11404 W KLING ST 91602
Certificate Information: 11404 W KLING ST 91602
- Application / Permit
- 18010-10000-05308
- Plan Check / Job No.
- B18LA23264
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 32'-1" X 26'-7" TWO-STORY ACCESSORY DWELLING UNIT WITH ATTACHED 2-CAR GARAGE AT FIRST FLOOR PER AB 494 AND SB 229.
- Permit Issued
- Issued on 4/24/2020
- Issuing Office
- Current Status
- CofO Issued on 12/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2018 | ROSENDO MEDINA |
| Corrections Issued | 11/27/2018 | ROSENDO MEDINA |
| Quality Review Completed | 11/28/2018 | TIEN JEN WANG |
| Building Plans Picked Up | 2/4/2019 | APPLICANT |
| Green Plans Picked Up | 3/5/2019 | APPLICANT |
| Plan Check Approved | 9/24/2019 | ROSENDO MEDINA |
| Plan Check Approved | 10/30/2019 | ROSENDO MEDINA |
| Issued | 4/24/2020 | APPLICANT |
| CofO in Progress | 12/9/2022 | JACK KARGODORIAN |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
| CofO Issued | 12/10/2022 | MICHAEL SMITH |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2019 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/29/2019 | LEE GUILBEAUX |
| Green Code | Cleared | 6/28/2019 | AARON COSTA |
| Low Impact Development | Cleared | 7/26/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/26/2019 | KAREN LE |
| Specific Plan | Cleared | 7/31/2019 | LUCERITO MARTINEZ |
| Construction near power lines | Cleared | 8/23/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/25/2020 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/11/2021 | Partial Approval | THOMAS FINNILA |
| Piling/Pier/Caisson | 1/11/2021 | Approved | THOMAS FINNILA |
| Structural Steel Frame | 1/11/2021 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 1/13/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 1/19/2021 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 1/25/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/28/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2021 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 7/13/2021 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/15/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 7/15/2021 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 7/15/2021 | Approved | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 7/15/2021 | Partial Approval | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 7/15/2021 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/20/2021 | Approved | THOMAS FINNILA |
| Wood Frame | 7/20/2021 | Approved | THOMAS FINNILA |
| Insulation | 8/9/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 8/9/2021 | Partial Approval | ALAN MORELOS |
| Drywall Nailing | 8/19/2021 | Approved | LILIANA PORTILLO |
| Green Building Rough | 8/19/2021 | Approved | LILIANA PORTILLO |
| Special/Order Compliance | 8/19/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Pre-Inspection | 9/3/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 9/9/2021 | Partial Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/30/2021 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 9/30/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/12/2021 | Approved | THOMAS FINNILA |
| Service/Power Release | 10/12/2021 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 9/27/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/27/2022 | Approved | GREGG CUMMINGS |
| Green Building Final | 9/27/2022 | Approved | GREGG CUMMINGS |
| MERV13>=Final | 9/27/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 9/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 9/27/2022 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 9/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/14/2022 | Approved | JACK KARGODORIAN |
| Final | 11/14/2022 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 11/14/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 11/14/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 11/21/2022 | Approved | ROBERT GOLD |
| Final | 11/21/2022 | Conditional Approval | ROBERT GOLD |
| Final | 12/9/2022 | OK to Issue CofO | JACK KARGODORIAN |