Up Cleared 10/8/2019 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 10/8/2019 EMIL KYUPELYAN
Sewer availability Cleared 10/8/2019 EMIL KYUPELYAN
ZI Cleared 10/8/2019 ANNA VIDAL
Low Impact Development Cleared 11/14/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/14/2019 THOMAS LANG
Grading Pre-Inspection Cleared 11/18/2019 LUIS RINCON
Grading Pre-Inspection Cleared 11/18/2019 LUIS RINCON
GPI Written Notices Cleared 12/11/2019 LUIS RINCON
Hydrant and Access approval Cleared 12/11/2019 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/7/2020 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 1/7/2020 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 1/7/2020 Corrections Issued OSVALDO PARAMO
Green Building Rough 1/7/2020 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 1/7/2020 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 1/7/2020 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 1/7/2020 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 2/18/2021 Conditional Approval OSVALDO PARAMO
METHANE-Barrier 2/18/2021 Approved OSVALDO PARAMO
METHANE-Subgrade 2/18/2021 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/15/2021 Approved OSVALDO PARAMO
Footing/Foundation/Slab 3/15/2021 Approved OSVALDO PARAMO
Wood Frame 4/6/2021 Not Ready for Inspection ROBERT VORHIS
Wood Frame 4/16/2021 Corrections Issued OSVALDO PARAMO
Deputy Drilled-In Anchors 5/28/2021 Conditional Approval CHRISTOPHER DELLEFIELD
Wood Frame 6/9/2021 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 7/7/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 7/7/2021 Approved OSVALDO PARAMO
Drywall Nailing 8/11/2021 Approved OSVALDO PARAMO
Green Building Rough 8/11/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 8/11/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 3/1/2022 Approved OSVALDO PARAMO
Final 3/1/2022 OK to Issue CofO OSVALDO PARAMO
Green Building Final 3/1/2022 Approved OSVALDO PARAMO
METHANE-Final 3/1/2022 Approved OSVALDO PARAMO
METHANE-Rough 3/1/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Approved OSVALDO PARAMO
Service/Power Release 3/1/2022 Approved OSVALDO PARAMO
Smoke Detectors 3/1/2022 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 3/1/2022 Approved OSVALDO PARAMO